Professional Documents
Culture Documents
Declaration: By submitting this assessment (Parts 1 – 4) for marking I declare that it is entirely my own work. I understand that falsely claiming that
the work is my own is malpractice and can lead to NEBOSH imposing severe penalties (see the NEBOSH Malpractice Policy for further information).
Important note: You must refer to the document ‘Unit IG2: risk assessment – Guidance and information for learners and Learning Partners’ while
completing all parts of this assessment. Your Learning Partner should provide you with a copy, but it can also be downloaded from the relevant
resources section for this qualification on the NEBOSH website.
Part 1: Background
Shift patterns:
Sites work was proceeded in only one shift for 9:00 am to 4:00 pm. There are 6 working days in
week while Sunday is off for workers and management.
Electricity Operator and workers RCB is installed in main switch 1. Maintenance of all the 1 month HSE officer (3,5)
Use of passing nearby. board. portable electrical equipment
Portable must be carried out
electrical By using faulty, damaged periodically.
equipment or damaged insulated first aid kit and first aider are 2 weeks Site
(Like grinder equipment can be present. Insulated PPEs such 2. Electrical installation must be supervisor(1,2,3)
and hand drill harmful. This harm can as gloves and shoes are checked by competent person.
machine) be induced either while given.
plugging in the socket or
placing foot on the 3. Necessary trainings must be 1 week
damaged insulation of delivered to all workers.
wire. Operators are trained and
certified. 4. Red-scaff tag must be placed 1 day
These circumstances can on damaged or faulty portable
cause cardiac arrest, skin tools.
burn or ultimate death of
worker.
5. Workers must be aware of 1 week
emergency procedure to be
followed in case of emergency
Slips and Workers, supervisors, First aid kit is available. 1. There must be cemented 2 wees HSE Officer (4)
trips HSE Officers and pathway to approach the
slippery Visitors. construction site
surfaces at
construction Because of rain water, 2. Place safety sign related to 1 day Site manager
site due to rain construction site was slip and trip hazard. (1,5)
Lone working Security Guard. Gun is already given to the 1. Cell-phone must be 3 days HSE officer
security guard. provided to security guard (2,3,4)
Security guard As security guard is the so he can contact for help.
at construction only person at
site during construction site during
2. Conduct risk assessment
night. night. 1 week Site manager
that how lone workers can (1)
If anything, unfavourable be harmed.
happen at construction
site during night then it 3. Ask security guard, no to 2 days
can lead toward death of attempt anything that
security guard or stealing cannot be done alone.
or loss of equipment or
property. 4. Educate lone workers not 1 week
to take unnecessary risk.
Manual Workers who were lifting Health Surveillance was 1. Provide trollies to avoid 1 month Site supervisor
Handling concrete blocks and available. manual handling. (2)
cement bags.
Manual Path was cleared. 2. Manual lifting more than 20
handling of Disorder like back pain, 1 day Site manager
kg must not be allowed as
concrete muscle or ligaments pain, (1,5)
Hazardous Workers who are working N/A 1. Limit the activities which are 1 day HSE Officer
Substance at construction site, site producing silica dust when (3)
supervisors, HSE Officer everyone is present at
Construction and visitors. construction site if possible.
dust mainly
produced from construction dust which Site supervisor
silica is producing from silica.
2. These dust particles must 2 days (1,2,4,5)
This dust is hazardous to be settled down on earth
health when either get via sprinkling water over
inhaled or get in contact them
with skin and eyes. 1 week
3. Information related to
Dust can cause eyes disorders of dust must be
irritation, dermatitis, told to workers.
lungs cancer and may
cause infection in 4. Visitors must not be allowed 1 day
Financial Arguments:
It is well acknowledged that if an employer fails to invest in workplace safety, the organisation may
incur significant financial liabilities in the event of an accident. The expenses related to accidents
often exceed the allocated budget for workplace safety. The expenses might be classified as either
direct or indirect. direct costs are normally recovered by insurance costs.
While indirect costs cannot be recovered. The costs that may arise in the event of an accident are
following:
Sick pay
Medical cost
Cost of replacement and maintenance of equipment’s.
Cost of training and hiring new employees.
Lose in reputation
Failure to get future projects.
