Professional Documents
Culture Documents
Annexure C
PPL—QHSE/PR/220
Rev; 01
UI’ELINES FOR
E CAVATION
1.; INTRpDUCTION
Excavation work involves creating a cut, cavity, trench, or depression in the ground by earth
removal-requires-the assurance for the safety of employees, facilities, and the community at large.
Excavation can be carried out:
• By mechanical means (e.g., using excavator I other such equipment)
• By manual means (e.g., digging with shovels, hammering of stakes etc.).
TERM DEFINITION
Method of protection to prevent cave-ins by excavating the sides of an
Benching excavation to form one or series of steps usually with vertical or near vertical
surfaces between levels.
Separation of mass of soil or rock material from the side of an excavation or
~ ave-in. movement
loss of soil into
fromtheunder
excavation
a trenchin shield
quantityor that
supporting
it could system
entrap, and
bury,its injure
suddenor
immobilize a person(s).
. Any man-made cut, cavity, trench or depression in earth surface formed by
Excavation
earth removal is excavation.
An inclined walking surface specifically provided to gain access from one point
Ramp to another and is constructed from earth or from structural members such as
steel or wood.
A narrow excavation (in relation to its length) made below the surface of the
Trench ground. In general, the depth is greater than the width, but the width of a trench
(measured at the bottom) is not greater than 15 feet.
A means of supporting the sides of an excavation to prevent movement of soil
Shoring and cave-ins. There are several types of shoring systems: timber, mechanical,
metal hydraulic, and pneumatic.
Sb ‘, in g A
excavation
method ofaway
protecting
from thepersonnel
excavation.from cave-ins by sloping the sides of an
Stable Rock Natural solid mineral matter that can be excavated with vertical sides and
remain intact while exposed.
Type A Soil Most stable: clay, silty clay, and hardpan (resist penetration). This is cohesive
(Good Soii) soils with an unconfined compressive strength of 1.5 tons per square foot (tsf)
(144 kPa) or greater.
Type B Soil Medium stability: silt, sand loam, medium clay and unstable dry rock. It
(Fairly Good includes cohesive soil with an unconfined compressive strength greater than
Soil) o.s tsf (48 kPa) but less than 1.5 tsf (144 kPa).
QHSE
Annexure C
PPL—QHSEIPR/220
__________________ Rev: 01
Type C Soil Least stable: gravel, loamy sand, soft clay, submerged soil or dense, he~
(Bad Soil) unstable rock. This is cohesive soil with an unconfined compressive strength of
0.5 tsf (48 kPa) or less, granular soils (including gravel, sand, and loamy sand),
_____________ submerged soil or soil from which water is freely seeping.
In addition to responsibilities mentioned in Section 3.0 of PTW procedure, Permit Issuer & receiver
are responsible for following actions regarding safe execution of excavation work.
4. GUIDELINES
The determination of the angle of slope, benches, or the choice and design of other protective
systems shall be based on evaluation of pertinent factors such as:
• Type of soil.
• Depth of cut.
• Possible variations in water content of the material while the excavation is open.
• Anticipated changes in materials from exposure to air, sun, or water.
• Loading imposed structures, equipment, overlying material, or stored material.
• Vibrations from equipment, blasting, traffic, or other sources.
Appended below details regarding maximum allowable slopes are adopted from OSHA:
Soil or Rock Maximum Allowable Slopes (H:V) for Excavations
Type Less Than 6.1 Meters (20 Feet) Deep
TYPE B SOIL
TYPE C SOIL
MIXED SOIL TYPES
20 Maximum
QHSE
Annexure C
PPL—QFISE/PR/220
Rev; 01
Figure 2 Excavations made in Multi-Layer Soil.
-
zli
3)4
(e) Backfilling
I. Backfilling and removal of trench supports shall be accomplished first by backfilling up to a
level allowing for the removal of the lower braces. Another layer of backfill shall be
positioned in the trench to the next layer of braces to be removed.
II. Removal of trench supports shall progress together with the backfill from the bottom of the
trench.
Ill. In unstable soil, ropes shall be used to pull out the jacks or braces from above after
employees have cleared the trench.
IV. All excavations shall be backfilled and consolidated, and the surface shall be left in good
condition as soon as is practicable. For protection of underground electric cables, telephone
lines, etc. appropriate technical procedures shall be consulted, and compliance ensured.
V. For backfilling of Cable trenches, layer by layer compaction is mandatory to achieve proper
compaction.
QHSE
Annexure C
PPL—QHSEIPRI22O
Rev: 01
VI. In case of uncompleted work, excavations should be temporarily fenced with high-visibility
rope or tape with blinking lights.
Snake bite is always a matter of concern and needs to be taken care of.
II. Overhead power lines that may pose a hazard during movement of equipment must also be
clearly indicated and clearances must be maintained.
Ill. Barricades shall be placed to prevent equipment from inadvertently crossing under a line.
IV. It should be ensured that all excavations are supervised by qualified person.
V. Give Toolbox Talks regarding safety measures to be observed to the workers involved
before starting the job.
VI. Warning signs including Light signal to be provided.
VII. If, during excavation, unexpected utilities are discovered, Contractor should stop excavation
and immediately notify the PM and/or Plant Control room. Work shall be resumed only after
obtaining further clearance in consultation with the competent person.
VIII. Hand tool excavation: Whenever the presence of underground pipes, cables, vessels, or
structures is known, or suspected, they shall be exposed by hand tool digging before
mechanical excavators are used. Hand tool excavation is required within 10 feet (3.0
meters) of the object.
IX. Machine excavation: When the location of all utilities or structure have been established by
surface markers or hand tool excavation, machine excavation may commence under close
surveillance of the Contractor’s supervisor.
X. Movement of vehicle and heavy cranes shall be 3 feet (1 meter) away or 1.5 times the depth
of excavation, whichever is greater
Xl. Loose excavated material must be placed no closer than 3 feet from the edge of the
excavations. In any case it shall be outside the excavation barricaded area. Precautions
must be taken to prevent loose excavated material falling into the excavated area.
XII. The disposal area should be defined, made safe for receiving the loose excavated material
and manner of disposal is defined.
XIII. All equipment, electrical connection and machinery used for excavation shall be tested and
validated by the Plant/site electrical department.
XIV. In case of excavation more than 15 feet (4.5 meters), ensure adequate means of
communication and proper ventilation are provided.
XV. Power supply to all electrical equipment/lights should be through ELCB (Tripping at 3OmA
current leakage to earth).
XVI. If there is evidence of cave-ins or slides, all work in the excavation must cease until the
necessary precautions have been taken to safeguard employees.