Toaz - Info DPSB Cms 002 Project Specific Handover Procedure PR
Toaz - Info DPSB Cms 002 Project Specific Handover Procedure PR
Revision A
MAINTENANCE,CONSTRUCTION
& MODIFICATION PROJECT
Printed initials in the approval boxes confirm that the document has been signed. The
originals are held within Document Management.
Project Specific Handover Procedure DPSB-CMS-002
PETRONAS CARIGALI Page 2 of 23
Revision Sheet
CONTENTS
Project Specific Handover Procedure DPSB-CMS-002
PETRONAS CARIGALI Page 3 of 23
1.0 PURPOSE 4
2.0 SCOPE 4
3.0 ABBREVIATIONS 4
4.0 DEFINITIONS 4
12.0 PUNCHLIST 16
13.0 COMMISSIONING 17
20.0 HANDOVER 23
1.0 PURPOSE
Project Specific Handover Procedure DPSB-CMS-002
PETRONAS CARIGALI Page 4 of 23
2.0 SCOPE
3.0 ABBREVIATION
4.0 DEFINITIONS
Operational Test (OTP) - Once all Basic Functions have been tested and
pre start-up activities are completed, major equipment,
system, sub-systems or group of Sub-systems are
subjected to Function/Operational Testing which is to
Demonstrate to the Client that the equipment and
system are ready for a Start Up and normal operation.
First Oil Ready For Start Up - Is when commissioning and functional testing, scraping
and inerting operations for the first have been
completed with a consolidated punch list where there
are no outstanding items that would compromise safe
start-up and First Oil Ready For Operation
Project Specific Handover Procedure DPSB-CMS-002
PETRONAS CARIGALI Page 6 of 23
Initial Acceptance - Is achieved for the Permanent Works when all of the
following conditions have been met:
i) The Permanent Works has been erected in
accordance with the Engineering Record; and
All Works to be performed by Contractor have
been carried out successfully and completed in
full accordance with all requirements set out in
the Contract, and all drawings and
documentation.
Final Acceptance - Is achieved for the Permanent Works upon expiry of the
Defect Notification Period.
Commissioning Dept will have listed and numbered all the systems, they will
also produce the priority list for system completion. This priority list is critical in
order to keep to a minimum the pre-commissioning and commissioning
periods. This is critical to achieving Turnover to the Client as early as
possible. DPSB Construction and the Sub Contractors are required to
complete the installation and pre commissioning testing of these critical
systems required for FORFS
Project Specific Handover Procedure DPSB-CMS-002
PETRONAS CARIGALI Page 7 of 23
6.3 The completion activities are separated into the following phases:
• Technical preparation.
• Construction, Installation
• Pre-Commissioning
• M.C.
• Commissioning.
• Start-Up.
• Operations & Maintenance
• Training
The general purpose of any commissioning phase of any Oil and Gas EPC Project is
to demonstrate the reliability, integrity and functionality of the relevant equipment and
system(s). The following activities are to be performed by the Commissioning Team:
The Utilities and Process facilities will be segregated into "Systems" and "Sub
Systems" in order to identify a methodical approach to Commissioning & Start Up. A
priorities list will be identified and issued to all departments, sub-contractors to
facilitate the Systems Pre-commissioning and Commissioning sequence for Early
Start Up.
Pre Commissioning checks/tests are generally carried out by a team of discipline tech
engineers from the Construction team, with QC Inspectors which verify the tests have
been completed Commissioning support, direct the Pre-commissioning and will
witness key pre-commissioning activities in order to reduce time for hand over at MC
from Construction to Commissioning. To facilitate the commissioning of a system or
partial system, detailed reviews are required to ensure that commissioning and start
up can take place in a safe controlled manner whilst other systems are still under
Construction e.g.
