Unit IG2: Risk assessment

Declaration: By submitting this assessment (Parts 1 – 4) for marking I declare that it is entirely my own work. I understand that falsely claiming that
the work is my own is malpractice and can lead to NEBOSH imposing severe penalties (see the NEBOSH Malpractice Policy for further information).

Important note: You must refer to the document ‘Unit IG2: risk assessment – Guidance and information for learners and Learning Partners’ while
completing all parts of this assessment. Your Learning Partner should provide you with a copy, but it can also be downloaded from the relevant
resources section for this qualification on the NEBOSH website.

Part 1: Background

You should aim to complete this section in 150 - 200 words.


Topic Comments
Name of organisation* Rizwan flour and general mills PVT (Ltd).
Site location* Zangali kohat road Peshawar.
Number of workers 450
Rizwan flour and general mills is a project of Malik. It was found by Malik’s father in 2007. It is one
of the most famous flour mill in Peshawar Pakistan. They are grinding grain into flour and supply
in all cities of KPK. Types of flour milling business the first one is a primary mill where customers
get their grains and have them ground and milled. The second type of flour mill is where you
purchase the raw materials, which is the grains and then grounds them at the mill to sell them
post packaging.
Activities
The activities carried out in flour milling operations including conditioning, cleaning, milling,
General description of the organisation reduction of seeds to flour, and flour dressing and packing in flour plants produce a large quantity
of potentially inhalable dust.
Equipment
Equipment used in flour mills are magnetic selector, pulse dust collector, gravity grading destoner,
vibrating separator, horizontal wheat scourer, purifier, bran finisher, impact detacher, conveyor
and packing machine.
Shift pattern
Rizwan flour mills having two shifts of working day and night, each shifts work for 11 hours and is
off on Friday.
Description of the area to be included in the Description of the area to be included in the risk assessment is packing area, pulse dust

Learner number: 00737007 Learner name: UMER SHABAB Page 1 of 17


risk assessment collector area, vibrating separator area, mechanical workshop and ware house.
Any other relevant information Each area in-charge and HSE officers is responsible for health and safety measurement.
* If you’re worried about confidentiality, you can invent a false name and location for your organisation but, all other information provided must be
factual.

You should aim to complete this section in 100 - 200 words.


Note: this section can be completed after you have competed your risk assessment.
Outline how the risk assessment was Source of information I have consulted International labour organization website to check if there is any
carried out this should include: code of practices related to flour mills which there was.
 sources of information consulted; https://www.ilo.org/dyn/normlex/en/f?p=NORMLEXPUB:13101:0::NO::P13101_COMMENT_ID:2087907
 who you spoke to; and www.hse.govt.uk
 how you identified: After reading the ILO and HSE website, I decided to visit the construction site to see what precautions
- the hazards; had been taken to safeguard the employees from hazards and risks. I spoke with the management and
- what is already being done; and learned the company has a health and safety management system and policy, but they are not
- any additional controls/actions successfully implemented owing to a lack of training and communication. I spoke with the site Workers ,
that may be required. site in-charge and many other staff members to know more about the construction site. I found that the
company prioritises profits and project completion over employee health and safety. During my
inspection and observation, I noticed that most workers were doing manual handling in poor posture
and position, workers were not aware of using one or more equipment together, workers were not much
aware about reporting accident and incident, and work at height activities were being done without
close supervision. I inspect lost time injuries, near misses, medical records, enforcement actions, and
employee complaints. by checking their past records also helped me a lot to identify hazards and risks.

I talked to workers and check PPE which was provided insufficient talking to workers and checking
previous records help me to identified hazard without any controls so I decided to recommend
additional controls that may be required to control present hazard.
https://www.osha.gov/grain-handling
https://www.ukflourmillers.org/healthandsafety

Part 2: Risk Assessment


Organisation name: Rizwan flour and general mills PVT (Ltd).
Date of assessment: 11 July 2023
Scope of risk assessment: Description of the area to be included in the risk assessment is packing area, pulse dust collector area, vibrating
separator area, mechanical workshop and ware house.

