THERMOGRAPHIC REPORT

Client : Total Biah Bintaro


Problem :
IDENTIFICATION
Location : Bintaro
Equipment : Kabel Tufur dari OHB PLN ke KWH mater
PROBLEM DECRIPTION
Fuse pada OHB PLN sering Putus , dengan kapasitas penyambungan 125 A/ 82500 VA
sudah lebih dari kapasitas seharusnya

THERMOGRAM TEMPERATURE MEASUREMENTS


50,5°C

Distance Rate Load Mess Load % Load

MAINTENANCE ACTION TEMPERATURE MEASUREMENTS


Description Repaired by Image date 14 September 2023
Hour 13:41
Target Temperature 42,9 °C
Emisitivy 0,9
Reflected Temp OFF
REPAIR PRIORITY WHEATER 30,4 °C
Subj. Rating Air Temp. Sunny
Temp. Rating 35-40 °C Sky 0 m/s
REINSPECTION Wind Speed -
Reinpection by From
Date °C Mess Load 60% Load

Comments
amper R 139,8 A Beban 93,20 %
S 107,9 A Beban 71,93 %
T 120,9 A Beban 80,60 %

page # 1
THERMOGRAPHIC REPORT
Client : Total Biah Bintaro
Problem :
IDENTIFICATION
Location : Bintaro
Equipment : Tufur dari KWH meter ( Outgoing ) ke panel COS
PROBLEM DECRIPTION
Panas Yng cukup berlebih , pada salah satu Phase R dan S
Penyambungan daya 105 KVA ( 150 A x 230 V )

THERMOGRAM TEMPERATURE MEASUREMENTS


50,5°C

Distance Rate Load Mess Load % Load

MAINTENANCE ACTION TEMPERATURE MEASUREMENTS


Description Repaired by Image date 14 September 2023
Hour 13;41
Target Temperature 52,3 °C
Emisitivy 0,9
Reflected Temp OFF

REPAIR PRIORITY WHEATER


Subj. Rating Air Temp.
Temp. Rating °C Sky
REINSPECTION Wind Speed
Reinpection by From
Date °C Mess Load % Load

Comments
Tegangan Jala jala Normal 223/392 V V drop 3,04 %
225/396 V V drop 2,17 %
224/395 V V drop 2,61 %
Cukup baik
page # 2
THERMOGRAPHIC REPORT
Client : Total Biah Bintaro
Problem :
IDENTIFICATION
Location : Bintaro
Equipment : Tufur PLN dan COS
PROBLEM DECRIPTION

THERMOGRAM TEMPERATURE MEASUREMENTS


50,5°C

Distance Rate Load Mess Load % Load

MAINTENANCE ACTION TEMPERATURE MEASUREMENTS


Description Repaired by Image date 14 September 2023
Hour 13;43
Target Temperature 59 °C
Emisitivy 0,9
Reflected Temp OFF

REPAIR PRIORITY WHEATER


Subj. Rating Air Temp.
Temp. Rating °C Sky
REINSPECTION Wind Speed
Reinpection by From
Date °C Mess Load % Load

Comments

page # 3
THERMOGRAPHIC REPORT
Client : Total Biah Bintaro
Problem : Kabel In -Out KWH
IDENTIFICATION
Location : Bintaro
Equipment : Tufur PLN dan COS
PROBLEM DECRIPTION

THERMOGRAM TEMPERATURE MEASUREMENTS


50,5°C

Incloming
PLN

Outgoung
COS
Distance Rate Load Mess Load % Load

MAINTENANCE ACTION TEMPERATURE MEASUREMENTS


Description Repaired by Image date 14 September 2023
Hour 13;55
Target Temperature 48,6 °C
Emisitivy 0,9
Reflected Temp OFF

REPAIR PRIORITY WHEATER


Subj. Rating Air Temp.
Temp. Rating °C Sky
REINSPECTION Wind Speed
Reinpection by From
Date °C Mess Load % Load

Comments
Tufur PLN temperatur Baik dan Drop Voltage juga baik
Ada masalah pada sisi Outgoing kabel sudah hangat dan tidak Balance

page # 4
THERMOGRAPHIC REPORT
Client : Total Biah Bintaro
Problem : Panel SDB
IDENTIFICATION
Location : Bintaro
Equipment : Tufur PLN dan COS
PROBLEM DECRIPTION

THERMOGRAM TEMPERATURE MEASUREMENTS


50,5°C

Distance Rate Load Mess Load % Load

MAINTENANCE ACTION TEMPERATURE MEASUREMENTS


Description Repaired by Image date 14 September 2023
Hour 13;57
Target Temperature 60,4
Emisitivy 0,9
Reflected Temp OFF

REPAIR PRIORITY WHEATER


Subj. Rating Air Temp.
Temp. Rating °C Sky
REINSPECTION Wind Speed
Reinpection by From
Date °C Mess Load % Load

Comments
Kabel Panel tufur dari COS ke beban sudah hangat perlu ada perubahan soize kabel

page # 5