Specific legal arguments In accordance with ILO Convention C167, it is the employer's responsibility to take all necessary
precautions to protect workers from peril while working at height. ILO conventions,
recommendations, guidance documents, and codes of practise stipulate that worker health and
safety must never be compromised. In addition, this Convention mandates that whenever a scaffold
or scaffolding is used to perform work at height, it must be equally secure and well maintained. The
scaffolding or ladder must comply with national regulations.
Consideration of likelihood AND severity Using the temporary structure of scaffolding platform, exterior wall painting was in progress. During
the execution of tasks at elevated heights, there are potential dangers such as falls involving people
types of injury or ill health or objects. In this particular scenario, the employees who are immediately exposed to these risks
number of workers at risk are those engaged in painting activities, including around 10-12 individuals. Individuals who are in
how often the activity is carried close proximity may also be affected by a falling person or objects from a significant elevation. This
out painting activity will continue until all exterior walls have been painted.
how widespread the risk is As there are no guardrails on the scaffolding platform. Thus, the likelihood of a person falling from a
height is considerable. This incident has the potential to result in significant bodily harm, including
bone fractures and, in extreme cases, death.
Workers who are in close proximity to a hospital may need medical attention, and the severity of
their condition is significant. The level of injury experienced by those operating at elevated heights
is of a catastrophic kind.
In this analysis, I will classify the total intensity of injury, ranging from substantial to catastrophic.
The potential hazard is limited to those engaged in the job at elevated heights, as well as those
working directly underneath them.
How effective the action is likely to be in
On scaffolding platforms, guardrails are used to prevent individuals from falling from a height. When
controlling the risk. This should include:
installed on the temporary platform, the guardrails will reduce the risk of a person falling. This
the intended impact of the action; control contributes to the overall risk reduction because, as the likelihood of a person falling
justification for the timescale that decreases, the risk of severe injuries and mortality also decreases. Three days are allotted for the
you indicated in your risk execution of this control measure. This timeline is provided because the site supervisor will arrange
assessment; and for a qualified scaffolder to be available within the next three days. I do not believe that the risk is
whether you think the action will completely controlled by this control measure. However, it is extremely useful for risk management.
fully control the risk
Specific legal arguments According to ILO Convention C127, the Maximum Weigh Convention, an employer is prohibited
from allowing any employee to physically carry a burden that might be harmful to his health.
According to convention, the employer is required to provide the essential trainings and information
pertaining to the safe management of the load whenever manual carriage of a live load is involved.
According to the convention's provisions, it is obvious that large loads cannot be handled manually
at work, and it is the employer's obligation to take all necessary precautions to prevent manual
handling.
Specific legal arguments According to ILO Convention C148, which relates to air pollution, it is the legal responsibility of the
employer to ensure that the working environment is free from any air pollution-related hazards.
Employers must implement all technical and supplementary control measures on processes and
apparatus for this purpose.
According to the provisions of the ILO convention C148, it is the employer's responsibility to ensure
that the environment or atmosphere is free of any health-threatening hazards.
Consideration of likelihood AND severity At the construction site, there was a lot of dust. These dust particles are made of silica and will be
made by different activities on a building site where silica is used. When workers breathe in or
types of injury or ill health touch these dust particles with their skin or eyes, they will get sick.
number of workers at risk These dust particles are around everyone at the building site. Nearly 8 to 10 workers who work
how often the activity is carried directly with silica are directly exposed to these dust particles. Other workers, such as bosses and
out guests, are also exposed, but not as closely.
how widespread the risk is This dust will stay in the air until these actions are done again. There is a high chance of being
exposed to these dust particles.
These dust particles can irritate your eyes, cause rashes, lead to lung cancer, and make you sick.
For discomfort of the eyes, rashes, and infections of the nasal system, the damage isn't too bad,
but for lung cancer, the damage is very bad.
So, I will rank the damage from small to big.
Dust is everywhere at the building site, so the risk is pretty broad. Almost all of the people who work
at the place are at risk.
How effective the action is likely to be in
At the construction site the dust is floating in the air. Therefore, the risk of exposure to these dust
controlling the risk. This should include:
particles may be reduced by causing them to settle by spraying water over them. The danger of
the intended impact of the action; developing the aforementioned condition decreases dramatically when the quantity of particles is
justification for the timescale that lowered, since less of such particles will be ingested. This preventative intervention is advised to be
you indicated in your risk used for a period of two days. If you need to schedule a water tanker, I believe this amount of time
assessment; and is sufficient. Action risk is not completely mitigated by this control method, however. However, the
whether you think the action will danger has been much diminished.
fully control the risk