You are on page 1of 64

DIVISION 04 : BRICKWORKS, PATENT STONEF IN FLOOR AND FANCY SCREEN BLOCK WORKS

Item No.- 04.1


Brick work with first class bricks in foundation (1:6)
Considering 100 cft work
1 Bricks 1100 nos @ Tk.
2 Sand (F.M 1.2) in/c wastage 36 cft @ Tk.
3 Cement 4 bags @ Tk.
4 Head mason 0.10 nos @ Tk.
5 Mason 1 no @ Tk.
6 Skilled labour 1 no @ Tk.
7 Ordinary labour 1.5 nos @ Tk.
8 Labour for soaking &
cleaning bricks 2 nos @ Tk.
9 Labour for 7 days curing
@ 1/8 labour per day: 0.875 no @ Tk.
10 Local carriage, sundries, T & P etc.

Add VAT with adjustment factor

Say, Tk.
Item No.- 04.2
Brick work with first class bricks in superstructure (1:6)
Considering 100 cft of work
1 Materials and labour as per item No. 04.1
2 Scaffolding 25 sft @ Tk.
3 Extra labour for carriage 1 no @ Tk.
4 Extra labour for 7 days curing 1/4 no @ Tk.
5 Labour for screening & washing 1 no @ Tk.
Add VAT with adjustment factor

(a) Ground floor

Say, Tk.
Item No.- 04.3
Brickwork with 1st class bricks in superstructure (1:4)
Considering 100 cft of work
1 Bricks 1100 nos @ Tk.
2 Sand (F.M 1.2) in/c wastage 40 cft @ Tk.
3 Cement 6 bags @ Tk.
4 Head mason 0.10 no @ Tk.
5 Mason 1 no @ Tk.
6 Skilled labour 1 no @ Tk.
7 Ordinary labour 2.5 nos @ Tk.
8 Labour for soaking
& cleaning bricks 2 nos @ Tk.
9 Screening and washing sand 1 no @ Tk.
10 Labour for 7 days curing
@ 1/8 labour per day: 0.875 nos @ Tk.

Analysis of PWD SoR 2018 for C


11 Scaffolding 25 sft @ Tk.
12 Local carriage, sundries, T & P etc.

Add VAT with adjustment factor

(a) Ground floor

Say, Tk.

Item No.- 04.4


Exposed brick work in exterior wall in superstructure (1:4) with special quality
(sorted) first class bricks
Considering 100 cft of work
1 Bricks 1100 nos @ Tk.
Extra cost for special quality 1st class bricks
in/c sorting out the bricks @
2 Sand (F.M. 1.2) in/c wastage 40 cft @ Tk.
3 Cement in/c pointing 6.5 bags @ Tk.
4 Head mason 1/2 no @ Tk.
5 Mason 1.5 nos @ Tk.
6 Skilled labour 1.5 nos @ Tk.
7 Ordinary labour 2 nos @ Tk.
8 Labour for soaking &
cleaning bricks 2 nos @ Tk.
9 Labour for screening &
washing sand 1 no @ Tk.
10 Labour for 7 days curing
@ 1/8 labour per day 0.875 nos @ Tk.
11 Scaffolding 25 sft @ Tk.
12 Local carriage, storage & sundries etc.

Add VAT with adjustment factor

(a) Ground floor

Say, Tk.

Item No.- 04.5


Exposed brick work in exterior wall in superstructure (1:4) with automatic machine
made first class bricks
Considering 100 cft of work
1 Bricks 1100 nos @ Tk.
2 Sand (F.M. 1.2) in/c wastage 40 cft @ Tk.
3 Cement in/c pointing 6.5 bags @ Tk.
4 Head mason 1/2 no @ Tk.
5 Mason 1.5 nos @ Tk.
6 Skilled labour 1.5 nos @ Tk.
7 Ordinary labour 2 nos @ Tk.
8 Labour for soaking &
cleaning bricks 2 nos @ Tk.
9 Labour for screening &
washing sand 1 no @ Tk.
10 Labour for 7 days curing
@ 1/8 labour per day 0.875 nos @ Tk.

Analysis of PWD SoR 2018 for C


11 Scaffolding 25 sft @ Tk.
12 Local carriage, storage & sundries etc.

Add VAT with adjustment factor

(a) Ground floor

Say, Tk.
Item No.- 04.6
Brick work with 10 holes machine made bricks (1:4)
Considering 100 cft work
1 Bricks 1100 nos @ Tk.
2 Sand (F.M 1.2) in/c wastage 40 cft @ Tk.
3 Cement 6.5 bags @ Tk.
4 Head mason 0.50 nos @ Tk.
5 Mason 1.5 nos @ Tk.
6 Skilled labour 1.5 nos @ Tk.
7 Ordinary labour 2 nos @ Tk.
8 Labour for soaking &
cleaning bricks 2 nos @ Tk.
9 Labour for screening and
washing sand 1.00 no @ Tk.
10 Labour for 7 days curing
@ 1/8 labour per day: 0.875 nos @ Tk.
11 Scaffolding 25 sft @ Tk.
12 Local carriage, sundries, T & P etc.
Add VAT with adjustment factor

(a) Ground floor

Say, Tk.
Item No.- 04.7
Brick work with 9.5" x 4.5" x 2.75" size machine made solid klinker facing bricks (1:4)
Considering 100 cft work
1 Bricks 1100 nos @ Tk.
2 Sand (F.M 1.2) in/c wastage 40.0 cft @ Tk.
3 Cement 6.5 bags @ Tk.
4 Head mason 0.25 nos @ Tk.
5 Mason 2.0 nos @ Tk.
6 Skilled labour 1.5 nos @ Tk.
7 Ordinary labour 2.0 nos @ Tk.
8 Labour for soaking
& cleaning bricks 1.0 no @ Tk.
9 Labour for screening and
washing sand 1/2 no @ Tk.
10 Labour for 7 days curing
@ 1/4 labour per day: 1.75 nos @ Tk.
11 Scaffolding 25 sft @ Tk.
12 Local carriage, sundries, T & P etc.

Analysis 115
Overhead 3.50% =
Total =
Add VAT w1.06383 6.00% =
Grand Tot=
(a) Ground floor Rate per c=
Rate per =
Say, Tk. 9,286 .00 per cum
Item No.- 04.8
Brick work with 9.5" x 4.5" x 2.75" size 10 hole machine made rock-face/textured klinker
facing bricks (1:4)
Considering 100 cft work
1 Bricks 1100 nos @ Tk.
2 Sand (F.M 1.2) in/c wastage 40 cft @ Tk.
3 Cement 6.5 bags @ Tk.
4 Head mason 0.25 nos @ Tk.
5 Mason 2 nos @ Tk.
6 Skilled labour 1.5 nos @ Tk.
7 Ordinary labour 2.0 nos @ Tk.
8 Labour for soaking &
cleaning bricks 1 no @ Tk.
9 Screening and washing sand 1/2 no @ Tk.
10 Labour for 7 days curing
@ 1/8 labour per day: 0.875 nos @ Tk.
11 Scaffolding 25 sft @ Tk.
12 Local carriage, sundries, T & P etc.

Add VAT with adjustment factor

(a) Ground floor

Say, Tk.

Item No.- 04.9


Brick work with 9.5" x 4.5" x 2.75" size 3 hole machine made reinforced
klinker facing bricks (1:4)
Considering 100 cft work
1 Bricks 1100 nos @ Tk.
Sand (F.M 2.2) in/c wastage 24 cft @ Tk.
2 Sand (F.M 1.2) in/c wastage 40 cft @ Tk.
3 Cement 6.5 bags @ Tk.
4 Head mason 0.25 nos @ Tk.
5 Mason 2 nos @ Tk.
6 Skilled labour 1.5 nos @ Tk.
7 Ordinary labour 2 nos @ Tk.
8 Labour for soaking
& cleaning bricks 1 no @ Tk.
9 Screening and washing sand 1/2 no @ Tk.
10 Labour for 7 days curing
@ 1/8 labour per day: 0.875 no @ Tk.
11 Scaffolding 25 sft @ Tk.
12 Local carriage, sundries, T & P etc.

Add VAT with adjustment factor

Analysis of PWD SoR 2018 for C 116


Grand Tot=
(a) Ground floor Rate per c=
Rate per =
Say, Tk. 13,380 .00 per cum
Item No.- 04.10
Extra rate for each additional floor for brick works (items nos- 4.2 to 4.9)
04.10.1 Add for each addl. floor up to 5th floor (@ 1.25 nosper cum =
04.10.2 Add for each addl. floor for 6th floor to 9th floor (@ per cum =
04.10.3 Add for each addl. floor for 10th floor and above (@per cum =

Item No.- 04.11


Extra rate (for per meter increase of height) over the rate of item No.- 4.2 to 4.9 where free
height of the structure exceeds 4 meter.
Considering 100 cft of work
1 Extra head mason 0.05 no @ Tk.
2 Extra mason 0.2 no @ Tk.
3 Extra skilled labour 0.1 no @ Tk.
4 Extra ordinary labour 0.3 no @ Tk.
5 Extra for scaffolding 12.5 sft @ Tk.
6 Extra for local carriage, storage & sundries etc.
Add VAT with adjustment factor

Say, Tk.

Item No.- 04.12


Facing brick work with 200 x 100 x 50 mm machine made hard pressed klinker
facing bricks (1:4) with out side pointing.
Considering 100 sft of work
1 200 x 100 x 50 mm facing bricks (facing 200 x 100 mm)
in/c 5% wastage 452 nos @ Tk.
2 Sand (F.M. 1.2) in/c wastage 12 cft @ Tk.
3 Cement in/c for pointing 2.26 bags @ Tk.
4 Head mason 1 no @ Tk.
5 Mason 2.25 nos @ Tk.
6 Skilled labour 1.5 nos @ Tk.
7 Ordinary labour 1.5 nos @ Tk.
8 Labour for 7 days curing
@ 1/8 labour per day 0.875 no @ Tk.
9 Scaffolding 25 sft @ Tk.
10 Washing of sand, local carriage, storage & sundries etc.