Learner number: 00737007 Learner name: UMER SHABAB Page 2 of 17


Hazard Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
category and and how? required? further actions person’s job
hazard to be title
completed
(within …)
Slip and trip Workers working in ware 1) Wet surface was 1) Wet surface should clean and 1 day Sweeper
In ware house house might be harm due barricaded. keep clean.
wet oily to slip and trip hazard. 2) TBT was conducted for 2) Electrical cable should be 1 day Workers
surface and Slip and trip hazard can awareness of removed from walking way and
electrical cause minor injuries such seriousness of slip and place in recommended proper
cables in as sprains and strains. trip hazard. place for avoid trip hazard.
walking way Broken bones due to the 3) Proper lighting was 3) Non-slippery shoes should be 2 days Ware house
was noticed. impact when trying to installed in ware house. provide to all workers to avoid In-charge
break the fall. Back 4) First aid team was slip hazard. 3 and 4
injuries due to the impact present in ware house. 4) All activities should be 1 day
from the fall. 5) PPE was provided such supervise on daily basis.
as shoes and helmet.
Work at Workers working at 1) TBT was conducted. 1) Only authorized workers 2 days HSE officer
height height. 2) Workers are well trained should carry out work at height 1, 3
In mechanical Working without wearing for work at height. activity.
workshop PPE and installing safety 3) PPE was provided. 2) Safety net should install use of 2 days Scaffold team
workers net there is chance of 4) Emergency response PPE should be mandatory for 2 and 4
working at falling object and workers team was present at all workers, nearby area should
height on from height as a result site. be barricade.
scaffold they will be facing serious 5) Proper lighting was 3) Permit to work system and 2 days
without personal injuries broken installed. penalty system should
installing bones head injury implement on not using PPE
safety net and bleeding disability and and working in improper way.
wearing PPE. death. 4) Inspection of scaffold before 2 days
Height is 12 starting work should be
meters supervise.

Learner number: 00737007 Learner name: UMER SHABAB Page 3 of 17


Hazard Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
category and and how? required? further actions person’s job
hazard to be title
completed
(within …)
Hazardous Workers working in pulse 1) Leaked pipe operating 1) Before starting pulse dust 2 days Mechanical
substances dust collector area might was stopped for fixing. collecting machine do check team
In pulse dust be harmed due to dust 2) Lock out and tag out the machine once. 12
collector area particles. was placed on leaked 2) All machinery should be keep 3 days
dust collector Workers will be facing pipe pulse dust collector maintain for long term use. Site in-charge
pipes was irritate eyes, throat and machine. 3) Only authorized workers 2 days 3 and 4
leaked which skin due to dust. Dust 3) Leaked pipe was fixed. should operate machine.
produce heavy may contain microscopic 4) PPE was provided to all 4) Only authorized person should 2 days
dust. solids or liquid droplets workers such as N-95 enter in pulse dust collector
that are small enough to mask. area.
get deep into the lungs 5) Health surveillance of
and cause serious health all workers was done by
problems. Large particles medical team.
may irritate the nose,
throat and eyes.
Loan working Workers involved 1) Manually loading 50kg 1) Forklift hand trolley and hoists 1 week Finance
In ware house individually in manual packages was stopped should be provided in large manager
workers handing might be harm by HSE officer. quantity to avoid manual 1
individually due to manual handling. 2) Health surveillance of handling.
involved in Due to manual handling all workers involved in 2) Manual handling should be 2 days HSE officer
loading truck for long term workers will manual handling was carry out where use of forklift 2 and 3
manually facing work related upper done by medical team. hoist and trolley is not possible
50KG limb disorders, back pain, 3) TBT was conducted. by strong workers.
packages for pain in muscles, hands, 4) Job rotation and 3) All activities should be check 2 days
so long time. legs and fingers. frequent break was on daily basis.
supervised.
5) Individually working was
prohibited.
6) Workers are well
trained.
7) Emergency response

Learner number: 00737007 Learner name: UMER SHABAB Page 4 of 17


Hazard Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
category and and how? required? further actions person’s job
hazard to be title
completed
(within …)
team was present in
ware house.