Pre Commissioning is the static and de-energized tests, which are carried out
in accordance with the Project technical specifications and Vendor's'
Project Specific Handover Procedure DPSB-CMS-002
PETRONAS CARIGALI Page 11 of 23
Within a system, the equipment plus it's component parts, are visually
checked by QC & Commissioning. Also the systems piping, instruments,
packages, cables, vessels, etc., will be checked visually to verify,
installation is complete, the condition of the equipment, are in compliance
with Project drawings and specifications. Vessels; where entry is possible
they shall be internally inspected using the AFC, GA drawings for internal
fittings also a cleanliness check will be undertaken.
Typical tests carried out on pipe work are, hydro testing, pneumatic tests, air
or water flushing I cleaning, leak tests, inerting. Conformity checks, static tests
and de-energised tests shall be carried out in accordance with, and reported
on the relevant check sheets I test sheets. The appropriate checksheet form
will be used relevant to each discipline, by System/Subsystem these
discipline. The detailed procedures for testing will be developed as for the
project, typically mechanical, piping, cabling, power, instruments and
equipment. These procedures will comply with to project specification. These
activities will be recorded on test sheets and also marked on the relevant
P&ID and piping isometrics. Once the Pre commissioning activities are
Project Specific Handover Procedure DPSB-CMS-002
PETRONAS CARIGALI Page 12 of 23
completed and all Category-A punch list items are cleared, then the SYSTEM
I SUBSYSTEM will have achieved MECHANICAL COMPLETION.
Checks shall be carried out Onshore and Offshore for each system/sub-
system to visually verify the condition of the equipment, the quality of the
installation, the compliance with drawings, specifications, manufacturers'
instructions, safety rules, codes, and standards. Flooding, Cleaning, Gauging,
Hydrostatic Testing, Calliper Pig Run, Dewatering operations shall be
performed by a specialist sub-contractor. All of these activities will be witness
by DPSB & Client nominated responsible person(s).
The following is a typical list of checks the list is a guide and not exhaustive:
• All instruments are installed taking into account the offshore prevailing
wind direction as designed in the installation specification.
Project Specific Handover Procedure DPSB-CMS-002
PETRONAS CARIGALI Page 13 of 23
• All the instruments are in position. In case of any issue I HOLD, they
shall be resolved and installation shall be completed before
proceeding with the PRE COMMISSIONING activities.
• The instruments are properly supported, free from vibration,
accessible and correctly oriented for operation and maintenance
purposes.
• All the in-line instruments including the in-line Flow Meters, Control
Valves, Actuated on-off Valves, Safety Relief Valves, Rupture Discs,
Pressure Instruments, Temperature Instruments, and Level
Instruments etc. are properly installed with supports.
• All the electronic instruments and panels are provided with sunshades,
as per drawings I documents.
• All instruments are well preserved.
• All the field instruments are calibrated (where possible) as per data
sheets and range I set points are verified.
• Wherever required the field instruments junction boxes are earthed
properly.
• All the VENDOR and third party inspection (if applicable) certification
documents are available.
• All cable run, tray work and tie wrapping are completed and the cables
are properly terminated, glanded, and cable earth loops are provided.
• All process impulse tubes and pneumatic tubes have been installed,
connected and secured as per hook-up drawings.
• All the instruments are properly tagged.
• There is no structural interference to the opening of the panel I box
doors and ease of operation & maintenance of the instruments and
local panels I boxes.
• There is no physical damage to the field instruments and panel I
boxes.
• All the extra cables and materials I accessories have been removed.
The typical types of instrumentation checks/tests include but not limited to the
following:
• Pressure Gauge
• Pressure Transmitter I Level Transmitter I Flow Transmitter
• Temperature Gauge.
Project Specific Handover Procedure DPSB-CMS-002
PETRONAS CARIGALI Page 14 of 23
• Temperature Transmitter.
• Thermowells I Temperature Elements.
• Analyzers.
• Level Gauges (with and without transmitter)
• Pressure Control Valve and Flow Control Valve and Level Control
Valves.
• Temperature Control Valve
• Orifice Plates (Flow I Restriction)
• Pressure Safety Valve.
• Valve Position Switches (Limit switch)
• Control valve loop functions.