Add VAT with adjustment factor

(i) Ground floor

Say, Tk.

Analysis 117

Item No.- 04.13


Facing brick work with 200 x 50 x 50 mm machine made klinker facing
strips (1:4) with outside pointing.
Considering 100 sft of work
1 200 x 50 x 50 mm facing bricks (facing 200 x 50 mm)
in/c 5% wastage 856 nos @ Tk. 16,000.00 per % 0 nos
2 Sand (F.M. 1.2) in/c wastage 14 cft @ Tk. 1,400.00
3 Cement in/c for pointing 2.75 bags @ Tk. 395.00
4 Head mason 1 no @ Tk. 600.00
5 Mason 2 1/3 nos @ Tk. 500.00
6 Skilled labour 1.5 nos @ Tk. 390.00
7 Ordinary labour 1.5 nos @ Tk. 320.00
8 Labour for 7 days curing
@ 1/8 labour per day 0.875 no @ Tk. 320.00
9 Scaffolding 25 sft @ Tk. 9.00
10 Washing of sand, local carriage, storage &

Profit
Overhead

Add VAT with adjus 1.06383

(i) Ground floor

Say, Tk. 2,401

Item No.- 04.14.1


Facing brick work with 200 x 62 x 16.51 mm clay wall tile (red strip) with 1:4 mortar with
out side pointing.
Considering 100 sft of work
1 200 x 62 x 16.51 mm machine made clay wall tile
facing red strips (facing 200 x 62 mm)
in/c 5% wastage 704 nos @ Tk. 18,500.00 per % 0 nos
2 Sand (F.M. 1.2) in/c wastage 14 cft @ Tk. 1,400.00
3 Cement in/c for pointing 2.75 bags @ Tk. 395.00
4 Head mason 1 no @ Tk. 600.00
5 Mason 2 nos @ Tk. 500.00
6 Skilled labour 1.5 nos @ Tk. 390.00
7 Ordinary labour 1.5 nos @ Tk. 320.00
8 Labour for 7 days curing
@ 1/8 labour per day 0.875 no @ Tk. 320.00
9 Scaffolding 25 sft @ Tk. 9.00
10 Washing of sand, local carriage, storage & sundries etc.

Profit
Overhead

Add VAT with adjus 1.06383

(i) Ground floor

Say, Tk. 2,313

Item No.- 04.14.2


Facing brick work with 200 x 62 x 12.7 mm clay wall tile (beige strip) with 1:4 mortar with
out side pointing.
Considering 100 sft of work
1 200 x 62 x 12.7 mm machine made clay wall tile
facing beige strips (facing 200 x 62 mm)
in/c 5% wastage 704 nos @ Tk. 21,000.00 p

Analysis of PWD So 118


2 Sand (F.M. 1.2) in/c wastage 14 cft @ Tk. 1,400.00
3 Cement in/c for pointing 2.75 bags @ Tk. 395.00
4 Head mason 1 no @ Tk. 600.00
5 Mason 2 nos @ Tk. 500.00
6 Skilled labour 1.5 nos @ Tk. 390.00
7 Ordinary labour 1.5 nos @ Tk. 320.00
8 Labour for 7 days curing
@ 1/8 labour per day 0.875 no @ Tk. 320.00
9 Scaffolding 25 sft @ Tk. 9.00
10 Washing of sand, local carriage, storage & sundries etc.

Profit
Overhead

Add VAT with adjus 1.06383


(i) Ground floor

Say, Tk. 2,542

Item No.- 04.14.3


Facing brick work with 200 x 62 x 8.9 mm clay wall tile (red strip) with 1:4 mortar with
out side pointing.
Considering 100 sft of work
1 200 x 62 x 8.9 mm machine made clay wall tile
facing red strips (facing 200 x 62 mm)
in/c 5% wastage 704 nos @ Tk. 16,400.00 per % 0 nos
2 Sand (F.M. 1.2) in/c wastage 14 cft @ Tk. 1,400.00
3 Cement in/c for pointing 2.75 bags @ Tk. 395.00
4 Head mason 1 no @ Tk. 600.00
5 Mason 2 nos @ Tk. 500.00
6 Skilled labour 1.5 nos @ Tk. 390.00
7 Ordinary labour 1.5 nos @ Tk. 320.00
8 Labour for 7 days curing
@ 1/8 labour per day 0.875 no @ Tk. 320.00
9 Scaffolding 25 sft @ Tk. 9.00
10 Washing of sand, local carriage, storage & sundries etc.

Profit
Overhead

Add VAT with adjus 1.06383

(i) Ground floor

Say, Tk. 2,121

Item No.- 04.14.4


Facing brick work with 241 x 70 x 12.7 mm clay wall tile (red strip) with 1:4 mortar with
out side pointing.
Considering 100 sft of work
1 241 x 70 x 12.7 mm machine made clay wall tile
facing red strips (facing 241 x 70 mm)
in/c 5% wastage 540 nos @ Tk. 28,000.00 per % 0 nos
2 Sand (F.M. 1.2) in/c wastage 14 cft @ Tk. 1,400.00
3 Cement in/c for pointing 2.75 bags @ Tk. 395.00
4 Head mason 1 no @ Tk. 600.00
5 Mason 2 nos @ Tk. 500.00
6 Skilled labour 1.5 nos @ Tk. 390.00
7 Ordinary labour 1.5 nos @ Tk. 320.00

Analysis of PWD So 119


8 Labour for 7 days curing
@ 1/8 labour per day 0.875 no @ Tk. 320.00
9 Scaffolding 25 sft @ Tk. 9.00
10 Washing of sand, local carriage, storage & sundries etc.

Profit
Overhead

Add VAT with adjus 1.06383

(i) Ground floor

Say, Tk. 2,585

Item No.- 04.14.5


Facing brick work with 242 x 70 x 12.7 mm clay wall tile (matt glazed textured) with 1:4 mortar with
out side pointing.
Considering 100 sft of work
1 242 x 70 x 12.7 mm machine made clay wall tile
facing matt glazed textured strips (facing 242 x 70 mm)
in/c 5% wastage 540 nos @ Tk.
2 Sand (F.M. 1.2) in/c wastage 14 cft @ Tk.
3 Cement in/c for pointing 2.75 bags @ Tk.
4 Head mason 1 no @ Tk.
5 Mason 2 nos @ Tk.
6 Skilled labour 1.5 nos @ Tk.
7 Ordinary labour 1.5 nos @ Tk.
8 Labour for 7 days curing
@ 1/8 labour per day 0.875 no @ Tk.
9 Scaffolding 25 sft @ Tk.
10 Washing of sand, local carriage, storage & sundries etc.

Add VAT with adjustment factor

(i) Ground floor

Say, Tk.
Item No.- 04.15
125 mm brick work with first class bricks (1:6) in superstructure
Considering 100 sft work
1 Bricks 480 nos @ Tk.
2 Sand (F.M. 1.2) 18 cft @ Tk.
3 Cement 1.75 bags @ Tk.
4 Head mason 0.1 no @ Tk.
5 Mason 3/4 no @ Tk.
6 Skilled labour 1/2 no @ Tk.
7 Ordinary labour 1/2 no @ Tk.
8 Labour for soaking &
cleaning bricks 1 no @ Tk.
9 Labour for screening &
washing sand 1/2 no @ Tk.
10 Labour for 7 days curing
@ 1/8 No. labour per day 0.875 no @ Tk.
11 Scaffolding 25 sft @ Tk.
12 Local carriage, storage & sundries etc.

Analysis of PWD SoR 2018 for C

Add VAT with adjustment factor

(i) Ground floor


Say, Tk.
Item No.- 04.16
125 mm brick work with first class bricks (1:4) in superstructure
Considering 100 sft work
1 Bricks 480 nos @ Tk.
2 Sand (F.M. 1.2) 17 cft @ Tk.
3 Cement 2.6 bags @ Tk.
4 Head mason 0.1 no @ Tk.
5 Mason 3/4 no @ Tk.
6 Skilled labour 1/2 no @ Tk.
7 Ordinary labour 1/2 no @ Tk.
8 Labour for soaking &
cleaning bricks 1 no @ Tk.
9 Labour for screening &
washing sand 1/4 no @ Tk.
10 Labour for 7 days curing
@ 1/8 No. labour per day 0.875 no @ Tk.
11 Scaffolding 25 sft @ Tk.
12 Local carriage, storage & sundries etc.

Add VAT with adjustment factor

(i) Ground floor

Say, Tk.
Item No.- 04.17
Exposed 125 mm pointing extra ordinary ornamental brick work (1:4)
Considering 100 sft of work
1 Bricks 480 nos @ Tk.
Extra cost for special quality 1st class bricks
in/c sorting out the bricks @
2 Sand (F.M. 1.2) in/c wastage 23 cft @ Tk.
3 Cement in/c pointing 3 bags @ Tk.
4 Head mason 0.10 no @ Tk.
5 Mason 1 no @ Tk.
6 Skilled labour 0.5 no @ Tk.
7 Ordinary labour 0.5 no @ Tk.
8 Labour for soaking &
cleaning bricks 1 no @ Tk.
9 Labour for screening &
washing sand 0.25 no @ Tk.
10 Labour for 7 days curing
@ 1/4 labour per day 1.75 nos @ Tk.
11 Scaffolding and stageing 25 sft @ Tk.
12 Local carriage, storage & sundries etc.