Vibration Machine operators might 1) Stopped operating 1) Use of PPE should be 1 day
In vibrating be harmed. vibration transmitted mandatory for all workers.
separator area machinery without 2) Job rotation and frequent break 1 day HSE officer
vibrating Vibration is transmitted in wearing gloves. of workers should be 1 2 and 3
separator hands and arms when 2) TBT was conducted for supervise.
operates by operating machinery. awareness of vibration 3) Don’t operate machine by 1 day All staff
operator Excessive exposure can hazard. single operator for long term try workers
without affects the nerves, blood 3) Health surveillance was to change operator. 4
wearing PPE vessels, muscles and supervised. 4) Demonstrate healthy working 2 days
and exposed joints of the hand, wrist 4) PPE was provided to all environment for more
for long term. and arm causing hand- workers. productive work force.
arm vibration syndrome.
Confined Workers working in 1) Working improper way 1) Oxygen level should be record 1 day Site in-charge
space confined space without was stopped between19.5 to 23.5 than start 1234
In pulse dust PPE. immediately. work in confined space.
collector area Working in confined 2) TBT was conducted for 2) SCABA should be use with 1 day HSE manager
workers fixing space is dangerous awareness of confined oxygen cylinder if there is lack 5
big pulse tube because of the risk from space hazard. of oxygen in confined space.
without noxious fumes, reduced 3) Provide training to all 3) Use helmet with torch. 1 day
wearing PPE. oxygen levels, or a risk of workers. 4) Emergency response team and 1 day
fire. 4) Only authorized person receiver team should be
entry in confined space present at the top of confined
was implemented. space.
5) Permit to work system 5) Al activities should be carry out 1 day
was implemented. in the presence of HSE
6) Oxygen level tester and manager.

Learner number: 00737007 Learner name: UMER SHABAB Page 5 of 17


Hazard Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
category and and how? required? further actions person’s job
hazard to be title
completed
(within …)
toxic gas detector was
provided.
7) Air blower was
provided.
8) PPE was provided.
Movement of All workers and visitors 1) Over speeding was 1) Al activities should be check by 2 days HSE officer
people and might be harm due to prohibited and stopped HSE officer on daily basis.
vehicle accident. immediately to avoid
In ware house Certain activity will lead fatality and accident. Risk is Well controlled.
during supply workers and visitors to 2) Walking route and
to customers fatal accident as a result driving route was
over speeding they will facing serious separated.
and wrong personal injuries such as 3) Speed limit was clearly
route driving broken bones head injury defined in TBT and
was noticed. disability and death. penalty system was
implemented on over
speeding and walking
on wrong route for both
drivers and walking
workers.
4) PPE was provided
along with high visible
jacket.
5) Proper lighting was
installed in ware house.
6) Keep distance from
other vehicle.
7) Provided training and
checked license of all
workers.

Learner number: 00737007 Learner name: UMER SHABAB Page 6 of 17


Hazard Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
category and and how? required? further actions person’s job
hazard to be title
completed
(within …)
Electricity Workers working in 1) Damaged electrical wire 1) Damaged wire should be 1 day Electrical
In mechanical electrical workshop. was removed from change and always check team
workshop Due to electrical shock walking way. electrical wire before start 1 and 4
damage workers may be dazed or 2) Damaged parts was using.
electrical wires may experience amnesia, fixed with insulation tap. 2) Don’t place electrical wire and 2 days Workshop In-
was placed in seizure or respiratory 3) TBT was conducted other cables or object in charge
walking way arrest. Long term damage about electricity hazard. walking way to avoid trip 2 3 and 5
was noticed. to the nerves and the 4) Workers are competent hazard.
brain. and trained. 3) Shock-resistance shoes should 3 days
5) Good house-keeping be provide to all workers.
was implemented in 4) Proper lighting should provide
mechanical workshop. in all mechanical workshop. 2 days
5) All activities should be check
daily. 2 days
Manual Workers involved in 1) Manually loading 50kg 1) Forklift hand trolley and hoists 1 week Finance
handling manual handing might be packages was stopped should be provided in large manager
In ware house harm due to manual by HSE officer. quantity to avoid manual 1
workers handling. 2) Health surveillance of handling.
involved in Due to manual handling all workers involved in 2) Manual handling should be 2 days HSE officer
loading truck for long term workers will manual handling was carry out where use of forklift 2 and 3
manually facing work related upper done by medical team. hoist and trolley is not possible
50KG limb disorders, back pain, 3) TBT was conducted. by strong workers.
packages for pain in muscles, hands, 4) Job rotation and 3) All activities should be check 2 days
so long time. legs and fingers. frequent break was on daily basis.
supervised.
5) Individually working was
prohibited.
6) Workers are well
trained.
7) Emergency response
team was present in

