Project Title Construction, Completion, and Maintenance Works of Alijarah Document reference No.: - HSEMS/P19/MEP
Warehouses
Project location Abu Saleel, Wakrah, Qatar Rev -0
Title (job description) JSA FOR INSTALLATION,TESTING AND COMMISSIONING OF Date – 14/12/2023
SEWER AND STROM WATER DRAINAGE SYSTEM AT 14 NOS. OF
ALIJARAH WAREHOUSE.
MATRIX
Please note: If the severity rating lies between 15 and 25, then corrective action shall be taken immediately by the concerned persons with documentary evidence
supporting the same.
Consequence (severity)
Low Minor Moderate Major Catastrophic
(1) (2) (3) (4) (5)
Almost
5 10 15 20 25
(probability)
Certain (5)
Likelihood
4 8 12 16 20
Likely (4)
3 6 9 12 15
Possible (3)
2 4 6 8 10
Unlikely (2)
Rare (1) 1 2 3 4 5
● The activity where practical should cease until safety controls are implemented.
● All risk mitigation factors to be explored and exhausted before proceeding. If the activity is to be continued after
implementing safety controls.
● Communicate the risk to relevant work group members.
Medium ● Take action to reduce the risk to an acceptable level before commencing work.
(8-12)
Low ● further control should be implemented to reduce the risk to as low as reasonably practicable.
● Communicate the risk to relevant work group members. Monitor the risk to ensure that it does not transform to the
(1-6) higher level.
Likely Often occurred within the industry and sometimes occurred with the company in similar condition or situation.
Unlikely Often occurred in other industries but rarely occurred in the construction industry in similar conditions or situations.
Rare Never occurred in the industries or within the company in similar condition or situation.
fall Operator
The watchman (banksman) is necessary with the
Operatives and excavator.
equipment have
Page 15 of 44 Doc no. HSEMS/P19/P01
Page 16 of 44 Doc no. HSEMS/P19/P01
RISK ASSESSMENT
S.L. Risk
Activity Significant Who might be Classificatio (VH, Residual Risk
Element Potential harmed & how n Rating H, (Likelihood x
Hazards (Likelihood M, Control Measures to be Implemented to severity) Action by
x severity) L) reduce the risk
L S Total L S Total
falling risk to the
noise excavation. Make sure excavated soil accumulates away from
the excavation.
Wrong and faulty Hand injury by All the hand tools would be made sure in Foreman
tools. using Damaged good working condition free of creaks,
tools and wrong nails, rust, broken edges and splintered Storekeeper
uses. handles etc.
Pinch point. Damage to the Carry out manual handling training as per AMCC
equipment & training program.
Inadequate property. Foreman
rest breaks. Adopting a correct posture to lift the load.
17
Scaffolding Incompetent Access should be maintained 75˚ (4:1 ratio) Project
work persons. with proper clamped and ensure its proper manager
Erection Untrained person stability.
modification or unauthorized
Slip, trip & fall. persons Ladders should not be hung, always it should be
and Scaffolding
dismantle. performing the job. stable on a solid platform. supervisor
Scaffold failure. Maintain adequate levels of supervision through
3 4 12 2 3 6
erection & dismantle. Safety
Struck by
Unsafe mechanized engineer
All SCAFFOLDERS to be trained and hold
scaffolding equipment. approved scaffold certificates.
platform.
Loss of load. Scaffolding
Proper & safe access should be provided for safe
foreman
working.
21 Project
Work at Fall from height. Fall from height Work at height is a risky job and dangerous, manager
height and get personal before starting the work to provide a handrail
Injury. system to determine anchorage point, safety nets
and safe access. Project
Falling hazards. engineer
Check scaffold tag or elevated platform capacity.
Site engineer
Daily checklist.
needed.
during placement.
pipe.
30483020/30207464. Project
engineer
Condor HSE team –
70425846/77224496