Analysis 121
Profit 10.00%
Overhead 3.50%
Total
Add VAT with adjus1.06383 6.00%
Grand Total
(a) Ground floor Rate per sft
Rate per sqm
Say, Tk. 1,155 .00 per sqm

Item No.- 04.18


Exposed 125 mm pointing extra ordinary ornamental brick work (1:4)
with automatic machine made 1st classs bricks
Considering 100 sft of work
1 Bricks 480 nos @ Tk.
2 Sand (F.M. 1.2) in/c wastage 23 cft @ Tk.
3 Cement in/c pointing 3 bags @ Tk.
4 Head mason 0.10 no @ Tk.
5 Mason 1 no @ Tk.
6 Skilled labour 0.5 no @ Tk.
7 Ordinary labour 0.5 no @ Tk.
8 Labour for soaking &
cleaning bricks 1 no @ Tk.
9 Labour for screening &
washing sand 0.25 no @ Tk.
10 Labour for 7 days curing
@ 1/4 labour per day 1.75 nos @ Tk.
11 Scaffolding and stageing 25 sft @ Tk.
12 Local carriage, storage & sundries etc.

Add VAT with adjustment factor

(a) Ground floor

Say, Tk.
Item No.- 04.19
125 mm brick work with 10 hole machine made ceramic bricks (1:4) in
Considering 100 sft work
1 Bricks 480 nos @ Tk. 18,900.00 per % 0 nos
2 Sand (F.M. 1.2) 18 cft @ Tk.
3 Cement 2.8 bags @ Tk.
4 Head mason 0.1 no @ Tk.
5 Mason 1 no @ Tk.
6 Skilled labour 1/2 no @ Tk.
7 Ordinary labour 1 no @ Tk.
8 Labour for soaking &
cleaning bricks 1 no @ Tk.
9 Labour for screening &
washing sand 1/4 no @ Tk.
10 Labour for 7 days curing
@ 1/8 No. labour per day 0.875 nos @ Tk.
11 Scaffolding 25 sft @ Tk.
12 Local carriage, storage & sundries etc.

Analysis of PWD So 122


Add VAT with adjustment factor

(i) Ground floor

Say, Tk.
Item No.- 04.20.1
Fancy screen work in wall with 4.5'' x 4.5'' x 4.5'' design block in all floors (1:3).
Considering 100 sft of work
A. Materials:
1 4.5" x 4.5" x 4.5" design
block in/c wastage 945 nos @ Tk.
2 Sand (F.M. 1.2) 3.75 cft @ Tk.
3 Cement 1 bag @ Tk.
4 Colour pigment 1 Ib @ Tk.
B. Labour:
1 Head mason 1 1/4 no @ Tk.
2 Mason 2.75 no @ Tk.
3 Skilled labour 2.5 no @ Tk.
4 Ordinary labour 1 no @ Tk.
5 Labour for soaking &
cleaning blocks. 1 no @ Tk.
6 Labour for 7 days curing
@ 1/8 No. labour per day 0.875 no @ Tk.
7 Scaffolding 25 sft @ Tk.
8 Washing of sand, local carriage & storage

Add VAT with adjustment factor

(i) Ground floor

Say, Tk.
Item No.- 04.20.2
Fancy screen work in wall with 5.5'' x 5.5'' x 4'' design block in all floors (1:3) facing 5.5" x 4"
Considering 100 sft of work
A. Materials:
1 5.5" x 5.5" x 4" design
block in/c wastage 510 nos @ Tk.
2 Sand (F.M. 1.2) 3.75 cft @ Tk.
3 Cement 1 bag @ Tk.
4 Colour pigment 1 Ib @ Tk.
B. Labour:
1 Head mason 1.25 nos @ Tk.
2 Mason 2.75 nos @ Tk.
3 Skilled labour 2.5 nos @ Tk.
4 Ordinary labour 1 no @ Tk.
5 Labour for soaking & .
cleaning blocks 0.50 no @ Tk.
6 Labour for 7 days curing
@ 1/8 No. labour per day 0.875 no @ Tk.
7 Scaffolding 25 sft @ Tk.
8 Washing of sand, local carriage & storage etc.

Analysis of PWD SoR 2018 for C

Add VAT with adjustment factor

(i) Ground floor

Say, Tk.
Item No.- 04.20.3
Fancy Screen work with 6'' x 6'' x 4" or 6'' x 6'' x 4.5'' design block in all floors (1:3)
Considering 100 sft of work
A. Materials:
1 6" x 6" x 4" or 6" x 6" x 4" design
block in/c wastage 420 nos @ Tk.
2 Sand (F.M. 1.2) 3.75 cft @ Tk.
3 Cement 1 bag @ Tk.
4 Colour pigment 1 Ib @ Tk.
B. Labour:
1 Head mason 1.25 nos @ Tk.
2 Mason 2.75 nos @ Tk.
3 Skilled labour 2.5 nos @ Tk.
4 Ordinary labour 1 no @ Tk.
5 Labour for soaking &
cleaning blocks. 0.50 no @ Tk.
6 Labour for 7 days curing
@ 1/8 No. labour per day 0.875 no @ Tk.
7 Scaffolding 25 sft @ Tk.
8 Washing of sand, local carriage & storage etc.

Add VAT with adjustment factor

(i) Ground floor

Say, Tk.
Item No.- 04.20.4
Fancy Screen work with 8'' x 8'' x 4.25'' design block
Considering 100 sft of work
A. Materials:
1 8" x 8" x 4.25" design
block in/c wastage 235 nos @ Tk.
2 Sand (F.M. 1.2) 2 cft @ Tk.
3 Cement 0.5 bag @ Tk.
4 Colour pigment 0.5 Ib @ Tk.
B. Labour:
1 Head mason 1 no @ Tk.
2 Mason 2 nos @ Tk.
3 Skilled labour 2.5 nos @ Tk.
4 Ordinary labour 1 no @ Tk.
5 Labour for soaking &
cleaning blocks. 0.50 no @ Tk.
6 Labour for 7 days curing
@ 1/8 No. labour per day 0.875 no @ Tk.
7 Scaffolding 25 sft @ Tk.
8 Washing of sand, local carriage & storage etc.

Analysis of PWD SoR 2018 for C

Add VAT with adjustment factor

(i) Ground floor

Say, Tk.
Item No.- 04.20.5
Fancy Screen work with 8'' x 4.75'' x 4'' design block in all floors (1:3)
Considering 100 sft of work
A. Materials:
1 8'' x 4.75'' x 4'' design
block in/c wastage 270 nos @ Tk.
2 Sand (F.M. 1.2) 2 cft @ Tk.
3 Cement 0.5 bag @ Tk.
4 Colour pigment 0.5 Ib @ Tk.
B. Labour:
1 Head mason 1 no @ Tk.
2 Mason 2 nos @ Tk.
3 Skilled labour 2.5 nos @ Tk.
4 Ordinary labour 1 no @ Tk.
5 Labour for soaking &
cleaning blocks. 0.50 no @ Tk.
6 Labour for 7 days curing
@ 1/8 No. labour per day 0.875 no @ Tk.
7 Scaffolding 25 sft @ Tk.
8 Washing of sand, local carriage & storage etc.

Add VAT with adjustment factor


(i) Ground floor

Say, Tk.
Item No.- 04.20.6
Fancy Screen work with 6'' x 6'' x 6''design block in all floors (1:3)
Considering 100 sft of work
A. Materials:
1 6" x 6" x 6" design
block in/c wastage 420 nos @ Tk.
2 Sand (F.M. 1.2) 3.75 cft @ Tk.
3 Cement 1 bag @ Tk.
4 Colour pigment 1 Ib @ Tk.
B. Labour:
1 Head mason 1.25 nos @ Tk.
2 Mason 2.75 nos @ Tk.
3 Skilled labour 2.5 nos @ Tk.
4 Ordinary labour 1 no @ Tk.
5 Labour for soaking &
cleaning blocks. 0.50 no @ Tk.
6 Labour for 7 days curing
@ 1/8 No. labour per day 0.875 no @ Tk.
7 Scaffolding 25 sft @ Tk.
8 Washing of sand, local carriage & storage etc.

Analysis of PWD SoR 2018 for C

Add VAT with adjustment factor

(i) Ground floor

Say, Tk.
Item No.- 04.20.7
Fancy Screen work with 9.5'' x 4.5'' x 2.75'' design block in all floors (1:3)
Considering 100 sft of work
A. Materials:
1 9.5'' x 4.5'' x 2.75'' design
block in/c wastage 300 nos @ Tk.
2 Sand (F.M. 1.2) 3.75 cft @ Tk.
3 Cement 1 bag @ Tk.
4 Colour pigment 1 Ib @ Tk.
B. Labour:
1 Head mason 1.25 nos @ Tk.
2 Mason 2.75 nos @ Tk.
3 Skilled labour 2.5 nos @ Tk.
4 Ordinary labour 1 no @ Tk.
5 Labour for soaking &
cleaning blocks. 0.50 no @ Tk.
6 Labour for 7 days curing
@ 1/8 No. labour per day 0.875 nos @ Tk.
7 Scaffolding 25 sft @ Tk.
8 Washing of sand, local carriage & storage etc.

