Professional Documents
Culture Documents
Cost or Rate Analysis of Brick Works Patent Stone in Floor and Fancy Screen Block Works
Cost or Rate Analysis of Brick Works Patent Stone in Floor and Fancy Screen Block Works
Say, Tk.
Item No.- 04.2
Brick work with first class bricks in superstructure (1:6)
Considering 100 cft of work
1 Materials and labour as per item No. 04.1
2 Scaffolding 25 sft @ Tk.
3 Extra labour for carriage 1 no @ Tk.
4 Extra labour for 7 days curing 1/4 no @ Tk.
5 Labour for screening & washing 1 no @ Tk.
Add VAT with adjustment factor
Say, Tk.
Item No.- 04.3
Brickwork with 1st class bricks in superstructure (1:4)
Considering 100 cft of work
1 Bricks 1100 nos @ Tk.
2 Sand (F.M 1.2) in/c wastage 40 cft @ Tk.
3 Cement 6 bags @ Tk.
4 Head mason 0.10 no @ Tk.
5 Mason 1 no @ Tk.
6 Skilled labour 1 no @ Tk.
7 Ordinary labour 2.5 nos @ Tk.
8 Labour for soaking
& cleaning bricks 2 nos @ Tk.
9 Screening and washing sand 1 no @ Tk.
10 Labour for 7 days curing
@ 1/8 labour per day: 0.875 nos @ Tk.
Say, Tk.
Say, Tk.
Say, Tk.
Item No.- 04.6
Brick work with 10 holes machine made bricks (1:4)
Considering 100 cft work
1 Bricks 1100 nos @ Tk.
2 Sand (F.M 1.2) in/c wastage 40 cft @ Tk.
3 Cement 6.5 bags @ Tk.
4 Head mason 0.50 nos @ Tk.
5 Mason 1.5 nos @ Tk.
6 Skilled labour 1.5 nos @ Tk.
7 Ordinary labour 2 nos @ Tk.
8 Labour for soaking &
cleaning bricks 2 nos @ Tk.
9 Labour for screening and
washing sand 1.00 no @ Tk.
10 Labour for 7 days curing
@ 1/8 labour per day: 0.875 nos @ Tk.
11 Scaffolding 25 sft @ Tk.
12 Local carriage, sundries, T & P etc.
Add VAT with adjustment factor
Say, Tk.
Item No.- 04.7
Brick work with 9.5" x 4.5" x 2.75" size machine made solid klinker facing bricks (1:4)
Considering 100 cft work
1 Bricks 1100 nos @ Tk.
2 Sand (F.M 1.2) in/c wastage 40.0 cft @ Tk.
3 Cement 6.5 bags @ Tk.
4 Head mason 0.25 nos @ Tk.
5 Mason 2.0 nos @ Tk.
6 Skilled labour 1.5 nos @ Tk.
7 Ordinary labour 2.0 nos @ Tk.
8 Labour for soaking
& cleaning bricks 1.0 no @ Tk.
9 Labour for screening and
washing sand 1/2 no @ Tk.
10 Labour for 7 days curing
@ 1/4 labour per day: 1.75 nos @ Tk.
11 Scaffolding 25 sft @ Tk.
12 Local carriage, sundries, T & P etc.
Analysis 115
Overhead 3.50% =
Total =
Add VAT w1.06383 6.00% =
Grand Tot=
(a) Ground floor Rate per c=
Rate per =
Say, Tk. 9,286 .00 per cum
Item No.- 04.8
Brick work with 9.5" x 4.5" x 2.75" size 10 hole machine made rock-face/textured klinker
facing bricks (1:4)
Considering 100 cft work
1 Bricks 1100 nos @ Tk.
2 Sand (F.M 1.2) in/c wastage 40 cft @ Tk.
3 Cement 6.5 bags @ Tk.
4 Head mason 0.25 nos @ Tk.
5 Mason 2 nos @ Tk.
6 Skilled labour 1.5 nos @ Tk.
7 Ordinary labour 2.0 nos @ Tk.
8 Labour for soaking &
cleaning bricks 1 no @ Tk.
9 Screening and washing sand 1/2 no @ Tk.
10 Labour for 7 days curing
@ 1/8 labour per day: 0.875 nos @ Tk.
11 Scaffolding 25 sft @ Tk.
12 Local carriage, sundries, T & P etc.
Say, Tk.
Say, Tk.
Say, Tk.
