FACULTY OF ARCHITECTURE,
BUILDING & PLANNING
ABPL90208
CONSTRUCTION MEASUREMENT AND ESTIMATING
Learning Objectives
(1) Extract quantities of building work items from BIM and 2D drawing using take-
off software;
(2) Prepare elemental cost plan / bill of quantities for the building;
(3) Price measured construction work items; and
(4) Prepare a Cost Plan Report for a building.
P a g e 1|8
Assessment 2.1 - COST PLAN (35 marks)
The Scenario
Your client has approached you to do a design development level cost plan and
report. They have a finite funding envelope and therefore value management
proposals need to be provided in case the cost plan is over budget.
The Report
The formal Design Development Cost Plan Report for this project should cover off,
but is not limited to the following sub-headings:
1. Front Cover
2. Contents page
3. Main Content such as (but not limited to):
i. Introduction
ii. Executive Summary
iii. Cost Plan Summary
iv. Issues Identified in the 3D Revit Model (At least 5 issues)
v. Risk Allocation and Mitigation Strategies
vi. Key Assumptions and Exclusions
vii. Value Management Proposals (At least 3)
viii. Appendices
• Cost Plan
• Document Register
• Assignment 2.2
P a g e 2|8
Generally
During the tutorials your tutor will take you through the step-by-step process
involved in preparing the cost plan using Cost X software. You are strongly advised to
attend tutorials as the knowledge developed will help you with your cost planning
assignment. Experience have shown that missing one week of tutorial and
lecture can have a serious impact on a student’s ability to catch up and benefit
from the subject’s learning outcome. The cost plan assignment is due on Friday
20th October 2023 at 11:59 pm.
(1) Soft copy of CostX file - save the file using a combination of (1) your name (2)
student number and (3) course code, in .exf (CostX native file) formats.
Notes on submission:
• CANVAS > Assignment Submission > Assignment 2.1
• All documents including CostX files and PDF report files (including
Assignment 2.2) should be zipped together in one .zip file, due to
CANVAS submission limitation.
CRITERIA MARK
Create the Rate Library for the respective Dimension Groups with the 20%
detailed description for the respective item along with the rate build-
ups
Create the Cost Plan in the Workbook using the coded Dimension 25%
Group with their respective coded Rate Library and presentation
Unit rate build ups in the rate library – consistency & methodology 10%
TOTAL 100%
P a g e 5|8
Note: All assumptions over and above to be documented on the front sheet
under the notes section.