Add VAT with adjustment factor

(i) Ground floor

Say, Tk.
Item No.- 04.21
Extra rate for each additional floor for brick and screen block work (Item nos- 4.12 to 4.20)
04.21.1 Add for each addl. floor up to 5th floor (@ 0.75 No. lab per % sft)
04.21.2 Add for each addl. floor for 6th floor to 9th floor (@ 1 No. lab per % sft)
04.21.3 Add for each addl. floor 10th floor and above (@ 1.25 nos lab per % sft)
Item No.- 04.22.1
100 mm thick flat brick pavement with 200 x 100 x 50 mm klinker paving bricks (1:4)
Considering 100 sft of work
A. Materials:
1 200 x 100 x 50 mm klinker paving
bricks (facing 200 x 50 mm)
in/c 5% wastage 856 nos @ Tk.
2 Sand (F.M. 1.2) 16 cft @ Tk.
3 Cement (in/c for flush pointing) 3.25 bags @ Tk.
B. Labour:
1 Head mason 1/4 no @ Tk.
2 Mason 1.5 nos @ Tk.
3 Skilled labour 3 nos @ Tk.
4 Ordinary labour 1.5 nos @ Tk.
5 Labour for soaking &
cleaning bricks 1 no @ Tk.

Analysis of PWD SoR 2018 for C


6 Labour for 7 days curing
@ 1/8 labour per day. 0.875 no @ Tk.
7 Local carriage & storage, sundries etc.

Add VAT with adjustment factor

Say, Tk.
Item No.- 04.22.2
50 mm thick brick on edge pavement with 200 x 100 x 50 mm klinker
Considering 100 sft of work
A. Materials:
1 200 x 100 x 50 mm klinker paving
bricks (facing 200 x 100 mm)
in/c 5% wastage 452 nos @ Tk.
2 Sand (F.M. 1.2) 13 cft @ Tk.
3 Cement (in/c for flush pointing) 2.5 bags @ Tk.
B. Labour:
1 Head mason 1/4 no @ Tk.
2 Mason 1 nos @ Tk.
3 Skilled labour 2.5 nos @ Tk.
4 Ordinary labour 1.5 nos @ Tk.
5 Labour for soaking &
cleaning bricks 0.50 no @ Tk.
6 Labour for 7 days curing
@ 1/8 labour per day. 0.875 no @ Tk.
7 Local carriage & storage, sundries etc.

Add VAT with adjustment factor

Say, Tk.

Item No.- 04.22.3


50 mm thick flat brick pavement with 200 x 50 x 50 mm klinker paving bricks (1:4)
facing 200 mm x 50 mm
Considering 100 sft of work
A. Materials:
1 200 x 50 x 50 mm klinker paving
bricks (facing 200 x 50 mm)
in/c 5% wastage 856 nos @ Tk.
2 Sand (F.M. 1.2) 10 cft @ Tk.
3 Cement (in/c for flush pointing) 2.5 bags @ Tk.
B. Labour:
1 Head mason 1/4 no @ Tk.
2 Mason 1.25 nos @ Tk.
3 Skilled labour 2.5 nos @ Tk.
4 Ordinary labour 1.5 nos @ Tk.
5 Labour for soaking &
cleaning bricks 1 no @ Tk.
6 Labour for 7 days curing

Analysis of PWD SoR 2018 for C


'@ 1/8 labour per day. 0.875 no @ Tk.
7 Local carriage & storage, sundries etc.
Add VAT with adjustment factor

Say, Tk.
Item No.- 04.23
125 mm thick brick pavement with 1st class bricks (1:4)
Considering 100 sft work
A. Materials:
1 1st class bricks in/c wastage 480 nos @ Tk.
2 Sand (F.M. 1.2) 15 cft @ Tk.
3 Cement (in/c for flush pointing) 3 bags @ Tk.
B. Labour:
1 Head mason 1/4 no @ Tk.
2 Mason 1.25 nos @ Tk.
3 Skilled labour 2.25 nos @ Tk.
4 Ordinary labour 1.5 nos @ Tk.
5 Labour for soaking &
cleaning bricks 1/2 no @ Tk.
6 Labour for 7 days curing
@ 1/8 labour per day 0.875 no @ Tk.
7 Local carriage, storage & sundries etc.

Add VAT with adjustment factor

Say, Tk.
Item No.- 04.24
125 mm thick brick pavement with 10 holes ceramic bricks (1:4)
Considering 100 sft of work
A. Materials:
1 10 holes ceramic bricks 480 nos @ Tk.
2 Sand (F.M. 1.2) 15 cft @ Tk.
3 Cement (in/c for flush pointing) 3.25 bags @ Tk.
B. Labour:
1 Head mason 1/4 no @ Tk.
2 Mason 1.25 nos @ Tk.
3 Skilled labour 2.25 nos @ Tk.
4 Ordinary labour 1.5 nos @ Tk.
5 Labour for soaking &
cleaning bricks 1/2 no @ Tk.
6 Labour for 7 days curing
@ 1/8 labour per day 0.875 no @ Tk.
7 Local carriage, storage & sundries etc.

Analysis of PWD SoR 2018 for Civil Work


Add VAT with adjustment factor

Say, Tk.
Item No.- 04.25
3" thick cement concrete (C.C.) in floor (1:3:6)
Considering 100 sft of work
From item No.-03.4.2 cost of concrete = Tk.
1 For 3" thick 100 sft of work
2 Add extra for floor casting:
Mason 1 No. @ Tk.

Add VAT with adjustment factor

Say, Tk.
Item No.- 04.26
25 mm thick artificial patent stone flooring (1:2:4) with brick chips
Considering 100 cft of work covering 1200 sft area
1 Bricks @ 8.5 nos per cft chips 765 nos @ Tk.
2 Sand (F.M. 1.2) 22.5 cft @ Tk.
3 Sand (F.M. 2.2) 22.5 cft @ Tk.
4 Cement 18 bags @ Tk.
5 Breaking chips in/c screening 90 cft @ Tk.
6 Labour for 7 days curing
@ 1/8 labour per day. 0.875 no @ Tk.
7 Local carriage, sundries, T & P and washing of sand etc.

8 Extra cement for finishing 1/2 bag @ Tk.


9 Labour cost:
i) Head mason 1/5 nos @ Tk.
ii) Mason 3/4 nos @ Tk.
iii) Skilled labour 1 no @ Tk.
iv) Ordinary labour 1 no @ Tk.
10 Extra cost of Garjan batten for side shutter
2 x 4 x 5'-0" x 1" x 3/4" = 0.21 cft
Add 5% wastage 0.01 cft
0.22 cft @ Tk.
Using 10 @ Tk.
11 Labour for shuttering
2 x 4 x 5'-0" x 1" = 3.33 sft @ Tk.

Add VAT with adjustment factor

(i) Ground floor

Say, Tk.

Analysis of PWD SoR 2018 for C


Item No.- 04.27
38 mm thick artificial patent stone flooring (1:2:4) with brick chips
Considering 100 cft of work covering 800 sft area
1 Bricks @ 8.5 nos per cft chips 765 nos @ Tk.
2 Sand (F.M. 1.2) 22.5 cft @ Tk.
3 Sand (F.M. 2.2) 22.5 cft @ Tk.
4 Cement 18 bags @ Tk.
5 Breaking brick chips
in/c screening 90 cft @ Tk.
6 Labour for 7 days curing
@ 1/8 labour per day. 0.875 no @ Tk.
7 Local carriage, sundries, T & P and washing of sand etc.

For 100 sft of work


8 Extra cement for finishing 1/2 bag @ Tk.
9 Labour cost:
(a) Head mason 1/5 no @ Tk.
(b) Mason 3/4 no @ Tk.
(c) Skilled labour 1 no @ Tk.
(d) Ordinary labour 1 no @ Tk.
10 Extra cost of Garjan batten for side shutter
2 x 4 x 5'-0" x 1.5" x 3/4" = 0.31 cft
Add 5% wastage 0.02 cft
0.33 cft @ Tk.
Using 10 @ Tk.
11 Labour for shuttering
2 x 4 x 5'-0" x 1.5" = 5 sft @ Tk.

Add VAT with adjustment factor

(i) Ground floor

Say, Tk.
Item No.- 04.28
25 mm thick artificial patent stone flooring (1:2:4) with 1/2" down graded stone chips
Considering 100 cft of work covering 1200 sft area
1 Crushed stone chips 90 cft @ Tk.
2 Sand (F.M. 1.2) 22.5 cft @ Tk.
3 Sand (F.M. 2.2) 22.5 cft @ Tk.
4 Cement 18 bags @ Tk.
5 Labour for 7 days curing
@ 1/8 labour per day. 0.875 no @ Tk.
6 Local carriage, sundries, T & P and washing of sand etc.

For 100 sft of work


7 Extra cement for finishing 1/2 bag @ Tk.
8 Labour cost:
(a) Head mason 1/5 no @ Tk.
(b) Mason 3/4 no @ Tk.
(c) Skilled labour 1 no @ Tk.
(d) Ordinary labour 1 no @ Tk.
10 Extra cost of Garjan batten for side shutter
2 x 4 x 5'-0" x 1" x 3/4" = 0.21 cft
Add 5% wastage 0.01 cft
0.22 cft @ Tk.

Analysis of PWD SoR 2018 for C


Using 10 times @ Tk.
11 Labour for shuttering
2 x 4 x 5'-0" x 1" = 3.33 sft @ Tk.

Add VAT with adjustment factor

(i) Ground floor

Say, Tk.
Item No.- 04.29
38 mm thick artificial patent stone flooring (1:2:4) with 1/2" down graded stone chips
Considering 100 cft of work covering 800 sft area
1 Crushed stone chips 90 cft @ Tk.
2 Sand (F.M. 1.2) 22.5 cft @ Tk.
3 Sand (F.M. 2.2) 22.5 cft @ Tk.
4 Cement 18 bags @ Tk.
5 Labour for 7 days curing
@ 1/8 labour per day. 0.875 no @ Tk.
6 Local carriage, sundries, T & P and washing of sand etc.