Analysis 117
Profit
Overhead
Profit
Overhead
Profit
Overhead
Profit
Overhead
Profit
Overhead
Say, Tk.
Item No.- 04.15
125 mm brick work with first class bricks (1:6) in superstructure
Considering 100 sft work
1 Bricks 480 nos @ Tk.
2 Sand (F.M. 1.2) 18 cft @ Tk.
3 Cement 1.75 bags @ Tk.
4 Head mason 0.1 no @ Tk.
5 Mason 3/4 no @ Tk.
6 Skilled labour 1/2 no @ Tk.
7 Ordinary labour 1/2 no @ Tk.
8 Labour for soaking &
cleaning bricks 1 no @ Tk.
9 Labour for screening &
washing sand 1/2 no @ Tk.
10 Labour for 7 days curing
@ 1/8 No. labour per day 0.875 no @ Tk.
11 Scaffolding 25 sft @ Tk.
12 Local carriage, storage & sundries etc.
Say, Tk.
Item No.- 04.17
Exposed 125 mm pointing extra ordinary ornamental brick work (1:4)
Considering 100 sft of work
1 Bricks 480 nos @ Tk.
Extra cost for special quality 1st class bricks
in/c sorting out the bricks @
2 Sand (F.M. 1.2) in/c wastage 23 cft @ Tk.
3 Cement in/c pointing 3 bags @ Tk.
4 Head mason 0.10 no @ Tk.
5 Mason 1 no @ Tk.
6 Skilled labour 0.5 no @ Tk.
7 Ordinary labour 0.5 no @ Tk.
8 Labour for soaking &
cleaning bricks 1 no @ Tk.
9 Labour for screening &
washing sand 0.25 no @ Tk.
10 Labour for 7 days curing
@ 1/4 labour per day 1.75 nos @ Tk.
11 Scaffolding and stageing 25 sft @ Tk.
12 Local carriage, storage & sundries etc.
Analysis 121
Profit 10.00%
Overhead 3.50%
Total
Add VAT with adjus1.06383 6.00%
Grand Total
(a) Ground floor Rate per sft
Rate per sqm
Say, Tk. 1,155 .00 per sqm
Say, Tk.
Item No.- 04.19
125 mm brick work with 10 hole machine made ceramic bricks (1:4) in
Considering 100 sft work
1 Bricks 480 nos @ Tk. 18,900.00 per % 0 nos
2 Sand (F.M. 1.2) 18 cft @ Tk.
3 Cement 2.8 bags @ Tk.
4 Head mason 0.1 no @ Tk.
5 Mason 1 no @ Tk.
6 Skilled labour 1/2 no @ Tk.
7 Ordinary labour 1 no @ Tk.
8 Labour for soaking &
cleaning bricks 1 no @ Tk.
9 Labour for screening &
washing sand 1/4 no @ Tk.
10 Labour for 7 days curing
@ 1/8 No. labour per day 0.875 nos @ Tk.
11 Scaffolding 25 sft @ Tk.
12 Local carriage, storage & sundries etc.
Say, Tk.
Item No.- 04.20.1
Fancy screen work in wall with 4.5'' x 4.5'' x 4.5'' design block in all floors (1:3).
Considering 100 sft of work
A. Materials:
1 4.5" x 4.5" x 4.5" design
block in/c wastage 945 nos @ Tk.
2 Sand (F.M. 1.2) 3.75 cft @ Tk.
3 Cement 1 bag @ Tk.
4 Colour pigment 1 Ib @ Tk.
B. Labour:
1 Head mason 1 1/4 no @ Tk.
2 Mason 2.75 no @ Tk.
3 Skilled labour 2.5 no @ Tk.
4 Ordinary labour 1 no @ Tk.
5 Labour for soaking &
cleaning blocks. 1 no @ Tk.
6 Labour for 7 days curing
@ 1/8 No. labour per day 0.875 no @ Tk.
7 Scaffolding 25 sft @ Tk.
8 Washing of sand, local carriage & storage
Say, Tk.
Item No.- 04.20.2
Fancy screen work in wall with 5.5'' x 5.5'' x 4'' design block in all floors (1:3) facing 5.5" x 4"
Considering 100 sft of work
A. Materials:
1 5.5" x 5.5" x 4" design
block in/c wastage 510 nos @ Tk.
