CitiHomes Builder & Development Inc.

DATE : July 25, 2019

TO : Ricky G. Celestial
Proprietor – E.G. CELESTIAL CONSTRUCTION & DEVELOPMENT

PROJECT : SABELLA VILLAGE


LOCATION: BRGY. PANUNGYANAN, GEN. TRIAS, CAVITE
SUBJECT : CONSTRUCTION OF CALLISTA MODEL (SA)

Sir,

This is to inform you that the construction of your Callista Model (SA) located at Phase 4
Block 38 lot 16 is fall behind in progress. According to the working calendar days the
completion percentage of your on-going construction must be averaging to 75%, but based on
our assessment, your completion average is very low at 11.07% with a delay percentage of 64%.

In this regard, we hereby instructing you an additional manpower, materials, tools and
equipment to cope the delay and to meet the target date completion. Also submit catch up
schedule.

You are therefore advised to coordinate with the site engineer/project in-charge
regarding this matter.

For your strict compliance.

Maikko Neil Carbonel


Site Engineer, Sabella-CBDI

Noted by:

Engr. Jefferson Jusay


Project In-Charge, Sabella-CBDI

CitiHomes Builder & Development Inc.


DATE : February 7, 2013

TO : Mr. Tony Abante Delas Peñas


Manager – 4655 Builders

PROJECT : AMARIS HOMES


LOCATION: BRGY. MOLINO 4, BACOOR, CAVITE
SUBJECT : CONSTRUCTION OF ELYANA MODEL TH 8

Sir,

This is to inform you regarding the construction of your Elyana Model TH 8 located at
Phase 3 Block 17 lot 1&3,5,7,9,11,13,15,17&19 is very slow moving base on my assessment the
percentage accomplishment is an average of 24%, base on the working calendar days the
percentage of your on-going construction must be averaging of 50.80%.

In this regard we hereby instructing you an additional manpower to cope the delay and to
meet the target date completion and also submit catch up schedule.

You are therefore advised to coordinate with the project engineer/project manager
regarding this matter.

For your strict compliance.

Reden P. Emata
AMRS Project Engr.

Noted by:

Engr. Rio R. Grafilo


CM-South Project
CitiHomes Builder & Development Inc.

DATE : February 7, 2013


TO : Mr. Paul Sicat
Manager – LS Builders

PROJECT : AMARIS HOMES


LOCATION: BRGY. MOLINO 4, BACOOR, CAVITE
SUBJECT : CONSTRUCTION OF ELYANA MODEL TH 8

Sir,

This is to inform you regarding the construction of your Elyana Model TH 8 located at
Phase 3 Block 16 lot 1&3,5,7,9,11,13,15,17&19 is very slow moving base on my assessment the
percentage accomplishment is an average of 32%, base on the working calendar days the
percentage of your on-going construction must be averaging of 52.50%.

In this regard we hereby instructing you an additional manpower to cope the delay and to
meet the target date completion and also submit catch up schedule.

You are therefore advised to coordinate with the project engineer/project manager
regarding this matter.

For your strict compliance.

Reden P. Emata
AMRS Project Engr.

Noted by:

Engr. Rio R. Grafilo


CM-South Project