LAMPRELL ENERGY LTD

Lamprell REQUEST FOR INSPECTION


RFI no: 2006-S003-NBPG-RFI-03784_R00 Project: ARO 2006 Client: ARO

Request Date: 17-May-2021 Date of Inspection: 20-May-2021 Time of Inspection: 13:00

Facility: Hamriyah - Phase I Location: NEW CNC

Request By: Dileepkumar Company: LEL Designation: Quality Inspector

TO: ARO PTC, IMI, ABS CC: ARO DC, IMI, LEL QC, LEL PMT

Equipment
Main Hull scantlings and Framing Equipment Tag No: 01-01-06 Client Discipline: STR
Description:

PO: NAP MR: NAP GRN: NAP

1) BLOCK 2A PANEL P12A (ARO DRG SHEET NO-06 TO 14)

Inspection or
Test Scope:

Inspection or Applicable
Fit up inspection 200-00-00-S003-PRO-51001_R00 In-Process Inspection Procedure
Test Type: Procedure:

ITP LEL/IMI ARO ABS


ITP Reference: Intervention
200-01-01-S003-PLN-51001_R00 Hull Structure-ITP Point: A1 A1 A2

Reference Documentation: ( All documentation necessary to complete the inspection or test e.g. drawings, documentation, procedures, certification,)

2006-01-01-S003-DTL-19723 Assembly drawing

1) Field sheets for pre welding dimension survey verification

2) Material traceability reports to be provided during fit-up inspection.

Acceptance
Criteria: S116E -CTS- REV0- ARO DRILLING 12-Jan-2020 and SHIPBUILDING CONTRACT FOR HULL NO. P20D0001 19-Jan-20

Inspection or Test Report(s) Cross Reference: (Cross References to all documentation used to record the results and findings of the inspection or test e.g. Completed procedures, ITRs, Test charts, Inspection reports
etc.)

Comments:(Any comments relevant to the Inspection or Test with identification of the party making the comment)

Entity LEL IMI ARO TPI ABS

Dileepkumar NAP
Name

QC Inspector NAP
Designation

NAP

Signature

NAP

Official Stamp

NAP
Date

Form: 19/2112/LGQCF031
Rev.: 02
Date: June 2020 Page: __of__