You are on page 1of 3

Republic of the Philippines

Department of Education
Region Vlll
Division of Samar
STA. MARGARITA 1 CENTRAL ELEMENTARY SCHOOL
Sta. margarita 1

PROJECT PROPOSAL

School: STA. MARGARITA 1 CENTRAL ELEMENTARY SCHOOL


School ID: 123738
District: Sta. Margarita 1
Project Title: Elevating the Flooring of the Grade 3 School
Prepared for Department of Education-Division of Samar

RATIONALE:

Sta. Margarita 1 Central Elementary School is often used as venues for meetings, sport fest, DFOT,
be it a district, a cluster and a division level.
One of the major concern is that our kitchen facility is unserviceable , its roof is dilapidated and the
floors are rough. We cannot offer a functional one when ever we have visitors and our school is used as
venue. In order that this facility to become functional , there must be an allocation from school fund to be
used for repair , that’s why this proposal is made in order to realize this project.

BACKGROUND

Sta. Margarita 1 Central School has long been always used as venues for any activities since it is the
center and accessible place nearest to Calbayog area. Because of this, teaching staff always have to get
ready especially its facilities , that anytime the school will used as venue , we can offer a functional facility
Just like our school kitchen , since its not serviceable, when the school is used as billeting we cannot offer
our kitchen, instead they used other classrooms as kitchen.
It has been the desire and of the administrator to repair this facility, but due to lack of fund the plan
did not materialized.
PICTORIALS OF TARGET AREAS/LOCATION OF THE PROJECT
OBJECTIVES:

The project proposal is an answer to the above mention issue of the school. The school teaching
personnel believes that this repair will make the functional and serviceable, specifically, the project aims to:
1. Repair of school kitchen
2. Minimize food purchases outside when there is visitor instead just cook it in the kitchen.
3. Add functionality of school facilities

SOURCE OF FUND/OTHER AGENCIES INVOLVED:


ADDITIONAL MOOE
MATERIALS NEEDED AND BUDGET
Materials Quantity Amount No. of Days Total
Needed for
Completion
Sack of cements 10 290 2900
Sand 1cu.m. 1600 1600
plywood 10 sheets 490 4900
2x2x6 good lumber 10 pcs 550 5500
Common nails 1’ 1kg 100 100
Common nails 2’ 1kg 100 100
Common nails 3’ 3kg 100 300
Common nails 4’ 4kg 100 300
GI sheets 20pcs (8’) recycled ----
Umbrella nails 3’ 3kg 150 450
2x3x8 10pcs recycled ----
Vulca seal 1l. 600 600
Red oxide 1 gal 1800 1800
Sub total 18,250
Labor Cost 5475
Grand Total 23,750
Prepared by:

JOCELYN C. TABOGOC MA GENES P. ORBASE


ESP ll AO ll/Property Custodian

PUREZA E. MENDOZA AGNES S. TOMALE


MT 1/Disbursing Office MT ll/ Sch. Inspectorate

APPROVED: MARITESS C. PERALTA


District In Charge