Project Name: Construction of one floor vertical Extension (3rd Floor)

Project Phase: Finishing


Site Engineer: Md. Asraful Hoque
Weather Condition: Sunny

Manpower Allocati
Sr. No. Task Name: Masonry Carpentry Rebar Concrete
M H M H M H M

Earth Excavation For Septic Tank


1 - 6 - - - - -
Exterior Wall Plaster
2 2 2 - - - - -
Tiling Work in Classroom
3 - - - - - - -

4 - - - - - - -

5 - - - - - - -

6 - - - - - - -

7 - - - - - - -

8 - - - - - - -

9 - - - - - - -

10 - - - - - - -
TOTAL MANPOWER COUNT: 2 8 0 0 0 0 0
#Special Instructions:

#Additional Notes: 1.Metal anchor for tower & Ac outdoor Platform MS A


2.Septic tank layout completed today.

Prepared By: Checked By:


UCEP GAZIPUR TVET INSTITUTE
North Salna, Gazipur.

Manpower Allocation Challenges/


Concrete Electrical Tiling Painting Plumbing Achievemets/ Progress Issues/Area of
H M H M H M H M H Concern

- - - - - - - - -

- - - - - - - - -

- - - 3 4 - - - -

- - - - - - - - -

- - - - - - - - -

- - - - - - - - -

- - - - - - - - -

- - - - - - - - -

- - - - - - - - -

- - - - - - - - -
0 0 0 3 4 0 0 0 0

Ac outdoor Platform MS Angle Frame required to remove as early as possible.


ted today.

Authorized By:
Date: 8/1/2024
Shift: 8:00 AM-05:00 PM
*M= Mason
*H= Helper

Upcoming Activities Comments

Steel Shed Installtion

Exterior Wall Plastering

Electrical Work

Thai-Aluminum

Tiles

Louver

Parapet Wall-B/W

uPvc Door Installation

Septic Tank & Soak-Well