Ruj Tuan :
Tarikh : 11/7/2023
PENGARAH
JKR Wilayah Persekutuan Kuala Lumpur,
Tingkat 17, Sunway Putra Tower,
No. 100, Jalan Putra,
50350 Kuala Lumpur WPKL
U/P : YBhg. DATO’ Ir. Hj. NORMAN BIN Hj. MD RABANI
Tuan,
PER: NAIKTARAF JABATAN KECEMASAN HOSPITAL KUALA LUMPUR (REKA & BINA)
- Maklum Balas Penemuan Kabel Sedia Ada di Kawasan ‘Court Yard’ Zon E.
2. Pihak kami Warna Generasi Sdn Bhd telah mengadakan satu sesi lawatan tapak
bersama wakil pihak Jabatan Kerja Raya (JKR), Unit Kejuruteraan Hospital Kuala Lumpur (HKL)
dan juga Tenaga Nasional Berhad (TNB) pada 5 Julai 2023.
3. Selepas perbincangan bersama, pihak Unit Kejuruteraan Hospital Kuala Lumpur (HKL)
telah memaklumkan bahawa lima kabel sedia ada di kawasan Zon E ‘Court Yard’ merupakan
kabel hidup (live) di bawah seliaan pihak mereka. Pihak HKL juga memaklumkan kabel sedia ada
ini ditunjukkan di dalam lukisan utiliti yang di edarkan kepada kami pada 3 Julai 2023. Laporan
terperinci dari pihak unit kejuruteraan Hospital Kuala Lumpur (HKL) masih belum diterima.
4. Sejurus itu, pihak kami dan konsultan elektrik mencadangkan perlindungan untuk kabel
sedia ada yang terdedah (yang kedalaman cetek – 300mm/400mm dari tanah) sebelum kerja
kerja struktur dilakukan. Semasa kerja kerja pelindungan kabel sedia ada dijalankan, pihak kami
memohon supaya kabel tersebut tidak aktif (tiada bekalan pada kabel sedia ada) bagi tujuan
keselamatan para pekerja.
5. Untuk makluman, kerja struktur di kawasan tersebut telah diberhentikan dari tarikh 19
Jun 2023 (tarikh mula makluman penemuan kabel sedia ada) atas faktor keselematan.
6. Bersama ini dilampirkan laporan kabel sedia ada di Zone E ‘Court Yard’ dan Request For
Information (RFIN) kepada konsultan elektrik.
Page 1 of 2
Sekian untuk makluman, terima kasih.
Yang benar,
WARNA GENERASI SDN BHD
…………………………..………….….
Ts. Mohd Fadzley Idzme bin Abdul Razak
Pengurus Projek
s.k
2. UNIT KEJURUTERAAN
HOSPITAL KUALA LUMPUR
50586 Jalan Pahang
U/P : EN FAHRIL
Page 2 of 2
DILAPIDATION REPORT
DILAPIDATION REPORT
1|Page
WGSB DILAPIDATION REPORT
DILAPIDATION REPORT
2|Page
WGSB DILAPIDATION REPORT
1.0 INTRODUCTION
We have found the 5 nos of existing cable at Zone E (Red Zone) during do the excavation
works on 17th June 2023. The existing cable is estimated 300mm/400mm from the existing
ground floor level.
This report is based on a visual inspection on the existing cable, detection works (using
RD8100) and a site visit with representative of Unit Kejuruteraan Hospital Kuala Lumpur
(HKL), Jabatan Kerja Raya (JKR) and Tenaga Nasional Berhad (Distrubution Network – DN).
2. 0 COMMENTARY
The contractor (Warna Generasi Sdn Bhd) needs to do the excavation works at Zone E
(Red Zone) before continue do the structural works (roof footing).
3. 0 ATTACHMENT
3|Page
WGSB DILAPIDATION REPORT
ATTACHMENT
4|Page
WGSB DILAPIDATION REPORT
Figure 1: Site Location View of the A&E Department Building Area
5|Page
WGSB DILAPIDATION REPORT
EXISTING LIVE CABLE
The attachment shown the chronology of found out the existing live cable during excavation
works, a site meeting with representative from Unit Kejuruteraan Hospital Kuala Lumpur (HKL),
and site visit with Jabatan Kerja Raya (JKR) and Tenaga Nasional Berhad (TNB).
Found out the existing cable during excavation works on 17th June 2023
A short site discussion meeting to Unit Kejuruteraan HKL on 19th June 2023. The existing cable is not
shown in their drawing as per discuss at that time.
6|Page
WGSB DILAPIDATION REPORT
The detection works for existing cable on 22th June 2023. The existing cable is on active status (live)
and have been marking the routing in ground.
7|Page
WGSB DILAPIDATION REPORT
1
2
3
4
A site visit with representative from Tenaga Nasinal Berhad (TNB), Jabatan Kerja Raya (JKR) and
Hospital Kuala Lumpur (HKL) on 5th July 2023. TNB clearify that the existing cable is not under their
responsibility as the existing cable is coming from existing substation in Hospital Kuala Lumpur (HKL).
8|Page
WGSB DILAPIDATION REPORT
The existing cable is shown in utility drawing from Unit Kejuruteraan HKL. The drawing was distributed
to WGSB on 3rd July 2023 and HKL already confirmed their existing cable on 5th July 2023.
9|Page
WGSB DILAPIDATION REPORT
Document Ref WGSB/RFIN/KBZ/01
Date 20/6/2023
Page Number
Pihak kami juga telah memaklumkan perkara ini kepada Unit Kejuruteraan Hospital Kuala Lumpur (HKL)
dan telah berbincang mengenai perkara ini pada 19/6/2023. Pihak unit kejuruteraan telah memaklumkan
bahawa kabel yang sedia ada tiada dalam lukisan simpanan pihak mereka.Pihak kami ingin mengetahui
sama ada kabel sedia
ada ini merupakan kabel hidup (live) ataupon tidak supaya kami boleh meneruskan kerja kerja korekan di
kawasan tersebut.
Bersama ini dilampirkan gambar di tapak pembinaan (lampiran 1), lukisan pembinaan yang terjejas
(lampiran 2) dan
gambar perbincangan bersama unit kejuruteraan Hospital Kuala Lumpur (lampiran 3).
Dimohon Oleh Kontraktor: Diterima Oleh:
(Cop Perunding) :
Tandatangan : : Tandatangan :
Nama : : Nama : Ahmad Shahron Amir
Tarikh : : Tarikh : 23/6/2023
1 Merujuk kepada RFI di atas dan laporan pada 22/6/2023 pihak kami menyarankan supaya
pihak wgsb membuat surat kepada pihak Kejuruteraan HKL bagi memastikan kabel
dijumpai yang masih hidup adalah dari MSB/SSB sediada ke SB/DB sediada di mana.
*Borang ini tidak boleh digunakan untuk sebarang tuntutan pertambahan kos dan masa.
NAIKTARAF JABATAN KECEMASAN HOSPITAL KUALA LUMPUR (REKA & BINA)
Lampiran 1
Page 3 of 5
NAIKTARAF JABATAN KECEMASAN HOSPITAL KUALA LUMPUR (REKA & BINA)
Lampiran 2
Kawasan yang terjejas untuk kerja kerja asas tapak (raft footing)
Page 4 of 5
NAIKTARAF JABATAN KECEMASAN HOSPITAL KUALA LUMPUR (REKA & BINA)
Lampiran 3
Page 5 of 5