ACAD REMAINING WORKS

TILE WORKS QTY 360.00 SQM

MATERIALS:
60 x 60 Ceramic Tiles 1,000.00 pc/s 180.00 /pc 180,000.00

LABOR:
Tile Setting 1,000.00 pc/s 60.00 /pc 60,000.00

EQUIPMENT:

SUBTOTAL 240,000.00

DOORS AND WINDOWS QTY 1.00 LOT

MATERIALS:
Panel Doors 3.00 set/s 4,500.00 /set 13,500.00
Windows 130.00 sqm 2,500.00 /sqm 325,000.00

LABOR:

EQUIPMENT:

SUBTOTAL 338,500.00

PLUMBING WORKS QTY 1.00 LOT

MATERIALS:
Urinal 4.00 set/s 4,500.00 /set 18,000.00
Water Closet 4.00 set/s 4,500.00 /set 18,000.00
Lavatory 5.00 set/s 4,500.00 /set 22,500.00

LABOR:
Installation 13.00 set/s 1,000.00 /set 13,000.00

EQUIPMENT:

SUBTOTAL 71,500.00

RAILINGS QTY 1.00 LOT


MATERIALS:
Stainless Steel 1.00 set/s 15,000.00 /set 15,000.00

LABOR:
Welding Works 1.00 set/s 6,500.00 /set 6,500.00

EQUIPMENT:

SUBTOTAL 21,500.00

ELECTRICAL WORKS QTY 1.00 LOT

MATERIALS:
Main Line Wires 1.00 set/s 20,000.00 /set 20,000.00

LABOR:
Electrical Works 1.00 set/s 95,000.00 /set 95,000.00

EQUIPMENT:

SUBTOTAL 115,000.00

TOTAL 786,500.00
OCM 78,650.00
GRANDTOTAL 865,150.00