2 Sand (F.M. 1.2) 3.75 cft @ Tk.
3 Cement 1 bag @ Tk.
4 Colour pigment 1 Ib @ Tk.
B. Labour:
1 Head mason 1.25 nos @ Tk.
2 Mason 2.75 nos @ Tk.
3 Skilled labour 2.5 nos @ Tk.
4 Ordinary labour 1 no @ Tk.
5 Labour for soaking & .
cleaning blocks 0.50 no @ Tk.
6 Labour for 7 days curing
@ 1/8 No. labour per day 0.875 no @ Tk.
7 Scaffolding 25 sft @ Tk.
8 Washing of sand, local carriage & storage etc.
Say, Tk.
Item No.- 04.20.3
Fancy Screen work with 6'' x 6'' x 4" or 6'' x 6'' x 4.5'' design block in all floors (1:3)
Considering 100 sft of work
A. Materials:
1 6" x 6" x 4" or 6" x 6" x 4" design
block in/c wastage 420 nos @ Tk.
2 Sand (F.M. 1.2) 3.75 cft @ Tk.
3 Cement 1 bag @ Tk.
4 Colour pigment 1 Ib @ Tk.
B. Labour:
1 Head mason 1.25 nos @ Tk.
2 Mason 2.75 nos @ Tk.
3 Skilled labour 2.5 nos @ Tk.
4 Ordinary labour 1 no @ Tk.
5 Labour for soaking &
cleaning blocks. 0.50 no @ Tk.
6 Labour for 7 days curing
@ 1/8 No. labour per day 0.875 no @ Tk.
7 Scaffolding 25 sft @ Tk.
8 Washing of sand, local carriage & storage etc.
Say, Tk.
Item No.- 04.20.4
Fancy Screen work with 8'' x 8'' x 4.25'' design block
Considering 100 sft of work
A. Materials:
1 8" x 8" x 4.25" design
block in/c wastage 235 nos @ Tk.
2 Sand (F.M. 1.2) 2 cft @ Tk.
3 Cement 0.5 bag @ Tk.
4 Colour pigment 0.5 Ib @ Tk.
B. Labour:
1 Head mason 1 no @ Tk.
2 Mason 2 nos @ Tk.
3 Skilled labour 2.5 nos @ Tk.
4 Ordinary labour 1 no @ Tk.
5 Labour for soaking &
cleaning blocks. 0.50 no @ Tk.
6 Labour for 7 days curing
@ 1/8 No. labour per day 0.875 no @ Tk.
7 Scaffolding 25 sft @ Tk.
8 Washing of sand, local carriage & storage etc.
Say, Tk.
Item No.- 04.20.5
Fancy Screen work with 8'' x 4.75'' x 4'' design block in all floors (1:3)
Considering 100 sft of work
A. Materials:
1 8'' x 4.75'' x 4'' design
block in/c wastage 270 nos @ Tk.
2 Sand (F.M. 1.2) 2 cft @ Tk.
3 Cement 0.5 bag @ Tk.
4 Colour pigment 0.5 Ib @ Tk.
B. Labour:
1 Head mason 1 no @ Tk.
2 Mason 2 nos @ Tk.
3 Skilled labour 2.5 nos @ Tk.
4 Ordinary labour 1 no @ Tk.
5 Labour for soaking &
cleaning blocks. 0.50 no @ Tk.
6 Labour for 7 days curing
@ 1/8 No. labour per day 0.875 no @ Tk.
7 Scaffolding 25 sft @ Tk.
8 Washing of sand, local carriage & storage etc.
Say, Tk.
Item No.- 04.20.6
Fancy Screen work with 6'' x 6'' x 6''design block in all floors (1:3)
Considering 100 sft of work
A. Materials:
1 6" x 6" x 6" design
block in/c wastage 420 nos @ Tk.
2 Sand (F.M. 1.2) 3.75 cft @ Tk.
3 Cement 1 bag @ Tk.
4 Colour pigment 1 Ib @ Tk.
B. Labour:
1 Head mason 1.25 nos @ Tk.
2 Mason 2.75 nos @ Tk.
3 Skilled labour 2.5 nos @ Tk.
4 Ordinary labour 1 no @ Tk.
5 Labour for soaking &
cleaning blocks. 0.50 no @ Tk.
6 Labour for 7 days curing
@ 1/8 No. labour per day 0.875 no @ Tk.
7 Scaffolding 25 sft @ Tk.
8 Washing of sand, local carriage & storage etc.
Say, Tk.
