Professional Documents
Culture Documents
Declaration: By submitting this assessment (Parts 1 – 4) for marking I declare that it is entirely my own work. I understand that falsely claiming that
the work is my own is malpractice and can lead to NEBOSH imposing severe penalties (see the NEBOSH Malpractice Policy for further information).
Important note: You must refer to the document ‘Unit IG2: risk assessment – Guidance and information for learners and Learning Partners’ while
completing all parts of this assessment. Your Learning Partner should provide you with a copy, but it can also be downloaded from the relevant
resources section for this qualification on the NEBOSH website.
Part 1: Background
Description of the area to be included in the Different area like Excavation area, steel yard, chemical storage area, diesel storage area,
risk assessment carpentry area, and electrical area is covered in the risk assessment.
Any other relevant information The project manager is responsible for health and safety.
* If you’re worried about confidentiality, you can invent a false name and location for your organisation but, all other information provided must be
factual.
Hazard category Who might be harmed What are you already What further controls/actions are Timescales for Responsible
and hazard and how? doing? required? further actions person’s job
to be title
completed
(within …)
1 Working Worker performing the 1) Tag system should be ensured Two week Project
at height work and worker 1) Catching nets are placed for scaffold were the green tag manager
height. below the area. below the slab to support indicates scaffold is fit for the work (Action 4)
workers if they and other hand red implies scaffold
Being involved on A worker's fall from a fall .edges of the slab. is unfit for work.
a scaffold with no scaffold can have
guard rails. serious 2) Ladders with hand rails are 2) Scaffold should be inspected by a One week Site engineer
consequences. It kept at 75-degree angle to competent person and verify it as (Action 2&3)
may lead. Injuries ground and tied to scaffold. safe prior to use.
to the skull, spinal
cord, and other 3) Permit are issued for height 3) Weekly checklist should be
essential sections work activity. provide for work at height activity Two weeks
of the and scaffolds.
2) Electrical Welding pipes without 1) Workers are wearing 1) Provide welding glass for eye Three days Site Engineer
hazard guards can lead to electric adequate PPEs for the work. protection. (Action 1)
shocks and eye injuries.
This also applies to 2) Conducted daily Tool box 2) Provide safety guard for all Two weeks Site Manager
The pipes are cut grinding machines and talk. electric equipment`s (Action 2)
and welded other hot works.
lacking any kind 3) Maintained proper 3) Inspect the all equipment`s before One day HSE Officer
of safe guarding. supervision. the work starts (Action 3)
3) Noise hazard Nearby workers of 1) protecting workers by 1) Eliminate the high noisy One week Site Engineer
compactor roller machine, providing ear muff/ear plug. compactor roller (Action 1)
Noise from roller Site supervisor etc…
compactor 2) Provided adequate intervals 2) Relocate the high noise work in Two weeks Site
machine, It may cause hearing loss. for workers separate area at the site supervisor
Concrete cutting High frequency sound (Action 2)
machines. cause more health issue.
like high blood pressure, 3) Aware of advantages of ear Site
Site
4) Regular noise evaluation required Two weeks supervisor
(Action4)
4) Vibration Machine operators, 1) Provided adequate PPE`s 1) Provide proper safety gears for 4 Months Store
hazard coworkers, and also for the work the workers Manager
supervisors and visitors. (Action 1)
Using of high
vibration Vibration from concrete 2) All staff receive proper 2) Aware of consequences of Two weeks Site
producing crushing and breaking training to utilize vibration Vibration supervisor
machines machines can induce hand-held instruments (Action 2)
vibration, white fingers,
HAVS, nerve 3) Required heath survey Two weeks Project
damage, and joint pain. Manager
(Action 3)
4) Proper inspection and
maintenance need to be done Three months Project
Manager
(Action 4)
5) Manual Workers loading and 1) Periodic rest intervals are 1) Provide load carrying hand One month Plant
handling unloading bulky items, provided trolleys or Lifting trucks Manager
such as ash bags, (Action 1)
Manual handling occasionally employ
injuries can occur uncomfortable postures 2) Provide instruction seasons on Two month
unloading large and inadequate handling manual handling procedures Activity
materials in techniques. Manual supervisor
6) Confined Oxygen deficiency or other 1) Close the open trenches 1) Provided proper PPE`s for the Two weeks Finance
spaces toxic gasses pose a and deep hole suggested work director
serious health danger, (Action1)
Underground potentially leading to 2) Barricade the area
drains and physical and 2) Implement permit work system Two weeks HSE Officer
overhead tanks. biological difficulties 3) Installed warning sign (Action 2)
boards
sewage and Workers may fall in to 3) Continuous Standby person Two weeks Site
pipeline works open spaces used for supervisor
sewage or pipeline (Action 3)
construction.
4) Maintain and follow adequate Two weeks Site
communication with co workers supervisor
(Action4)
10) Health
welfare and
workplace
environment