Learner number: 00737007 Learner name: UMER SHABAB Page 7 of 17


Hazard Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
category and and how? required? further actions person’s job
hazard to be title
completed
(within …)
ware house.

Noise Packing machine 1) All packing rust full 1) Rust full parts of machinery 2 days Mechanical
In packing operators and nearby noisy machine was should be lubricate while team
area packing workers. stopped for lubricating. lubricating lock out and tag out 1 2 and 3
machine In packing machine area 2) All doors ventilation and system should be implement to
create noise packing machines create windows was kept avoid fatality. HSE officer
due to rust full noise due to rust full parts opened to minimize 2) If rust full parts is damaged 2 days 4 and 5
parts. workers exposed for long noise. change it.
term will lead to hearing 3) Only authorized 3) Acoustical panel should be 3 days
loss, damaged to ear operators operates install to minimize noise.
drums, headache and packing machine. 4) Wearing ear muffs is 1 day
sleeping disorders. 4) TBT was conducted and mandatory.
PPE was provided to all 5) All activities should be check 2 days
workers. on daily basis.
5) Reduction in work time
job rotation and
frequent break was
supervised.
6) Health surveillance of
all workers was done as
per company policy.
Fire Mechanics and nearby 1) Rescue operation was 1) Fuel should be keep in closed 1 day Workshop In-
In mechanical workers working in start immediately. and packed tank and place in charge
workshop mechanical workshop 2) Injured workers shifted proper safe place. 12468
during harmed due to fire. to hospital immediately. 2) Provide separate smoking 1 day
lubricating Due to fire mechanics 3) Area was barricaded for point for smoking. HSE officer
heavy and nearby workers got investigation and record 3) Wrinkle system should be 3 days 7 and 9

Learner number: 00737007 Learner name: UMER SHABAB Page 8 of 17


Hazard Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
category and and how? required? further actions person’s job
hazard to be title
completed
(within …)
machinery injuries of severe burns, to avoid causing fire install when fire cause it will
mechanics head injury due to falling again in future. start falling water automatically Plumber
involved in object, bleeding, 4) Fire extinguisher was to eliminate fire. 3
smoking near unconsciousness and provided. 4) Emergency exit door should be 1 day
fuel which disability. Furtherly 5) Smoking was prohibited keep open all the time for easy Electrical
caused heavy damaged to property and while working. escape in case of fire. team
fire in product. 6) TBT was conducted. 5) Fire alarm system should be 2 days 5
mechanical install in mechanical workshop.
workshop. 6) PPE should be provided to all 2 days
worker.
7) Penalty system should be 1 week
implement on violence.
8) Only authorized and trained 2 days
mechanics should lubricate 2 days
heavy machinery while
lubricating heavy machinery
lock out and tag out system
should be supervise to avoid
fatality.
9) All activities should be 2 days
supervise.