Item No.- 04.20.7
Fancy Screen work with 9.5'' x 4.5'' x 2.75'' design block in all floors (1:3)
Considering 100 sft of work
A. Materials:
1 9.5'' x 4.5'' x 2.75'' design
block in/c wastage 300 nos @ Tk.
2 Sand (F.M. 1.2) 3.75 cft @ Tk.
3 Cement 1 bag @ Tk.
4 Colour pigment 1 Ib @ Tk.
B. Labour:
1 Head mason 1.25 nos @ Tk.
2 Mason 2.75 nos @ Tk.
3 Skilled labour 2.5 nos @ Tk.
4 Ordinary labour 1 no @ Tk.
5 Labour for soaking &
cleaning blocks. 0.50 no @ Tk.
6 Labour for 7 days curing
@ 1/8 No. labour per day 0.875 nos @ Tk.
7 Scaffolding 25 sft @ Tk.
8 Washing of sand, local carriage & storage etc.
Say, Tk.
Item No.- 04.21
Extra rate for each additional floor for brick and screen block work (Item nos- 4.12 to 4.20)
04.21.1 Add for each addl. floor up to 5th floor (@ 0.75 No. lab per % sft)
04.21.2 Add for each addl. floor for 6th floor to 9th floor (@ 1 No. lab per % sft)
04.21.3 Add for each addl. floor 10th floor and above (@ 1.25 nos lab per % sft)
Item No.- 04.22.1
100 mm thick flat brick pavement with 200 x 100 x 50 mm klinker paving bricks (1:4)
Considering 100 sft of work
A. Materials:
1 200 x 100 x 50 mm klinker paving
bricks (facing 200 x 50 mm)
in/c 5% wastage 856 nos @ Tk.
2 Sand (F.M. 1.2) 16 cft @ Tk.
3 Cement (in/c for flush pointing) 3.25 bags @ Tk.
B. Labour:
1 Head mason 1/4 no @ Tk.
2 Mason 1.5 nos @ Tk.
3 Skilled labour 3 nos @ Tk.
4 Ordinary labour 1.5 nos @ Tk.
5 Labour for soaking &
cleaning bricks 1 no @ Tk.
Say, Tk.
Item No.- 04.22.2
50 mm thick brick on edge pavement with 200 x 100 x 50 mm klinker
Considering 100 sft of work
A. Materials:
1 200 x 100 x 50 mm klinker paving
bricks (facing 200 x 100 mm)
in/c 5% wastage 452 nos @ Tk.
2 Sand (F.M. 1.2) 13 cft @ Tk.
3 Cement (in/c for flush pointing) 2.5 bags @ Tk.
B. Labour:
1 Head mason 1/4 no @ Tk.
2 Mason 1 nos @ Tk.
3 Skilled labour 2.5 nos @ Tk.
4 Ordinary labour 1.5 nos @ Tk.
5 Labour for soaking &
cleaning bricks 0.50 no @ Tk.
6 Labour for 7 days curing
@ 1/8 labour per day. 0.875 no @ Tk.
7 Local carriage & storage, sundries etc.
Say, Tk.
Say, Tk.
Item No.- 04.23
125 mm thick brick pavement with 1st class bricks (1:4)
Considering 100 sft work
A. Materials:
1 1st class bricks in/c wastage 480 nos @ Tk.
2 Sand (F.M. 1.2) 15 cft @ Tk.
3 Cement (in/c for flush pointing) 3 bags @ Tk.
B. Labour:
1 Head mason 1/4 no @ Tk.
2 Mason 1.25 nos @ Tk.
3 Skilled labour 2.25 nos @ Tk.
4 Ordinary labour 1.5 nos @ Tk.
5 Labour for soaking &
cleaning bricks 1/2 no @ Tk.
6 Labour for 7 days curing
@ 1/8 labour per day 0.875 no @ Tk.
7 Local carriage, storage & sundries etc.
Say, Tk.
Item No.- 04.24
125 mm thick brick pavement with 10 holes ceramic bricks (1:4)
Considering 100 sft of work
A. Materials:
1 10 holes ceramic bricks 480 nos @ Tk.
2 Sand (F.M. 1.2) 15 cft @ Tk.
3 Cement (in/c for flush pointing) 3.25 bags @ Tk.
B. Labour:
1 Head mason 1/4 no @ Tk.
2 Mason 1.25 nos @ Tk.
3 Skilled labour 2.25 nos @ Tk.
4 Ordinary labour 1.5 nos @ Tk.
5 Labour for soaking &
cleaning bricks 1/2 no @ Tk.