7 Extra cement for finishing 1/2 bag @ Tk.


8 Labour cost:
(a) Head mason 1/5 no @ Tk.
(b) Mason 3/4 no @ Tk.
(c) Skilled labour 1 no @ Tk.
(d) Ordinary labour 1 no @ Tk.
10 Extra cost of Garjan batten for side shutter
2 x 4 x 5'-0" x 1.5" x 3/4" = 0.31 cft
Add 5% wastage 0.02 cft
0.33 cft @ Tk.
Using 10 @ Tk.
11 Labour for shuttering
2 x 4 x 5'-0" x 1.5" = 5 sft @ Tk.

Add VAT with adjustment factor

(i) Ground floor

Say, Tk.
Item No.- 04.30
25 mm thick artificial patent stone flooring (1 : 1.5 : 3) with 1/2" down graded stone chips
Considering 100 cft of work covering 1200 sft area
1 Crushed stone chips 90 cft @ Tk.
2 Sand (F.M. 1.2) 22.5 cft @ Tk.
3 Sand (F.M. 2.2) 22.5 cft @ Tk.
4 Cement 22 bags @ Tk.
5 Labour for 7 days curing
@ 1/8 labour per day. 0.875 no @ Tk.
6 Local carriage, sundries, T & P and washing of sand etc.

Analysis 131

7 Extra cement for finishing 1/2 bag @ Tk.


8 Labour cost:
(a) Head mason 1/5 no @ Tk.
(b) Mason 3/4 no @ Tk.
(c) Skilled labour 1 no @ Tk.
(d) Ordinary labour 1 no @ Tk.
10 Extra cost of Garjan batten for side shutter
2 x 4 x 5'-0" x 1" x 3/4" = 0.21 cft
Add 5% wastage 0.01 cft
0.22 cft @ Tk.
Using 10 times @ Tk.
11 Labour for shuttering
2 x 4 x 5'-0" x 1" = 3.33 sft @ Tk.

Add VAT with adjustment factor

(i) Ground floor

Say, Tk.
Item No.- 04.31
38 mm thick artificial patent stone flooring (1: 1.5 : 3) with 1/2" down graded stone chips
Considering 100 cft of work covering 800 sft area
1 Crushed stone chips 90 cft @ Tk.
2 Sand (F.M. 1.2) 22.5 cft @ Tk.
3 Sand (F.M. 2.2) 22.5 cft @ Tk.
4 Cement 22 bags @ Tk.
5 Labour for 7 days curing
@ 1/8 labour per day. 0.875 no @ Tk.
6 Local carriage, sundries, T & P and washing of sand etc.
7 Extra cement for finishing 1/2 bag @ Tk.
8 Labour cost:
(a) Head mason 1/5 no @ Tk.
(b) Mason 3/4 no @ Tk.
(c) Skilled labour 1 no @ Tk.
(d) Ordinary labour 1 no @ Tk.
10 Extra cost of Garjan batten for side shutter
2 x 4 x 5'-0" x 1.5" x 3/4" = 0.31 cft
Add 5% wastage 0.02 cft
0.33 cft @ Tk.
Using 10 @ Tk.
11 Labour for shuttering
2 x 4 x 5'-0" x 1.5" = 5 sft @ Tk.

Add VAT with adjustment factor

(i) Ground floor

Say, Tk.

Analysis of PWD SoR 2018 for C 132


Item No.- 04.32
Extra rate for each additional floor for patent stone flooring
04.32.1 Add for each addl. floor up to 5th floor (@per sqm = Tk. 31.00
04.32.2 Add for each addl. floor for 6th floor to 9t per sqm = Tk. 42.00
04.32.3 Add for each addl. floor 10th floor and ab per sqm = Tk. 52.00
CY SCREEN BLOCK WORKS

8,700.00 per % 0 nos = Tk. 9,570.00


1,400.00 per % cft = Tk. 504.00
395.00 per bag = Tk. 1,580.00
600.00 per day = Tk. 60.00
500.00 per day = Tk. 500.00
390.00 per day = Tk. 390.00
320.00 per day = Tk. 480.00

320.00 per day = Tk. 640.00

320.00 per day = Tk. 280.00


LS = Tk. 160.00
Sub - Total = Tk. 14,164.00
Profit 10.00% = Tk. 1,416.40
Overhead 3.50% = Tk. 495.74
Total = Tk. 16,076.14
1.06383 6.00% = Tk. 1,026.14
Grand Total = Tk. 17,102.28
Rate per cft = Tk. 171.02
Rate per cum = Tk. 6,039.57
6,040 .00 per cum

= Tk. 14,164.00
9.00 per sft = Tk. 225.00
320.00 per day = Tk. 320.00
320.00 per day = Tk. 80.00
320.00 per day = Tk. 320.00
Sub - Total = Tk. 15,109.00
Profit 10.00% = Tk. 1,510.90
Overhead 3.50% = Tk. 528.82
Total = Tk. 17,148.72
1.06383 6.00% = Tk. 1,094.60
Grand Total = Tk. 18,243.32
Rate per cft = Tk. 182.43
Rate per cum = Tk. 6,442.63
6,443 .00 per cum

8,700.00 per % 0 nos = Tk. 9,570.00


1,400.00 per % cft = Tk. 560.00
395.00 per bag = Tk. 2,370.00
600.00 per day = Tk. 60.00
500.00 per day = Tk. 500.00
390.00 per day = Tk. 390.00
320.00 per day = Tk. 800.00

320.00 per day = Tk. 640.00


320.00 per day = Tk. 320.00

320.00 per day = Tk. 280.00

113
9.00 per sft = Tk. 225.00
LS = Tk. 160.00
Sub - Total = Tk. 15,875.00
Profit 10.00% = Tk. 1,587.50
Overhead 3.50% = Tk. 555.63
Total = Tk. 18,018.13
1.06383 6.00% = Tk. 1,150.09
Grand Total = Tk. 19,168.22
Rate per cft = Tk. 191.68
Rate per cum = Tk. 6,769.18
6,769 .00 per cum
8,700.00 per % 0 nos = Tk. 9,570.00

20% = Tk. 1,914.00


1,400.00 per % cft = Tk. 560.00
395.00 per bag = Tk. 2,567.50
600.00 per day = Tk. 300.00
500.00 per day = Tk. 750.00
390.00 per day = Tk. 585.00
320.00 per day = Tk. 640.00

320.00 per day = Tk. 640.00

320.00 per day = Tk. 320.00

320.00 per day = Tk. 280.00


9.00 per sft = Tk. 225.00
LS = Tk. 160.00
Sub - Total = Tk. 18,511.50
Profit 10.00% = Tk. 1,851.15
Overhead 3.50% = Tk. 647.90
Total = Tk. 21,010.55
1.06383 6.00% = Tk. 1,341.10
Grand Total = Tk. 22,351.65
Rate per cft = Tk. 223.52
Rate per cum = Tk. 7,893.61
7,894 .00 per cum

9,000.00 per % 0 nos = Tk. 9,900.00


1,400.00 per % cft = Tk. 560.00
395.00 per bag = Tk. 2,567.50
600.00 per day = Tk. 300.00
500.00 per day = Tk. 750.00
390.00 per day = Tk. 585.00
320.00 per day = Tk. 640.00
320.00 per day = Tk. 640.00

320.00 per day = Tk. 320.00

320.00 per day = Tk. 280.00

114
9.00 per sft = Tk. 225.00
LS = Tk. 160.00
Sub - Total = Tk. 16,927.50
Profit 10.00% = Tk. 1,692.75
Overhead 3.50% = Tk. 592.46
Total = Tk. 19,212.71
1.06383 6.00% = Tk. 1,226.34
Grand Total = Tk. 20,439.05
Rate per cft = Tk. 204.39
Rate per cum = Tk. 7,218.03
7,218 .00 per cum

18,900.00 per % 0 nos= Tk. 20,790.00


1,400.00 per % cft = Tk. 560.00
395.00 per bag = Tk. 2,567.50
600.00 per day = Tk. 300.00
500.00 per day = Tk. 750.00
390.00 per day = Tk. 585.00
320.00 per day = Tk. 640.00

320.00 per day = Tk. 640.00

320.00 per day = Tk. 320.00

320.00 per day = Tk. 280.00


9.00 per sft = Tk. 225.00
LS = Tk. 160.00
Sub - Total = Tk. 27,817.50
Profit 10.00% = Tk. 2,781.75
Overhead 3.50% = Tk. 973.61
Total = Tk. 31,572.86
1.06383 6.00% = Tk. 2,015.29
Grand Total = Tk. 33,588.15
Rate per cft = Tk. 335.88
Rate per cum = Tk. 11,861.60
11,862 .00 per cum

ker facing bricks (1:4)

13,500.00 per % 0 nos= Tk. 14,850.00


1,400.00 per % cft = Tk. 560.00
395.00 per bag = Tk. 2,567.50
600.00 per day = Tk. 150.00
500.00 per day = Tk. 1,000.00
390.00 per day = Tk. 585.00
320.00 per day = Tk. 640.00

320.00 per day = Tk. 320.00

320.00 per day = Tk. 160.00

320.00 per day = Tk. 560.00


9.00 per sft = Tk. 225.00
LS = Tk. 160.00
Sub - Total = Tk. 21,777.50
Profit 10.00% = Tk. 2,177.75

Tk. 762.21
Tk. ###
Tk. 1,577.71
Tk. ###
Tk. 262.95
Tk. 9,286.08
extured klinker

13,500.00 per % 0 nos= Tk. 14,850.00


1,400.00 per % cft = Tk. 560.00
395.00 per bag = Tk. 2,567.50
600.00 per day = Tk. 150.00
500.00 per day = Tk. 1,000.00
390.00 per day = Tk. 585.00
320.00 per day = Tk. 640.00

