HOMEWORK CHAPTER 9
Problem 15:
a) AON
0 5 11 13 13 18
a 5 d 2 g 5
6 11 11 13 13 18
Start 4 11 11 14
c 7 e 3 Finish
0 4
4 11 11 14
b 4
0 4 4 12 14 18
f 8 h 4
6 14 14 18
0 5 11 12 12 17
a 5 d 2 g 5
6 11 11 12 12 17
17
Start 4 11 11 14
c 7 e 3 Finish
0 4
4 11 11 14
b 4
0 4 4 12 14 17
f 8 h 4
6 14 14 17
New AON after crash activity for b 1 day
0 5 10 11 11 16
a 5 d 2 g 5
5 10 10 11 11 16
16
Start 3 10 10 13
c 7 e 3 Finish
0 3
3 10 10 13
b 4
0 3 3 11 13 16
f 8 h 4
5 13 13 16
e) After that we continue to crash activity b for 1 day because it has the lowest crash cost per
day belong to 2 critical paths and then crash activity c for 1 day.
In the end, we have 2 critical paths : B_C_D_G and B_C_E_H
The total expected time: 14 days
New project cost = 630+ 80 + 90 = 800
0 5 8 9 9 14
a 5 d 2 g 5
3 8 8 9 9 14
14
Start 2 8 8 11
c 7 e 3 Finish
0 2
2 8 8 11
b 4
0 2 2 10 11 14
f 8 h 4
3 11 11 14