Project Name: Construction of one floor vertical Extension (3rd Floor)

Project Phase: Finishing


Site Engineer: Md. Asraful Hoque
Weather Condition: Sunny

Manpower Allocation
Sr. No. Task Name: Masonry Carpentry Rebar Concrete
M H M H M H M

Interior Wall Plastering


1 2 2 - - - - -
Window Grill Jamb Plaster
2 2 1 - - - - -

3 - - - - - - -

4 - - - - - - -

5 - - - - - - -

6 - - - - - - -

7 - - - - - - -

8 - - - - - - -

9 - - - - - - -

10 - - - - - - -
TOTAL MANPOWER COUNT: 4 3 0 0 0 0 0
#Special Instructions:

#Additional Notes: 1.Metal anchor for tower & Ac outdoor Platform MS A


2.Electrical Cable & Board or all sort of cable need to r
3.Safety Measures shall follow during Exterior Plaster
Prepared By: Checked By:
UCEP GAZIPUR TVET INSTITUTE
North Salna, Gazipur.
Date:
Shift:
*M=
*H=

power Allocation Challenges/


Achievemets/
Concrete Electrical Plumbing Issues/Area of Upcoming Activities
Progress
H M H M H Concern

Main Service Line for MS Grill Installation


- - - - - 3rd Floor
Steel Shed Installtion
- - - - -
Exterior Wall Plastering
- - - - -
Electrical Work
- - - - -
Thai-Aluminum
- - - - -
Tiles
- - - - -
Louver
- - - - -
Parapet Wall-B/W
- - - - -

- - - - -

- - - - -
0 0 0 0 0

Ac outdoor Platform MS Angle Frame required to remove as early as possible.


r all sort of cable need to remove .
ow during Exterior Plaster Work
Authorized By:
18/12/2023
8:00 AM-05:00 PM
Mason
Helper

Comments