320.00 per day = Tk. 320.00


320.00 per day = Tk. 160.00

320.00 per day = Tk. 280.00


9.00 per sft = Tk. 225.00
LS = Tk. 160.00
Sub - Total = Tk. 21,497.50
Profit 10.00% = Tk. 2,149.75
Overhead 3.50% = Tk. 752.41
Total = Tk. 24,399.66
1.06383 6.00% = Tk. 1,557.43
Grand Total = Tk. 25,957.09
Rate per cft = Tk. 259.57
Rate per cum = Tk. 9,166.71
9,167 .00 per cum

21,500.00 per % 0 nos= Tk. 23,650.00


4,500.00 per % cft = Tk. 1,080.00
1,400.00 per % cft = Tk. 560.00
395.00 per bag = Tk. 2,567.50
600.00 per day = Tk. 150.00
500.00 per day = Tk. 1,000.00
390.00 per day = Tk. 585.00
320.00 per day = Tk. 640.00

320.00 per day = Tk. 320.00


320.00 per day = Tk. 160.00

320.00 per day = Tk. 280.00


9.00 per sft = Tk. 225.00
LS = Tk. 160.00
Sub - Total = Tk. 31,377.50
Profit 10.00% = Tk. 3,137.75
Overhead 3.50% = Tk. 1,098.21
Total = Tk. 35,613.46
1.06383 6.00% = Tk. 2,273.20

Tk. ###
Tk. 378.87
Tk. ###

Tk. 171.00
Tk. 239.00
Tk. 273.00

to 4.9 where free

600.00 per day = Tk. 30.00


500.00 per day = Tk. 100.00
390.00 per day = Tk. 39.00
320.00 per day = Tk. 96.00
9.00 per sft = Tk. 112.50
LS = Tk. 32.00
Sub - Total = Tk. 409.50
Profit 10.00% = Tk. 40.95
Overhead 3.50% = Tk. 14.33
Total = Tk. 464.78
1.06383 6.00% = Tk. 29.67
Grand Total = Tk. 494.45
Rate per cft = Tk. 4.94
Rate per cum = Tk. 174.46
174 .00 per cum

19,000.00 per % 0 nos = Tk. 8,588.00


1,400.00 per % cft = Tk. 168.00
395.00 per bag = Tk. 892.70
600.00 per day = Tk. 600.00
500.00 per day = Tk. 1,125.00
390.00 per day = Tk. 585.00
320.00 per day = Tk. 480.00

320.00 per day = Tk. 280.00


9.00 per sft = Tk. 225.00
LS = Tk. 160.00
Sub - Total = Tk. 13,103.70
Profit 10.00% = Tk. 1,310.37
Overhead 3.50% = Tk. 458.63
Total = Tk. 14,872.70
1.06383 6.00% = Tk. 949.32
Grand Total = Tk. 15,822.02
Rate per sft = Tk. 158.22
Rate per sqm = Tk. 1,703.08
1,703 .00 per sqm
(facing 200 x 50 mm)
000.00 per % 0 nos = Tk. ###
per % cft = Tk. 196.00
per bag = Tk. 1,086.25
per day = Tk. 600.00
per day = Tk. 1,166.67
per day = Tk. 585.00
per day = Tk. 480.00

per day = Tk. 280.00


per sft = Tk. 225.00
LS = Tk. 160.00
Sub - Total = Tk. ###
10.00% = Tk. 1,847.49
3.50% = Tk. 646.62
Total = Tk. ###
6.00% = Tk. 1,338.45
Grand Total = Tk. ###
Rate per sft = Tk. 223.07
Rate per sqm = Tk. 2,401.13
.00 per sqm

1:4 mortar with

500.00 per % 0 nos = Tk. ###


per % cft = Tk. 196.00
per bag = Tk. 1,086.25
per day = Tk. 600.00
per day = Tk. 1,000.00
per day = Tk. 585.00
per day = Tk. 480.00
per day = Tk. 280.00
per sft = Tk. 225.00
LS = Tk. 320.00
Sub - Total = Tk. ###
10.00% = Tk. 1,779.63
3.50% = Tk. 622.87
Total = Tk. ###
6.00% = Tk. 1,289.28
Grand Total = Tk. ###
Rate per sft = Tk. 214.88
Rate per sqm = Tk. 2,312.97
.00 per sqm

1:4 mortar with

= Tk. 14,784.00

per % cft = Tk. 196.00


per bag = Tk. 1,086.25
per day = Tk. 600.00
per day = Tk. 1,000.00
per day = Tk. 585.00
per day = Tk. 480.00

per day = Tk. 280.00


per sft = Tk. 225.00
LS = Tk. 320.00
Sub - Total = Tk. ###
10.00% = Tk. 1,955.63
3.50% = Tk. 684.47
Total = Tk. ###
6.00% = Tk. 1,416.79
Grand Total = Tk. ###
Rate per sft = Tk. 236.13
Rate per sqm = Tk. 2,541.70
.00 per sqm

mortar with

400.00 per % 0 nos = Tk. ###


per % cft = Tk. 196.00
per bag = Tk. 1,086.25
per day = Tk. 600.00
per day = Tk. 1,000.00
per day = Tk. 585.00
per day = Tk. 480.00

per day = Tk. 280.00


per sft = Tk. 225.00
LS = Tk. 320.00
Sub - Total = Tk. ###
10.00% = Tk. 1,631.79
3.50% = Tk. 571.12
Total = Tk. ###
6.00% = Tk. 1,182.18
Grand Total = Tk. ###
Rate per sft = Tk. 197.03
Rate per sqm = Tk. 2,120.83
.00 per sqm

4 mortar with

000.00 per % 0 nos = Tk. ###


per % cft = Tk. 196.00
per bag = Tk. 1,086.25
per day = Tk. 600.00
per day = Tk. 1,000.00
per day = Tk. 585.00
per day = Tk. 480.00

per day = Tk. 280.00


per sft = Tk. 225.00
LS = Tk. 320.00
Sub - Total = Tk. ###
10.00% = Tk. 1,989.23
3.50% = Tk. 696.23
Total = Tk. ###
6.00% = Tk. 1,441.13
Grand Total = Tk. ###
Rate per sft = Tk. 240.19
Rate per sqm = Tk. 2,585.41
.00 per sqm

ured) with 1:4 mortar with

34,000.00 per % 0 nos= Tk. 18,360.00


1,400.00 per % cft = Tk. 196.00
395.00 per bag = Tk. 1,086.25
600.00 per day = Tk. 600.00
500.00 per day = Tk. 1,000.00
390.00 per day = Tk. 585.00
320.00 per day = Tk. 480.00

320.00 per day = Tk. 280.00


9.00 per sft = Tk. 225.00
LS = Tk. 320.00
Sub - Total = Tk. 23,132.25
Profit 10.00% = Tk. 2,313.23
Overhead 3.50% = Tk. 809.63
Total = Tk. 26,255.11
1.06383 6.00% = Tk. 1,675.86
Grand Total = Tk. 27,930.97
Rate per sft = Tk. 279.31
Rate per sqm = Tk. 3,006.49
3,006 .00 per sqm

8,700.00 per % 0 nos = Tk. 4,176.00


1,400.00 per % cft = Tk. 252.00
395.00 per bag = Tk. 691.25
600.00 per day = Tk. 60.00
500.00 per day = Tk. 375.00
390.00 per day = Tk. 195.00
320.00 per day = Tk. 160.00

320.00 per day = Tk. 320.00

320.00 per day = Tk. 160.00

320.00 per day = Tk. 280.00


9.00 per sft = Tk. 225.00
LS = Tk. 160.00
Sub - Total = Tk. 7,054.25

120
Profit 10.00% = Tk. 705.43
Overhead 3.50% = Tk. 246.90
Total = Tk. 8,006.58
1.06383 6.00% = Tk. 511.06
Grand Total = Tk. 8,517.64
Rate per sft = Tk. 85.18
Rate per sft = Tk. 85.18
Rate per sqm = Tk. 916.88
917 .00 per sqm

8,700.00 per % 0 nos = Tk. 4,176.00


1,400.00 per % cft = Tk. 238.00
395.00 per bag = Tk. 1,027.00
600.00 per day = Tk. 60.00
500.00 per day = Tk. 375.00
390.00 per day = Tk. 195.00
320.00 per day = Tk. 160.00

320.00 per day = Tk. 320.00

320.00 per day = Tk. 80.00

320.00 per day = Tk. 280.00


9.00 per sft = Tk. 225.00
LS = Tk. 160.00
Sub - Total = Tk. 7,296.00
Profit 10.00% = Tk. 729.60
Overhead 3.50% = Tk. 255.36
Total = Tk. 8,280.96
1.06383 6.00% = Tk. 528.57
Grand Total = Tk. 8,809.53
Rate per sft = Tk. 88.10
Rate per sft = Tk. 88.10
Rate per sqm = Tk. 948.31
948 .00 per sqm

8,700.00 per % 0 nos = Tk. 4,176.00

20% = Tk. 835.20


1,400.00 per % cft = Tk. 322.00
395.00 per bag = Tk. 1,185.00
600.00 per day = Tk. 60.00
500.00 per day = Tk. 500.00
390.00 per day = Tk. 195.00
320.00 per day = Tk. 160.00

320.00 per day = Tk. 320.00

320.00 per day = Tk. 80.00

320.00 per day = Tk. 560.00


9.00 per sft = Tk. 225.00
LS = Tk. 266.67
Sub - Total = Tk. 8,884.87

= Tk. 888.49
= Tk. 310.97
= Tk. 10,084.33
= Tk. 643.68
= Tk. 10,728.01
= Tk. 107.28
= Tk. 1,154.76