8.7 Electrical
The following is a typical list of installation checks the list is a guide and not
exhaustive:
• All electrical cables are installed as per spec.
• Check that the trays are well supported.
• Check that all electrical equipment is supported.
• Check that all the electrical equipment I control instruments are p
roperly tagged.
• Check that there is no interference to ease of operation and
maintenance of the equipment including the panels.
• Check that the field control stations are well supported.
• Check the device I equipment for correct rating, voltage etc. as
per drawings.
• Check that the extra cables have been removed. The following is a
typical list of tests and checks detailed procedures using as built
drawing engineering docs and vendor docs will be produced for such
as:
• The earthing system, installation is complete, in accordance with the
project specifications and drawings.
• The installation is complete and is in accordance with the drawings &
Specifications.
• All the third party inspection certification & documents are available (if
applicable).
• Check the quality of installation, recommend corrections where
Project Specific Handover Procedure DPSB-CMS-002
PETRONAS CARIGALI Page 15 of 23
necessary.
• Check that all cable runs are completed identified, and terminations
have been completed.
Any energized, pre livening up tests will use certified test equipment.
Where partial systems have been identified for early commissioning and
startup, a detailed review with HSE review will be carried out. This is to
ensure that the system or partial system can be energized safely, whilst
construction, takes place on the rest of the system The review will cover HSE
requirements for positive isolations typically, Tag & Lockout, Spading Lists,
Double block bleed, chained and or locked equipment. The PTW
Procedure/system must also be robust enough to reflect the changes in
plant/system status, going from construction to commissioning.
equipment/package has been SAT/SIT, all the loops function tested, the test
records/sheets will be signed by the concerned parties. All of the activities will be
done in accordance with "Installation, Commissioning, Operation and Maintenance
Manual" from the VENDOR. The System Design Manual provided by the Vendor
shall contain all relevant information pertaining to the design and operation of the
delivered equipment and system.Vendor documentation, FAT's procedures ect, will
be required as early as possible by DPSB Commissioning Dept for producing
procedures and reviewing SAT and requirements. Any vendors Punch lists are
required to be transmitted to LO as early as possible.
HSE will review the early oil requirements with Commissioning, ensuring any
temporary signs, equipment, escape routes are in place in time. The Safety plot plan
drawings will be checked to ensure that portable fire extinguishers and safety
equipment are supplied as per contract, installed at the correct location as per project
specifications I drawings and VENDOR instructions, and that they are easily
accessible I operable during an emergency.
12.0 PUNCHLIST
Punch listing will follow an approved procedure and all defective items listed.
Subsequent correction work will be coordinated through the DPSB Construction
responsible persons. Once construction, sub contractor's or the vendors have cleared
the punched item(s), a site visit with the Client, QC or Commissioning discipline
engineer will verify that the items has been cleared, once verified as being cleared
they will sign off the form and the cleared punch item(s) listed on Master Punch list
held in the data base.
Project Specific Handover Procedure DPSB-CMS-002
PETRONAS CARIGALI Page 17 of 23
13.0 COMMISSIONING
Once System Mechanical Completion has been achieved and the Mechanical
Completion Certificate has been signed off, the system shall be considered "Ready
for Commissioning". Responsibility for that portion of the plant is transferred from the
Construction Department to the Commissioning Department. A Handover Certificate
for each discipline will be forwarded to COM, which will list installation and tests,
relevant to that system have all been completed witnessed signed off.
"Commissioning" means all Energized tests, function testing and activities associated
with preparing a system or facility for startup and operations.
During this phase, the Electrical Equipment is finally energized; Instrument Loops and
all equipment within the systems are energized, pressurized and functionally tested.
The Commissioning Discipline Engineer and his team, Vendors or when required,
Specialist Sub Contractors shall demonstrate the function testing to the Client.
Commissioning is divided into activities/steps for which reports/documents shall be
generated for each System/Sub-System. The general activities/steps for the
Commissioning stage are presented in the following paragraphs along with the
required reports, which shall be generated to certify the completion of each activity.