Learner number: 00737007 Learner name: UMER SHABAB Page 9 of 17


Hazard Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
category and and how? required? further actions person’s job
hazard to be title
completed
(within …)

Learner number: 00737007 Learner name: UMER SHABAB Page 10 of 17


Part 3: Prioritise 3 actions with justification for the selection
Suggested word counts
Moral, general legal and financial arguments for all actions: 300 to 350 words
For EACH action:
Specific legal arguments: 100 to 150 words
Likelihood AND severity: 75 to 150 words
How effective the action is likely to be in controlling the risk: 100 to 150 words

Moral, general legal and financial arguments for ALL actions


Moral, general legal and financial Moral argument
arguments
It is morally right to ensure your workers return home safe and health at the end of every working
day. By protecting your workers, you reduce absences, ensuring that your workplace is more
efficient and productive. Research shows that workers are more productive in workplaces that are
committed to health and safety. Rizwan flour mill has morally responsible to provide safe system of
working plate form and risk free environment. It is necessary for company and workers that workers
comes to company for work and go back to home safely.
Legal argument
International labour organization has set out convention C155 and recommendation R164 which
apply to workplace health and safety standards. As a law are made to protect human rights so it
compels the employer to do what he morally should do in order to take reasonable care of
employees. Law define the framework that governs the conduct of business and organization. If
company shows non-compliance with health and safety standards and accidents occurs. It is
mandated by criminal law and any employer who fails to comply is exposed to very significant legal
risks. Both an organizational and individual level. Directors and employees can and do go to prison
for health and safety breaches, and significant fines are handed out.
The employer of Company has Following Legal duties of the ILO R164 article 10 obligations that
the Employer must;

1. (a) Provide & maintain workplace machinery, use work safe working methods which
without risks to health.

Learner number: 00737007 Learner name: UMER SHABAB Page 11 of 17


2. (b) Give necessary training and instructions.
3. (c) Provide supervision, working practice and applications.
4. (d) Provide the organizational arrangements,
5. (e) Provide PPEs and clothing,

Financial argument
As per ice burg model, uninsured cost is 8 to 36 times greater than insured costs. Every accident
has some costs which is direct and indirect cost. Some of these cost may be insured but many
cannot. Accidents and ill health at work are extremely expensive and represent a huge, often
hidden, source of loss. Accidents increase insurance premium. When accident occurs direct costs
will by pay by company is first aid treatment, hospital treatment charges, workers sick pay, and
visible damaged to property equipment and product. While indirect cost is just like invisible that will
be appointing new labour, compensation of injured workers, loss of investigation time, reduction in
staff morale and decreasing number of clients, heavy fines from civil and criminal courts etc.

Justification for action 1


Action (Taken from column 4 of risk Fire
assessment)
Fuel should be keep in closed and packed tank and place in proper safe place
Specific legal arguments As per ILO recommendations R175 fire precaution Article 46,47 affirms that:
(Where necessary to guard against danger, workers should be suitable trained in the action to be
taken in the event of fire, including the use of means of escape)
(Where appropriate suitable visual signs should be provided to indicate clearly the directions of
escape in case of fire)

As per Pakistan factory act 1934 as amended to 1997 article 25. Precautions in case of fire
sub article 5 and 7 affirms that
(In every factory there shall be provided effective and clearly audible means of giving warning in
case of fire to every person employed therein)

Learner number: 00737007 Learner name: UMER SHABAB Page 12 of 17


(In every factory wherein more than ten workers are ordinary employed in any place above the
ground floor, or explosive or highly inflammable materials are use or stored, effective measures
shall be taken to ensure that all the workers are familiar with the means of escape in case of fire
and have been adequately trained in the routine to be followed in such case)
Consideration of likelihood AND severity severity consideration can be classified as:
 types of injury or ill health Severity Categories:
 number of workers at risk 1=Minimum: no physical injury & no property loss.
 how often the activity is carried
2=Medium: Required first aid after accident.
out
 how widespread the risk is 3= Major: in this situation worker face serious injury that should be shifted to hospital/sick leave
required, chance of disability, serious injuries long time hospital treatments requires and also
property loss.
4=Catastrophic: in this situation worker death / chance of permanent disability, un recoverable
property loss. Fatal injuries
LIKELIHOOD 4 CATEGORIES:
1 = Unlikely
2 = Possible
3 = High Likelihood
4 = Very High Likelihood
Consideration of likelihood of causing fire is high In mechanical workshop during lubricating heavy
machinery mechanics involved in smoking near fuel which caused heavy fire in mechanical
workshop.
Severity of being harm due to fire is major Due to fire mechanics and nearby workers got injuries of
severe burns, head injury due to falling object, bleeding, unconsciousness and disability. Furtherly
damaged to property and product.
Types of injury severe burns, head injury due to falling object, bleeding, unconsciousness and
disability
21 workers are at risk.
The activity has been carried out in mechanical workshop workers involved in smoking near fuel

