P.W.D.

Sub-Division Khultabad sanctioned work 5054,03 and 04 Information

Visitted Type of Amount in


R.N. Chainage Work Name Remarks Visitted Engineer's
Date Roads Lakh Rs.
Improvement of road from Kateshevari Fata to Takli Road work not started
34 25/07/2023 20/00 to 23/00 SH-214 Rajarai 250.00 No. of Pothole =13

Construction of minor bridge from Kateshevari Fata to bridge work is in progress. Completed upto slab
11 25/07/2023 24/500 SH-214 100.00
Takli Rajarai level Arman & Eknath
Construction of minor bridge from Takli Rajarai to bridge work is in progress. Completed upto slab
4 25/07/2023 22/400 & 27/00 SH-214 170.00
Dhamangaon level
Improvement of road from Takli Rajarai to Dhamangaon Road work has completed
14 25/07/2023 25/00 to 29/00 SH-214 250.00

Construction of minor bridge from Takli Rajarai to bridge work is in progress. Completed upto slab
28/07/2023 27/00 SH-214
Dhamangaon level
Construction of Improvement of road at road crossing
28/07/2023 29/500 SH-214
from Takli Rajarai to Dhamangaon Road work has not started
4 170.00 Arman & Eknath
Construction of Improvement of road at road crossing
28/07/2023 30/900 SH-214
from Takli Rajarai to Dhamangaon Road work has not started
Construction of Improvement of road at road crossing
28/07/2023 32/300 SH-214
from Takli Rajarai to Dhamangaon Road work has not started
Improvement of road from Jamalwdi to Lamangaon Fata Road work completed but new road surface
15 28/07/2023 29/00 to 32/00 SH-214 250.00 Arman & Eknath
damaged, new pothole = 11
Construction of minor bridge near Dhamangaon -
12 28/07/2023 32/400 SH-214 Vadgaon 150.00 bridge work is in progress. Completed upto slab Arman & Eknath
level but this bridge has constructed at ch33/00
Construction of C.C. Road near Dhamangaon(Wadgaon) Road work has completed
33 28/07/2023 32/00 to 32/400 SH-214 150.00 Arman & Eknath
25 28/07/2023 37/00 to 37/500 SH-214 Construction of C.C. Road near Bodkha 100.00 Road work has completed Arman & Eknath
Construction of minor bridge near Bodkha bridge work is in progress. Completed upto slab
26 28/07/2023 38/580 SH-214 150.00 Arman & Eknath
level LHS wall top cracked due to less curing
Improvement of road from Wadgaon to Jaitkheda Road work has completed upto 1350 m and 150
3 29/07/2023 44/500 to 46/00 SH-214 150.00 Eknath & Arman
m not completed
bridge work is in progress. Completed upto slab
42/580
Construction of minor bridge in Harsul-Jatwada-Jaitkheda level
29 29/07/2023 SH-214 150.00 Eknath & Arman
42/980 Road bridge work has completed
42/480 bridge work has not started
bridge work is in progress. Completed upto slab
43/580
Construction of minor bridge in Harsul-Jatwada-Jaitkheda level
30 29/07/2023 SH-214 150.00 Eknath & Arman
42/980 Road bridge work has completed
42/480 bridge work has not started
Visitted Type of Amount in
R.N. Chainage Work Name Remarks Visitted Engineer's
Date Roads Lakh Rs.
Construction of minor bridge in Harsul-Jatwada-Jaitkheda bridge work is in progress. Completed upto slab
27 29/07/2023 10/500 SH-214 150.00 Eknath & Arman
Road level
Construction of protection wall from Indapur to Bajar Work has not Started
17 30/07/2023 26/00 to 27/00 SH-214 150.00 Eknath & Arman
Sawangi
24/300 Work has not Started
24/900 Work has not Started
25/200 Construction of minor bridge in Chikhalthan-Loni-bodkha- bridge work has completed
28 30/07/2023 SH-219 250 Eknath & Arman
Bajar Sawangi Road bridge work is in progress. Completed upto slab
27/300
level
28/700 Work has not Started
22/300 Work has not Started
22/900 Work has not Started
Construction of minor bridge in Chikhalthan-Loni-bodkha-
6 30/07/2023 25/200 SH-219 250 bridge work has completed Eknath & Arman
Bajar Sawangi Road
25/600 Work has not Started
29/800 bridge work has completed
Improvement of road in Chikhalthan-Loni-bodkha-Bajar Work has not Started no. of pothole = 14
5 30/07/2023 21/500 to 24/00 SH-219 Sawangi Road (from Bodkha to Indapur) 250 1000 m length of existing B.T. has no wearing Eknath & Arman
surface
Improvement of road in Chikhalthan-Loni-bodkha-Bajar Work has not Started no. of pothole = 10
13 30/07/2023 19/00 to 21/500 SH-219 200 Eknath & Arman
Sawangi Road (from Bodkha to Loni)
Improvement of road from Khirdi to Khandi Pimpalgaon Work has not Started no. of pothole = 8
7 31/07/2023 3/300 to 12/00 MDR-59 200 Eknath Kinwad

