LOADING/UNLOADING PLAN FOR BULK CARRIERS S-06.60.02/Rev.

02/March 1 2016
Voyage No: 013/20 Date: 30/10/2020 Vessel Name: M/V MEGHNA ROSE
Load / Unload Port: Cargo: Assumed stow' factor of cargo: Ballast Pumping Rate: Dock Water density: Max. draught avaiable (HW): Max Air draught in berth:
MINA SAQR CEMENT CLINKER 1.19MT/M3 2 X 500 m3/hr 1.025 18.0 M
To / From: Last Cargo: No. of loaders/Dischages: Load / Dischare Rate: Min Draught Avalable (LW): Max ballasting time avaiable
CHATTOGRAM STONE CHIPS, LIME STONE, SLAG 3 SHORE CRANE 1500MT/HR Meters (by terminal)

Hold No.5 Hold No.4 Hold No.3 Hold No.2 Hold No.1

M/Ton 11900 12000 9000 11000 10100

Grade CEMENT CLINKER CEMENT CLINKER CEMENT CLINKER CEMENT CLINKER CEMENT CLINKER

Total: 54,000 M/Tons

Calculated Values Calculated Values Observed Values


Cargo Time
Pour No: Ballast Operations Comments Draught Maximum Air Draft Draft Draught
Trim
CH No. M/Tons (Hours) Fwd Aft BM/Frame SF/Frame Mid Fwd Aft Mid
ARRIVAL CONDITION 4.30 6.19 66% 36% 5.28 1.89
1 1 5000 GO TST 1 & 3 AND 10 5.83 7.79 83% 39% 6.85 1.96
3 5000 PO WBT 1, 3 & 5
5 5000 STRIPING
2 2 5000 GO TST 2, 4 & 5 AND 10 6.25 10.32 67% 46% 8.36 4.07
4 5000 PO WBT 2 & 4 & APT
5 5000 STRIPING
3 1 5100 PO FPT 10 COMPLETED LOADING # 1 9.87 11.43 36% -36% 10.68 1.56
3 4000 STRIPING COMPLETED LOADING # 3
4 5000
4 2 5000 STRIPING 10 12.12 12.17 -31% -39% 12.15 0.05
4 2000 COMPLETED LOADING # 4
5 1100
REMAINING 1800 MT WILL BE LOADED AFTER INTERMEDIATE DRAFT SURVEY (TREAMING PURPOSE)
5 2 1000 2 COMPLETED LOADING # 2 12.46 12.48 -32% -43% 12.47 0.02
5 800 COMPLETED LOADING # 5
SAILING CONDITION 12.46 12.48 -32% -43% 12.47 0.02

TOTAL 54000.00 Total Quantity (MT)

NO DEVIATION FROM THE ABOBE PLAN WITHOUT PRIOR APPROVAL OF


CHIEF OFFICER. * Bending moments (BM) & Share Forces (SF) are to be expressed as a % of macimum purmittted at-sea values for
Signed
initial & final state. Every step in the loading/unloading plan must repain within allowable limits for full ginder share
Terminal: forces, bending moments and tonnage per hold where applicable.
Abbereviations: PI = Pump In / GI = Gravitate In / F = Full / PO =
Pump Out / GO =Graviate Out / MT = Empty
Signed
Ship:

CAPT. SALAH UDDIN MAHMOOD


NASIM AKTHER RAJ
Prepared by : Chief Officer Verified by: Master