Learner number: 00737007 Learner name: UMER SHABAB Page 13 of 17


tank which cause heavy fire.
The risk is widespread and present for all workers working in mechanical workshop.
How effective the action is likely to be in
The intended impact of the action is fuel should be keep in closed and packed tank and place in
controlling the risk. This should include:
proper safe place. It will eliminate the source of causing fire in mechanical workshop due to
 the intended impact of the action; smoking. Workers will be working in risk free environment.
 justification for the timescale that Justification for timescale I have given is 1 day because it not requires budget allocation it just
you indicated in your risk requires to stop nearby activities and shift fuels tanks from one place to another so it requires one
assessment; and day.
 whether you think the action will
fully control the risk I think the action will fully control the risk of fire.

Justification for action 2


Action (Taken from column 4 of risk Noise
assessment) Rust full parts of machinery should be lubricate while lubricating lock out and tag out system should
be implement to avoid fatality. If rust full parts is damaged change it.
Specific legal arguments According to the ILO C148-working Environment (Air pollution, noise and vibration)
convention, 1977 (no.148) article 3 (b) says (the term noise covers all sound which can result in
hearing impairment or be harmful to health or otherwise dangerous) and article 12 says (the use of
processes, substances, machinery and equipment, to be specified by the competent authority,
which involve exposure of workers to occupational hazards in the working environment due to air
pollution, noise.
According to ILO convention C148 article 4 1. (National laws or regulations shall prescribe that
measure be taken for the prevention and control of, and protection against, occupational hazards in
the working environment due to noise.
Consideration of likelihood AND severity The severity consideration can be classified as:
 types of injury or ill health Severity Categories:
 number of workers at risk 1=Minimum: no physical injury & no property loss.
 how often the activity is carried
2=Medium: Required first aid after accident.
out
 how widespread the risk is 3= Major: in this situation worker face serious injury that should be shifted to hospital/sick leave
required, chance of disability, serious injuries long time hospital treatments requires and also

Learner number: 00737007 Learner name: UMER SHABAB Page 14 of 17


property loss.
4=Catastrophic: in this situation worker death / chance of permanent disability, un recoverable
property loss. Fatal injuries
LIKELIHOOD 4 CATEGORIES:
1 = Unlikely
2 = Possible
3 = High Likelihood
4 = Very High Likelihood

Consideration of likelihood is high In packing area packing machine create noise due to rust full
parts, they work there almost 8 hours so high likelihood due to long term exposure.
Severity of being harm due to noise is Major In packing machine area packing machines create
noise due to rust full parts workers exposed for long term will lead to hearing loss, damaged to ear
drums, headache and sleeping disorders.
Types of ill health hearing loss, damaged to ear drums, headache and sleeping disorders.
70 workers are at risk.
Activity has been carried out in packing area workers exposed to noisy machine for long term might
be harm.
Risk is widespread and present for all workers who exposed to noise and working in packing area.
How effective the action is likely to be in
The intended impact of the action is Rust full parts of machinery should be lubricate while
controlling the risk. This should include:
lubricating lock out and tag out system should be implement to avoid fatality. If rust full parts is
 the intended impact of the action; damaged change it. It will eliminate creating noise.
 justification for the timescale that Justification for the timescale I have given is two days because working in noisy environment is
you indicated in your risk harm full for workers health so stop working and immediately maintaining all machine is necessary
assessment; and so it will take two days to maintain all packing machine.
 whether you think the action will
fully control the risk I think the action will fully control the risk of noise.