9,000.00 per % 0 nos = Tk. 4,320.00


1,400.00 per % cft = Tk. 322.00
395.00 per bag = Tk. 1,185.00
600.00 per day = Tk. 60.00
500.00 per day = Tk. 500.00
390.00 per day = Tk. 195.00
320.00 per day = Tk. 160.00

320.00 per day = Tk. 320.00


320.00 per day = Tk. 80.00

320.00 per day = Tk. 560.00


9.00 per sft = Tk. 225.00
LS = Tk. 400.00
Sub - Total = Tk. 8,327.00
Profit 10.00% = Tk. 832.70
Overhead 3.50% = Tk. 291.45
Total = Tk. 9,451.15
1.06383 6.00% = Tk. 603.27
Grand Total = Tk. 10,054.42
Rate per sft = Tk. 100.54
Rate per sqm = Tk. 1,082.21
1,082 .00 per sqm

e machine made ceramic bricks (1:4) in superstructure

18,900.00 per % 0 nos = Tk. 9,072.00


1,400.00 per % cft = Tk. 252.00
395.00 per bag = Tk. 1,106.00
600.00 per day = Tk. 60.00
500.00 per day = Tk. 500.00
390.00 per day = Tk. 195.00
320.00 per day = Tk. 320.00

320.00 per day = Tk. 320.00

320.00 per day = Tk. 80.00

320.00 per day = Tk. 280.00


9.00 per sft = Tk. 225.00
LS = Tk. 160.00
Sub - Total = Tk. 12,570.00
Profit 10.00% = Tk. 1,257.00
Overhead 3.50% = Tk. 439.95
Total = Tk. 14,266.95
1.06383 6.00% = Tk. 910.66
Grand Total = Tk. 15,177.61
Rate per sft = Tk. 151.78
Rate per sft = Tk. 151.78
Rate per sqm = Tk. 1,633.76
1,634 .00 per sqm

all floors (1:3).

28,000.00 per % 0 nos = Tk. 26,460.00


1,400.00 per % cft = Tk. 52.50
395.00 per bag = Tk. 395.00
70.00 per Ib = Tk. 70.00

600.00 each = Tk. 750.00


500.00 each = Tk. 1,375.00
390.00 each = Tk. 975.00
320.00 each = Tk. 320.00

320.00 each = Tk. 320.00

320.00 each = Tk. 280.00


9.00 per sft = Tk. 225.00
LS = Tk. 160.00
Sub - Total = Tk. 31,382.50
Profit 10.00% = Tk. 3,138.25
Overhead 3.50% = Tk. 1,098.39
Total Tk. 35,619.14
1.06383 6.00% = Tk. 2,273.56
Grand Total = Tk. 37,892.70
Rate per sft = Tk. 378.93
Rate per sqm = Tk. 4,078.80
4,079 .00 per sqm

ll floors (1:3) facing 5.5" x 4"


34,000.00 per % 0 nos = Tk. 17,340.00
1,400.00 per % cft = Tk. 52.50
395.00 per bag = Tk. 395.00
70.00 per Ib = Tk. 70.00

600.00 per day = Tk. 750.00


500.00 per day = Tk. 1,375.00
390.00 per day = Tk. 975.00
320.00 per day = Tk. 320.00

320.00 per day = Tk. 160.00

320.00 per day = Tk. 280.00


9.00 per sft = Tk. 225.00
LS = Tk. 160.00
Sub - Total = Tk. 22,102.50
Profit 10.00% = Tk. 2,210.25
Overhead 3.50% = Tk. 773.59

123
Total = Tk. 25,086.34
1.06383 6.00% = Tk. 1,601.26
Grand Total = Tk. 26,687.60
Rate per sft = Tk. 266.88
Rate per sqm = Tk. 2,872.70
2,873 .00 per sqm

ck in all floors (1:3)

37,000.00 per % 0 nos = Tk. 15,540.00


1,400.00 per % cft = Tk. 52.50
395.00 per bag = Tk. 395.00
70.00 per Ib = Tk. 70.00
600.00 per day = Tk. 750.00
500.00 per day = Tk. 1,375.00
390.00 per day = Tk. 975.00
320.00 per day = Tk. 320.00

320.00 per day = Tk. 160.00

320.00 per day = Tk. 280.00


9.00 per sft = Tk. 225.00
LS = Tk. 160.00
Sub - Total = Tk. 20,302.50
Profit 10.00% = Tk. 2,030.25
Overhead 3.50% = Tk. 710.59
Total = Tk. 23,043.34
1.06383 6.00% = Tk. 1,470.85
Grand Total = Tk. 24,514.19
Rate per sft = Tk. 245.14
Rate per sqm = Tk. 2,638.69
2,639 .00 per sqm

47,000.00 per % 0 nos = Tk. 11,045.00


1,400.00 per % cft = Tk. 28.00
395.00 per bag = Tk. 197.50
70.00 per Ib = Tk. 35.00

600.00 per day = Tk. 600.00


500.00 per day = Tk. 1,000.00
390.00 per day = Tk. 975.00
320.00 per day = Tk. 320.00

320.00 per day = Tk. 160.00

320.00 per day = Tk. 280.00


9.00 per sft = Tk. 225.00
LS = Tk. 160.00
Sub - Total = Tk. 15,025.50
Profit 10.00% = Tk. 1,502.55
Overhead 3.50% = Tk. 525.89

124
Total = Tk. 17,053.94
1.06383 6.00% = Tk. 1,088.55
Grand Total = Tk. 18,142.49
Rate per sft = Tk. 181.42
Rate per sqm = Tk. 1,952.80
1,953 .00 per sqm

47,000.00 per % 0 nos = Tk. 12,690.00


1,400.00 per % cft = Tk. 28.00
395.00 per bag = Tk. 197.50
70.00 per Ib = Tk. 35.00

600.00 per day = Tk. 600.00


500.00 per day = Tk. 1,000.00
390.00 per day = Tk. 975.00
320.00 per day = Tk. 320.00

320.00 per day = Tk. 160.00

320.00 per day = Tk. 280.00


9.00 per sft = Tk. 225.00
LS = Tk. 160.00
Sub - Total = Tk. 16,670.50
Profit 10.00% = Tk. 1,667.05
Overhead 3.50% = Tk. 583.47
Total = Tk. 18,921.02
1.06383 6.00% = Tk. 1,207.72
Grand Total = Tk. 20,128.74
Rate per sft = Tk. 201.29
Rate per sqm = Tk. 2,166.69
2,167 .00 per sqm

37,000.00 per % 0 nos = Tk. 15,540.00


1,400.00 per % cft = Tk. 52.50
395.00 per bag = Tk. 395.00
70.00 per Ib = Tk. 70.00

600.00 per day = Tk. 750.00


500.00 per day = Tk. 1,375.00
390.00 per day = Tk. 975.00
320.00 per day = Tk. 320.00

320.00 per day = Tk. 160.00

320.00 per day = Tk. 280.00


9.00 per sft = Tk. 225.00
LS = Tk. 160.00
Sub - Total = Tk. 20,302.50
Profit 10.00% = Tk. 2,030.25
Overhead 3.50% = Tk. 710.59

125
Total = Tk. 23,043.34
1.06383 6.00% = Tk. 1,470.85
Grand Total = Tk. 24,514.19
Rate per sft = Tk. 245.14
Rate per sqm = Tk. 2,638.69
2,639 .00 per sqm
37,000.00 per % 0 nos = Tk. 11,100.00
1,400.00 per % cft = Tk. 52.50
395.00 per bag = Tk. 395.00
70.00 per Ib = Tk. 70.00

600.00 per day = Tk. 750.00


500.00 per day = Tk. 1,375.00
390.00 per day = Tk. 975.00
320.00 per day = Tk. 320.00

320.00 per day = Tk. 160.00

320.00 per day = Tk. 280.00


9.00 per sft = Tk. 225.00
LS = Tk. 160.00
Sub - Total = Tk. 15,862.50
Profit 10.00% = Tk. 1,586.25
Overhead 3.50% = Tk. 555.19
Total = Tk. 18,003.94
1.06383 6.00% = Tk. 1,149.19
Grand Total = Tk. 19,153.13
Rate per sft = Tk. 191.53
Rate per sqm = Tk. 2,061.63
2,062 .00 per sqm

ork (Item nos- 4.12 to 4.20)


per sqm = Tk. 31.00
per sqm = Tk. 42.00
per sqm = Tk. 52.00

er paving bricks (1:4)

19,000.00 per % 0 nos = Tk. 16,264.00


1,400.00 per % cft = Tk. 224.00
395.00 per bag = Tk. 1,283.75

600.00 per day = Tk. 150.00


500.00 per day = Tk. 750.00
390.00 per day = Tk. 1,170.00
320.00 per day = Tk. 480.00

320.00 per day = Tk. 320.00

126

320.00 per day = Tk. 280.00


LS = Tk. 160.00
Sub - Total = Tk. 21,081.75
Profit 10.00% = Tk. 2,108.18
Overhead 3.50% = Tk. 737.86
Total = Tk. 23,927.79
1.06383 6.00% = Tk. 1,527.31
Grand Total = Tk. 25,455.10
Rate per sft = Tk. 254.55
Rate per sqm = Tk. 2,739.98
2,740 .00 per sqm

ement with 200 x 100 x 50 mm klinker paving bricks (1:4)

19,000.00 per % 0 nos = Tk. 8,588.00


1,400.00 per % cft = Tk. 182.00
395.00 per bag = Tk. 987.50

600.00 per day = Tk. 150.00


500.00 per day = Tk. 500.00
390.00 per day = Tk. 975.00
320.00 per day = Tk. 480.00