This work shall include items listed under the Contract Document and comprise all
steps required to make the system ready for commissioning.
A Ready for Startup Notice/Acceptance will be issued by the Client to DPSB for each
process system, when it judges that all commissioning activities have been
completed and the system is ready for startup and Introduction of Hydrocarbons. This
will follow an approved procedure and HSE requirements.
The Punch List Management procedure will be developed and submitted for approval
to the Client, The approved Punching Management procedure is executed in
conjunction with Contractors Construction, Quality Dept, Vendors, and
Commissioning Department. The Procedure will typically cover the organization and
the establishment of Punch List Management control, and clearance protocols for all
Onshore and Offshore Pre-Commissioning and Commissioning activities.
of each noted Punch-list item, one of the following three Punch-list categories
A, B or C.
Category A:
Category B:
Final Commissioning.
• These, Punch List items which shall be cleared prior to applying for the
Ready For Startup Certificate for each System/Sub-System.
Category C:
17.3 Clearance
The relevant constructions disciplines will clear the Punched items. When the
item(s) are cleared the QC or Commissioning responsible person(s) will verify
the items has been attended to and signed it off the item.
All the Punch Lists forms are considered to be reference documents and shall
be filed in specific system Punch List dossiers sorted alpha numerically. This
list will be updated as punched items are cleared and signed off
DPSB shall provide as per the Contract to the Employer for review and approval as a
minimum:
• Commissioning Plan;
• Integrated Systems Completion Schedule up to issue of Certificate of
Completion;
• Schedule for Contractor Home Office work and deliverables;
• Marked-up P&IDs showing preliminary System Selection;
• Marked-up P&IDs showing Systems' definitions, details and
• Detailed equipment lists for each System, listing all items;
• System Completion Manuals;
• Pre-Commissioning, Commissioning, Start-up and Initial
operation procedures;
• System dossiers for each Systems Vendor Attendance Schedule and
responsibilities;
• Interface procedures between Commissioning, Construction and
Employer's Operation & Maintenance team;
• Procedures for Punch Management, Hydro testing & cleaning vessels,
pipe work, loading and unloading of chemicals as required by
Employer and Vendors;
• Identify utility consumption, other materials and equipment,
and Subcontractors' work required for Pre-Commissioning,
Commissioning and plan for their availability;
Project Specific Handover Procedure DPSB-CMS-002
PETRONAS CARIGALI Page 22 of 23
The Project milestone "FIRST OIL READY FOR START-UP" will be achieved when
all of the required function testing and commissioning for the first pipeline, associated
and partial systems are completed. Punch lists are cleared; there are no outstanding
items that would compromise safe start-up and operation.
When DPSB considers that all the contractual requirements for the FORFSU, all sub-
systems/systems are completed, and a joint HAZOP review for Hydrocarbons
introduction has been conducted for the FORFSU, then FIRST OIL READY FOR
START UP has been achieved.
DPSB shall send a notice "FIRST OIL READY FOR START UP CERTIFICATE" (To
Be developed and approved) to the Employer/CLIENT. When considers that the all
the remaining works associated with the Permanent Works has been completed the
"OVERALL READY FOR START UP" they will then submit to the Employer. A notice
"OVERALL READY FOR START UP CERTFICATE"(To be developed and approved)
stating that the Permanent Works have achieved Overall Ready for Start Up.
Project Specific Handover Procedure DPSB-CMS-002
PETRONAS CARIGALI Page 23 of 23
DPSB shall manage and carry out all necessary work(s) until the acceptance of "First
Oil Ready for Startup Certificate" up to the date of acceptance by the Employer of
Overall Ready For Start Up for Permanent Works, the Client/Employer
representative(s) will take over the care, custody and control of the Permanent Works
respectively.
20.0 HANDOVER
When the entire facility has been completed and operated by DPSB for 30 days as
per contract;
• Engineering.
• Civil.
• Construction.
• QA & QC Documents.
• System Dossiers.
• Vendor's, Sub Contractors Documents.
• O & M Manuals.
• As Built Drawings, Tech Reports.