6 Labour for 7 days curing
@ 1/8 labour per day 0.875 no @ Tk.
7 Local carriage, storage & sundries etc.
Say, Tk.
Item No.- 04.25
3" thick cement concrete (C.C.) in floor (1:3:6)
Considering 100 sft of work
From item No.-03.4.2 cost of concrete = Tk.
1 For 3" thick 100 sft of work
2 Add extra for floor casting:
Mason 1 No. @ Tk.
Say, Tk.
Item No.- 04.26
25 mm thick artificial patent stone flooring (1:2:4) with brick chips
Considering 100 cft of work covering 1200 sft area
1 Bricks @ 8.5 nos per cft chips 765 nos @ Tk.
2 Sand (F.M. 1.2) 22.5 cft @ Tk.
3 Sand (F.M. 2.2) 22.5 cft @ Tk.
4 Cement 18 bags @ Tk.
5 Breaking chips in/c screening 90 cft @ Tk.
6 Labour for 7 days curing
@ 1/8 labour per day. 0.875 no @ Tk.
7 Local carriage, sundries, T & P and washing of sand etc.
Say, Tk.
Say, Tk.
Item No.- 04.28
25 mm thick artificial patent stone flooring (1:2:4) with 1/2" down graded stone chips
Considering 100 cft of work covering 1200 sft area
1 Crushed stone chips 90 cft @ Tk.
2 Sand (F.M. 1.2) 22.5 cft @ Tk.
3 Sand (F.M. 2.2) 22.5 cft @ Tk.
4 Cement 18 bags @ Tk.
5 Labour for 7 days curing
@ 1/8 labour per day. 0.875 no @ Tk.
6 Local carriage, sundries, T & P and washing of sand etc.
Say, Tk.
Item No.- 04.29
38 mm thick artificial patent stone flooring (1:2:4) with 1/2" down graded stone chips
Considering 100 cft of work covering 800 sft area
1 Crushed stone chips 90 cft @ Tk.
2 Sand (F.M. 1.2) 22.5 cft @ Tk.
3 Sand (F.M. 2.2) 22.5 cft @ Tk.
4 Cement 18 bags @ Tk.
5 Labour for 7 days curing
@ 1/8 labour per day. 0.875 no @ Tk.
6 Local carriage, sundries, T & P and washing of sand etc.
Say, Tk.
Item No.- 04.30
25 mm thick artificial patent stone flooring (1 : 1.5 : 3) with 1/2" down graded stone chips
Considering 100 cft of work covering 1200 sft area
1 Crushed stone chips 90 cft @ Tk.
2 Sand (F.M. 1.2) 22.5 cft @ Tk.
3 Sand (F.M. 2.2) 22.5 cft @ Tk.
4 Cement 22 bags @ Tk.
5 Labour for 7 days curing
@ 1/8 labour per day. 0.875 no @ Tk.
6 Local carriage, sundries, T & P and washing of sand etc.
Analysis 131
Say, Tk.
Item No.- 04.31
38 mm thick artificial patent stone flooring (1: 1.5 : 3) with 1/2" down graded stone chips
Considering 100 cft of work covering 800 sft area
1 Crushed stone chips 90 cft @ Tk.
2 Sand (F.M. 1.2) 22.5 cft @ Tk.
3 Sand (F.M. 2.2) 22.5 cft @ Tk.
4 Cement 22 bags @ Tk.
5 Labour for 7 days curing
@ 1/8 labour per day. 0.875 no @ Tk.
6 Local carriage, sundries, T & P and washing of sand etc.
7 Extra cement for finishing 1/2 bag @ Tk.
8 Labour cost:
(a) Head mason 1/5 no @ Tk.
(b) Mason 3/4 no @ Tk.
(c) Skilled labour 1 no @ Tk.
(d) Ordinary labour 1 no @ Tk.
10 Extra cost of Garjan batten for side shutter
2 x 4 x 5'-0" x 1.5" x 3/4" = 0.31 cft
Add 5% wastage 0.02 cft
0.33 cft @ Tk.
Using 10 @ Tk.
11 Labour for shuttering
2 x 4 x 5'-0" x 1.5" = 5 sft @ Tk.
Say, Tk.