Learner number: 00737007 Learner name: UMER SHABAB Page 15 of 17


Justification for action 3
Action (Taken from column 4 of risk Manual handling
assessment)
Forklift hand trolley and hoists should be provided in large quantity to avoid manual handling
Specific legal arguments According ILO convention C127 maximum weight convention 1967, article 3 (No worker shall
be required or permitted to engage in the manual transport of a load which, by reason of its weight,
is likely to jeopardise his health or safety.) And article 6 of C127 states that (In order to limit or to
facilitate the manual transport of loads, suitable technical devices shall be used as much as
possible.) article 5 (Each member shall take appropriate steps to ensure that any worker assigned
to manual transport of loads other than light loads receives, prior to such assignment, adequate
training or instruction in working techniques, with a view to safeguarding health and preventing
accidents)
Consideration of likelihood AND severity See Justification 1 for likelihood and severity.
 types of injury or ill health
 number of workers at risk Consideration of likelihood is high In ware house workers involved in loading truck manually 50KG
 how often the activity is carried packages for so long time. So working almost 8 hours is quite risky so that is why likelihood is high.
out
Severity of being harm due to manual handling is major Due to manual handling for long term
 how widespread the risk is workers will facing work related upper limb disorders, back pain, pain in muscles, hands, legs and
fingers.
35 workers are at risk
Types of ill health work related upper limb disorders, back pain, pain in muscles, hands, legs and
fingers.
Activity has been carried out in ware house workers working manually for long term might be
harmed due to manual handling.
Risk is widespread and present for all those workers who involved in manual handling.
How effective the action is likely to be in
The intended impact of the action is forklift hand trolley and hoists should be provided in large
controlling the risk. This should include:
quantity to avoid manual handling. It will make work easy and eliminate manual handling. Workers
 the intended impact of the action; will be working in risk free environment it will lead workers to more productive workforce.
 justification for the timescale that Justification for timescale have given is q week because it requires meeting and approval on other
you indicated in your risk side purchasing forklift hoists and hand trolley is very important to avoid ill health of workers while
assessment; and

Learner number: 00737007 Learner name: UMER SHABAB Page 16 of 17


 whether you think the action will working. So it requires 1 week.
fully control the risk I think the action will fully control the risk of manual handling.

Part 4: Review, communicate and check


Suggested word counts for each section:
 Planned review date or period and reasoning for this: 50 - 100 words
 How the risk assessment findings will be communicated and who needs to know the information: 100 - 150 words
 Follow up on the risk assessment: 100 - 150 words.
Planned review date/period with Rizwan flour mill has the policy to review risk assessment is 6 months. So the review date of flour
reasoning mill is 11 July 2024. It is recommended date of reviewing risk assessment as per company policy.
The risk assessment will be review before 6 months
In case of occurrence of fatal accident and damaged to property equipment product.
In case of recording too many workers ill health during work absenteeism, turn over.
In case of starting new project appointing new top management.
In case of introducing new technology and changing in company policy of health and safety.
How the risk assessment findings will be The risk assessment findings will be communicated through effective risk communication. I will
communicated AND who you need to tell present my findings in front of top management after getting approval I will conduct TBT and have a
common ground. Before talking about risks. Workers need to understand the basic concept of
safety. Then I will make sure everyone can understand. After that I will talk about present hazard
and how to protect from hazards. After tool box talk I will share my risk assessment findings in
different languages translated and distribute in company workers and share all my risk assessment
findings in company health safety and environment groups.
How you will follow up on the risk For follow up on the risk assessment to check that the action have been carried out I will set a
assessment to check that the actions reminder 4 days before the action. On due date I will talk to HSE officer for each action to find out
have been carried out the progress that the recommended action have been implemented or not. If not I will find out the
reason e.g. is it down to finance or other resource issues such as worker time to complete actions.
If the action not completing due to financial problem on time I will talk to finance manager for
additional fund providing to complete actions on time.

Learner number: 00737007 Learner name: UMER SHABAB Page 17 of 17