320.00 per day = Tk. 160.00


320.00 per day = Tk. 280.00
LS = Tk. 160.00
Sub - Total = Tk. 12,462.50
Profit 10.00% = Tk. 1,246.25
Overhead 3.50% = Tk. 436.19
Total = Tk. 14,144.94
1.06383 6.00% = Tk. 902.87
Grand Total = Tk. 15,047.81
Rate per sft = Tk. 150.48
Rate per sqm = Tk. 1,619.77
1,620 .00 per sqm

16,000.00 per % 0 nos = Tk. 13,696.00


1,400.00 per % cft = Tk. 140.00
395.00 per bag = Tk. 987.50

600.00 per day = Tk. 150.00


500.00 per day = Tk. 625.00
390.00 per day = Tk. 975.00
320.00 per day = Tk. 480.00

320.00 per day = Tk. 320.00

127
320.00 per day = Tk. 280.00
LS = Tk. 160.00
Sub - Total = Tk. 17,813.50
Profit 10.00% = Tk. 1,781.35
Overhead 3.50% = Tk. 623.47
Total = Tk. 20,218.32
1.06383 6.00% = Tk. 1,290.53
Grand Total = Tk. 21,508.85
Rate per sft = Tk. 215.09
Rate per sqm = Tk. 2,315.23
2,315 .00 per sqm

8,700.00 per % 0 nos = Tk. 4,176.00


1,400.00 per % cft = Tk. 210.00
395.00 per bag = Tk. 1,185.00

600.00 per day = Tk. 150.00


500.00 per day = Tk. 625.00
390.00 per day = Tk. 877.50
320.00 per day = Tk. 480.00

320.00 per day = Tk. 160.00

320.00 per day = Tk. 280.00


L.S = Tk. 160.00
Sub - Total = Tk. 8,303.50
Profit 10.00% = Tk. 830.35
Overhead 3.50% = Tk. 290.62
Total = Tk. 9,424.47
1.06383 6.00% = Tk. 601.56
Grand Total = Tk. 10,026.03
Rate per sft = Tk. 100.26
Rate per sqm = Tk. 1,079.20
1,079 .00 per sqm

18,900.00 per % 0 nos = Tk. 9,072.00


1,400.00 per % cft = Tk. 210.00
395.00 per bag = Tk. 1,283.75

600.00 per day = Tk. 150.00


500.00 per day = Tk. 625.00
390.00 per day = Tk. 877.50
320.00 per day = Tk. 480.00

320.00 per day = Tk. 160.00

320.00 per day = Tk. 280.00


L.S = Tk. 160.00
Sub - Total = Tk. 13,298.25
Profit 10.00% = Tk. 1,329.83
Overhead 3.50% = Tk. 465.44
Total = Tk. 15,093.52

128
1.06383 6.00% = Tk. 963.42
Grand Total = Tk. 16,056.94
Rate per sft = Tk. 160.57
Rate per sqm = Tk. 1,728.38
1,728 .00 per sqm

13,595.50
= Tk. 3,398.88

500.00 per day = Tk. 500.00


Sub - Total = Tk. 3,898.88
Profit 10.00% = Tk. 389.89
Overhead 3.50% = Tk. 136.46
Total = Tk. 4,425.23
1.06383 6.00% = Tk. 282.46
Grand Total = Tk. 4,707.69
Rate per sft = Tk. 47.08
Rate per sqm = Tk. 506.77
507 .00 per sqm
8,700.00 per % 0 nos = Tk. 6,655.50
1,400.00 per % cft = Tk. 315.00
4,500.00 per % cft = Tk. 1,012.50
395.00 per bag = Tk. 7,110.00
1,200.00 per % cft = Tk. 1,080.00

320.00 per day = Tk. 280.00


LS = Tk. 480.00
Sub-total = Tk. 16,933.00
For 100 sft of work = Tk. 1,411.08
395.00 per bag = Tk. 197.50

600.00 per day = Tk. 120.00


500.00 per day = Tk. 375.00
390.00 per day = Tk. 390.00
320.00 per day = Tk. 320.00

2,000.00 per cft


200.00 per cft = Tk. 44.00

2.50 per sft = Tk. 8.33


Sub - Total = Tk. 2,865.91
Profit 10.00% = Tk. 286.59
Overhead 3.50% = Tk. 100.31
Total = Tk. 3,252.81
1.06383 6.00% = Tk. 207.63
Grand Total = Tk. 3,460.44
Rate per sft = Tk. 34.60
Rate per sqm = Tk. 372.43
372 .00 per sqm

129
8,700.00 per % 0 nos = Tk. 6,655.50
1,400.00 per % cft = Tk. 315.00
4,500.00 per % cft = Tk. 1,012.50
395.00 per bag = Tk. 7,110.00

1,200.00 per % cft = Tk. 1,080.00

320.00 per day = Tk. 280.00


LS = Tk. 480.00
Sub-total = Tk. 16,933.00
For 100 sft of work = Tk. 2,116.63
395.00 per bag = Tk. 197.50

600.00 per day = Tk. 120.00


500.00 per day = Tk. 375.00
390.00 per day = Tk. 390.00
320.00 per day = Tk. 320.00

2,000.00 per cft


200.00 per cft = Tk. 66.00

2.50 per sft = Tk. 12.50


Sub - Total = Tk. 3,597.63
Profit 10.00% = Tk. 359.76
Overhead 3.50% = Tk. 125.92
Total = Tk. 4,083.31
1.06383 6.00% = Tk. 260.64
Grand Total = Tk. 4,343.95
Rate per sft = Tk. 43.44
Rate per sqm = Tk. 467.59
468 .00 per sqm

n graded stone chips


16,500.00 per % cft = Tk. 14,850.00
1,400.00 per % cft = Tk. 315.00
4,500.00 per % cft = Tk. 1,012.50
395.00 per bag = Tk. 7,110.00

320.00 per day = Tk. 280.00


LS = Tk. 480.00
Sub-total = Tk. 24,047.50
For 100 sft of work = Tk. 2,003.96
395.00 per bag = Tk. 197.50

600.00 per day = Tk. 120.00


500.00 per day = Tk. 375.00
390.00 per day = Tk. 390.00
320.00 per day = Tk. 320.00

2,000.00 per cft

130
200.00 per cft = Tk. 44.00

2.50 per sft = Tk. 8.33


Sub - Total = Tk. 3,458.79
Profit 10.00% = Tk. 345.88
Overhead 3.50% = Tk. 121.06
Total = Tk. 3,925.73
1.06383 6.00% = Tk. 250.58
Grand Total = Tk. 4,176.31
Rate per sft = Tk. 41.76
Rate per sqm = Tk. 449.50
450 .00 per sqm

n graded stone chips

16,500.00 per % cft = Tk. 14,850.00


1,400.00 per % cft = Tk. 315.00
4,500.00 per % cft = Tk. 1,012.50
395.00 per bag = Tk. 7,110.00

320.00 per day = Tk. 280.00


LS = Tk. 480.00
Sub-total = Tk. 24,047.50
For 100 sft of work = Tk. 3,005.94
395.00 per bag = Tk. 197.50

600.00 per day = Tk. 120.00


500.00 per day = Tk. 375.00
390.00 per day = Tk. 390.00
320.00 per day = Tk. 320.00

2,000.00 per cft


200.00 per cft = Tk. 66.00

2.50 per sft = Tk. 12.50


Sub - Total = Tk. 4,486.94
Profit 10.00% = Tk. 448.69
Overhead 3.50% = Tk. 157.04
Total = Tk. 5,092.67
1.06383 6.00% = Tk. 325.06
Grand Total = Tk. 5,417.73
Rate per sft = Tk. 54.18
Rate per sqm = Tk. 583.19
583 .00 per sqm

down graded stone chips

16,500.00 per % cft = Tk. 14,850.00


1,400.00 per % cft = Tk. 315.00
4,500.00 per % cft = Tk. 1,012.50
395.00 per bag = Tk. 8,690.00

320.00 per day = Tk. 280.00


LS = Tk. 480.00
Sub-total = Tk. 25,627.50

For 100 sft of work = Tk. 2,135.63


395.00 per bag = Tk. 197.50

600.00 per day = Tk. 120.00


500.00 per day = Tk. 375.00
390.00 per day = Tk. 390.00
320.00 per day = Tk. 320.00

2,000.00 per cft


200.00 per cft = Tk. 44.00

2.50 per sft = Tk. 8.33


Sub - Total = Tk. 3,590.46
Profit 10.00% = Tk. 359.05
Overhead 3.50% = Tk. 125.67
Total = Tk. 4,075.18
1.06383 6.00% = Tk. 260.12
Grand Total = Tk. 4,335.30
Rate per sft = Tk. 43.35
Rate per sqm = Tk. 466.62
467 .00 per sqm

down graded stone chips

16,500.00 per % cft = Tk. 14,850.00


1,400.00 per % cft = Tk. 315.00
4,500.00 per % cft = Tk. 1,012.50
395.00 per bag = Tk. 8,690.00

320.00 per day = Tk. 280.00


LS = Tk. 480.00
Sub-total = Tk. 25,627.50
For 100 sft of work = Tk. 3,203.44
395.00 per bag = Tk. 197.50

600.00 per day = Tk. 120.00


500.00 per day = Tk. 375.00
390.00 per day = Tk. 390.00
320.00 per day = Tk. 320.00

2,000.00 per cft


200.00 per cft = Tk. 66.00

2.50 per sft = Tk. 12.50


Sub - Total = Tk. 4,684.44
Profit 10.00% = Tk. 468.44
Overhead 3.50% = Tk. 163.96
Total = Tk. 5,316.84
1.06383 6.00% = Tk. 339.37
Grand Total = Tk. 5,656.21
Rate per sft = Tk. 56.56
Rate per sqm = Tk. 608.81
609 .00 per sqm

You might also like