Minor bridge work has not started


Construction of minor bridge from SH-211 Kajipura
12/150 Eknath Kinwad
Mawsala Khirdi Salukheda SH-214 Golegaon Khandi
16 31/07/2023 MDR-59 250
Pipmpalgaon to SH-216 Sultanpur Kanadgaw to Sawangi
SH Road to MDR-59 Km at ch 12/150 and ch 15/750.
bridge work is in progress. Completed upto
15/750 Eknath Kinwad
Abutment and Pier Level
Improvement of road from SH-211 Kajipura Mawsala Work has not Started
Khirdi Salukheda SH-214 Golegaon Khandi Pipmpalgaon no. of pothole = 5
19 31/07/2023 12/500 to 15/00 MDR-59 to SH-216 Sultanpur Kanadgaw to Sawangi SH Road to 250 Eknath Kinwad
MDR-59 Km at ch 12/500 to ch 15/00. ( from Jafarwadi
to Khandi Pimpalgaon )
Construction of minor bridge from SH-211 Kajipura Minor bridge work has not started
Mawsala Khirdi Salukheda SH-214 Golegaon Khandi
38 31/07/2023 12/150 MDR-59 1500 Eknath Kinwad
Pipmpalgaon to SH-216 Sultanpur Kanadgaw to Sawangi
SH Road to MDR-59 Km at ch 12/150
Construction of minor bridge from SH-211 Kajipura Minor bridge work has not started
Mawsala Khirdi Salukheda SH-214 Golegaon Khandi
39 31/07/2023 13/800 MDR-59 Pipmpalgaon to SH-216 Sultanpur Kanadgaw to Sawangi 250 Eknath Kinwad
SH Road to MDR-59 Km at ch 13/800 (Nnear Khandi
Pimpalgaon)
Visitted Type of Amount in
R.N. Chainage Work Name Remarks Visitted Engineer's
Date Roads Lakh Rs.
Improvement of road from SH-211 Kajipura Mawsala Work has not Started No. of pothole = 11
Khirdi Salukheda SH-214 Golegaon Khandi Pipmpalgaon
20 02/08/2023 15/00 to 19/00 MDR-59 to SH-216 Sultanpur Kanadgaw to Sawangi SH Road to 200 Eknath Kinwad
MDR-59 Km at Ch 15/00 to 19/00 Km ( Khandi
Pimpalgaon to Sultanpur)
Construction of minor bridge from SH-211 Kajipura Work has not started
Mawsala Khirdi Salukheda SH-214 Golegaon Khandi
21 02/08/2023 19/200 MDR-59 Pipmpalgaon to SH-216 Sultanpur Kanadgaw to Sawangi 250 Eknath Kinwad
SH Road to MDR-59 Km at ch 19/200 (near Khandi
Pimpalgaon)
Construction of minor bridge from SH-211 Kajipura Work has not started
Mawsala Khirdi Salukheda SH-214 Golegaon Khandi
22 02/08/2023 18/200 MDR-59 Pipmpalgaon to SH-216 Sultanpur Kanadgaw to Sawangi 250 Eknath Kinwad
SH Road to MDR-59 Km at ch 18/200 (near Khandi
Pimpalgaon)
Improvement of road from SH-211 Kajipura Mawsala 250 m C.C. Road has completed at ch 22/00 in
Khirdi Salukheda SH-214 Golegaon Khandi Pipmpalgaon Kandgaon . Remaing portion 4.750 Km has not
23 02/08/2023 22/00 to 27/00 MDR-59 to SH-216 Sultanpur Kanadgaw to Sawangi SH Road to 250 started. Eknath Kinwad
MDR-59 Km at Ch 22/00 to 27/00 Km (from Kanadgaon
to kanakshil)
Work has not started
Construction of minor bridge from SH-211 Kajipura
Mawsala Khirdi Salukheda SH-214 Golegaon Khandi
32 02/08/2023 25/530 MDR-59 200 Eknath Kinwad
Pipmpalgaon to SH-216 Sultanpur Kanadgaw to Sawangi
SH Road to MDR-59 Km at ch 25/530 (near Kankshil)
Construction of minor bridge from PimpalgaonWalan- Work has not started
8 03/08/2023 0/100 MDR-19 Adgaon Pal Wakod Mahal Kinola to MST-5 to MDR-19 Km 200 Eknath Kinwad
at ch 0/100 (near Bazar Sawangi)