= Tk. 14,164.00
9.00 per sft = Tk. 225.00
320.00 per day = Tk. 320.00
320.00 per day = Tk. 80.00
320.00 per day = Tk. 320.00
Sub - Total = Tk. 15,109.00
Profit 10.00% = Tk. 1,510.90
Overhead 3.50% = Tk. 528.82
Total = Tk. 17,148.72
1.06383 6.00% = Tk. 1,094.60
Grand Total = Tk. 18,243.32
Rate per cft = Tk. 182.43
Rate per cum = Tk. 6,442.63
6,443 .00 per cum
113
9.00 per sft = Tk. 225.00
LS = Tk. 160.00
Sub - Total = Tk. 15,875.00
Profit 10.00% = Tk. 1,587.50
Overhead 3.50% = Tk. 555.63
Total = Tk. 18,018.13
1.06383 6.00% = Tk. 1,150.09
Grand Total = Tk. 19,168.22
Rate per cft = Tk. 191.68
Rate per cum = Tk. 6,769.18
6,769 .00 per cum
8,700.00 per % 0 nos = Tk. 9,570.00
114
9.00 per sft = Tk. 225.00
LS = Tk. 160.00
Sub - Total = Tk. 16,927.50
Profit 10.00% = Tk. 1,692.75
Overhead 3.50% = Tk. 592.46
Total = Tk. 19,212.71
1.06383 6.00% = Tk. 1,226.34
Grand Total = Tk. 20,439.05
Rate per cft = Tk. 204.39
Rate per cum = Tk. 7,218.03
7,218 .00 per cum
Tk. 762.21
Tk. ###
Tk. 1,577.71
Tk. ###
Tk. 262.95
Tk. 9,286.08
extured klinker
Tk. ###
Tk. 378.87
Tk. ###
Tk. 171.00
Tk. 239.00
Tk. 273.00
= Tk. 14,784.00
mortar with
4 mortar with
120
Profit 10.00% = Tk. 705.43
Overhead 3.50% = Tk. 246.90
Total = Tk. 8,006.58
1.06383 6.00% = Tk. 511.06
Grand Total = Tk. 8,517.64
Rate per sft = Tk. 85.18
Rate per sft = Tk. 85.18
Rate per sqm = Tk. 916.88
917 .00 per sqm
= Tk. 888.49
= Tk. 310.97
= Tk. 10,084.33
= Tk. 643.68
= Tk. 10,728.01
= Tk. 107.28
= Tk. 1,154.76
123
Total = Tk. 25,086.34
1.06383 6.00% = Tk. 1,601.26
Grand Total = Tk. 26,687.60
Rate per sft = Tk. 266.88
Rate per sqm = Tk. 2,872.70
2,873 .00 per sqm
124
Total = Tk. 17,053.94
1.06383 6.00% = Tk. 1,088.55
Grand Total = Tk. 18,142.49
Rate per sft = Tk. 181.42
Rate per sqm = Tk. 1,952.80
1,953 .00 per sqm
125
Total = Tk. 23,043.34
1.06383 6.00% = Tk. 1,470.85
Grand Total = Tk. 24,514.19
Rate per sft = Tk. 245.14
Rate per sqm = Tk. 2,638.69
2,639 .00 per sqm
37,000.00 per % 0 nos = Tk. 11,100.00
1,400.00 per % cft = Tk. 52.50
395.00 per bag = Tk. 395.00
70.00 per Ib = Tk. 70.00
126
127
320.00 per day = Tk. 280.00
LS = Tk. 160.00
Sub - Total = Tk. 17,813.50
Profit 10.00% = Tk. 1,781.35
Overhead 3.50% = Tk. 623.47
Total = Tk. 20,218.32
1.06383 6.00% = Tk. 1,290.53
Grand Total = Tk. 21,508.85
Rate per sft = Tk. 215.09
Rate per sqm = Tk. 2,315.23
2,315 .00 per sqm
128
1.06383 6.00% = Tk. 963.42
Grand Total = Tk. 16,056.94
Rate per sft = Tk. 160.57
Rate per sqm = Tk. 1,728.38
1,728 .00 per sqm
13,595.50
= Tk. 3,398.88
129
8,700.00 per % 0 nos = Tk. 6,655.50
1,400.00 per % cft = Tk. 315.00
4,500.00 per % cft = Tk. 1,012.50
395.00 per bag = Tk. 7,110.00
130
200.00 per cft = Tk. 44.00