Both Minor bridge work has not started
Improvement of road from Bazar Sawangi to Tajnapur at
Ch 2/00 to 3/00 Km = 1km road work completed .
ch 0/00 to 3/00 and Construction of minor bridge from
9 03/08/2023 0/800 and 1/400 MDR-19 200 Remaining work ch 0/00 Km to 0/200 Km has not Eknath Kinwad
PimpalgaonWalan-Adgaon Pal Wakod Mahal Kinola to
completed . No
MST-5 to MDR-19 Km at ch 0/800 and 1/400
of Pothole = 34
Improvement of road from SH-220 to Ganori to Tajnapur Protection wall work has not started
2/00 TO 3/00
to Shirodi in MDR-14 at ch 2/00 to 3/00 Km and Road Improvement work from ch 2/00 to 3/00 km
37 03/08/2023 &0/800 and MDR-14 200 Eknath Kinwad
Construction of Protection wall from Tajnapur to Shirodi has not started.
1/400
Road in MDR-14 Km at ch 0/950 to 1/150 Km
Construction of Road and Minor Bridge from Mhaismal Road work and Minor bridge has not started Eknath kinwad
48 04/08/2023 3/00 to 7/00 ODR-270 280
to Tisgaon at ch 3/00 to 7/00
Strengthing & Construction of B.T.Road from Tisgaon- Work has not started Eknath kinwad
57 05/08/2023 5/500 to 11/00 ODR-18 Dhamangaon -MDR-59 -to Bazar Sawangi at ch 5/500 to 500 No. of pothole = 33
11/00
Visitted Type of Amount in
R.N. Chainage Work Name Remarks Visitted Engineer's
Date Roads Lakh Rs.
Strengthing & Construction of B.T.Road from NH-752 H Work has not started Eknath kinwad
59 08/08/2023 0/20 to 2/00 ODR-101 150
Vadod Bk. To Kanifnath Temple at ch 0/20 to 2/00 No. of pothole = 4
Strengthing & Construction of B.T.Road from MDR-59 Work has not started Eknath kinwad
60 09/08/2023 1/500 to 3/00 ODR-103 150
Sobalgaon To Padali at ch 1/500 to 3/00 No. of pothole = 8
Work has not started Eknath kinwad
Strengthing & Construction of B.T.Road from Sawangi
49 10/08/2023 0/00 to 1/500 VR-6 105 No. of pothole = 36
Bazar To Shekhpurwadi at ch 0/00 to 1/500 Km
Strengthing & Construction of B.T.Road with Work has not started Eknath kinwad
66 10/08/2023 0/00 to 1/00 VR-7 Construction of Minor Bride from Shekhpurwadi to 100 No. of pothole = 11
Sobalgaon at ch 0/00 to 1/00 Km
Work has not started Eknath kinwad
Construction of Road from Nirgudi Kh. to Palasgaon at ch
62 11/08/2023 0/00 to 3/00 ODR-102 300 No. of pothole = 65
0/00 to 3/00 Km
Totally Damaged patch = 200 m
Improvement of road from MDR-20-Ajampur-Palasgaon- Work has not started Eknath kinwad
Kautgaon to Hatnur at Ch 3/00 to 9/00 km No. of pothole = 62
64 12/08/2023 3/00 to 9/00 ODR-30 25
crust has not available = 1.5 km at ch 7/500 to
9/00 Km
Improvement of road from Verul to Vitkheda at Ch 6/00 Road work haxs not started Eknath kinwad
MDR-58 to 8/500 km No. of Pothole = 36
8 13/08/2023 6/00 to 8/500 396.56
NABARD- Crust is not available = 700 m at ch 7/900 to 8/500
28 Km
MDR-14 Work has not started Eknath kinwad
Construction of Minor Bridge from Tajnapur to Shirodi at
11 14/08/2023 2/400 NABARD- 99.03
ch 2/400 Km
28
Work has not started Eknath kinwad
Strengthing & Construction of B.T.Road from SH-215
58 14/08/2023 0/500 to 2/00 ODR-132 180 No. of pothole = 28
Padali To Daregaon at ch 0/500 to 2/00 Km
W.B.M. Crust available