JOB CARD PACKAGE TITLE: CES -

Installation of the MLG Bay Fire-Detector Tail Number - MSN -


FSN
ALL

MPD Reference Title DocType


A350-
NONE A-26-11-15-02001-720A- Installation of the MLG Bay Fire-Detector Line Maintenance
A

Job Cards Package is made of: 1 job cards.

JCP Title: Installation of the MLG CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 1 of 2
Bay Fire-Detector PRINT DATE: Jan 11/2024
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
JOB CARD PACKAGE TITLE: CES -
Installation of the MLG Bay Fire-Detector Tail Number - MSN -
FSN
ALL

INTENTIONALLY LEFT BLANK

JCP Title: Installation of the MLG CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 2 of 2
Bay Fire-Detector PRINT DATE: Jan 11/2024
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
JOB CARD REV DATE: Jan 01/2024
Line Maintenance - CES - A350 TASK:
A350-
A-26-11-15-02001-720A-
A
MAINTENANCE
PROCEDURE
Tail Number - MSN - TITLE:
MPD TASK:
FSN: A350-A-26-11-15-02001-720A-A - Installation of the MLG Bay NONE
ALL Fire-Detector

MECH. INSP.

DM status information

DM Code : A350-A-26-11-15-02001-720A-A
Airline : CES
Issue Number : 011
Issue Date : Mar 01/23
Breakdown Title : Detector - Fire, MLG Bay
DM Title : Installation of the MLG Bay Fire-Detector
Applicability : ON A/C MSN ALL
Aircraft Type : A350
DM Producer : FAPE3
Language : Simplified English
Copyright : A350-A-00-65-XX-10000-021A-D

ON A/C MSN ALL


TASK A350-A-26-11-15-02001-720A-A
Installation of the MLG Bay Fire-Detector
FIN: 2WP 3WP 4WP 5WP

WARNING: MAKE SURE THAT THE SAFETY DEVICES AND THE WARNING
NOTICES ARE IN POSITION BEFORE YOU START A TASK ON OR
NEAR:
-THE FLIGHT CONTROLS
-THE FLIGHT CONTROL SURFACES
-THE LANDING GEAR AND RELATED DOORS
-THE CARGO DOORS
-THE ENGINES
-OTHER COMPONENTS THAT MOVE.
MOVEMENT OF COMPONENTS CAN KILL OR CAUSE INJURY TO
PERSONS AND/OR DAMAGE TO EQUIPMENT.

WARNING: BE CAREFUL WHEN YOU USE CONSUMABLE MATERIALS. OBEY


THE MATERIAL MANUFACTURER INSTRUCTIONS AND YOUR
LOCAL REGULATIONS.

JCP Title: Installation of the MLG CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 1 of 11
Bay Fire-Detector PRINT DATE: Jan 11/2024
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
JOB CARD REV DATE: Jan 01/2024
Line Maintenance - CES - A350 TASK:
A350-
A-26-11-15-02001-720A-
A
MAINTENANCE
PROCEDURE
Tail Number - MSN - TITLE:
MPD TASK:
FSN: A350-A-26-11-15-02001-720A-A - Installation of the MLG Bay NONE
ALL Fire-Detector

MECH. INSP.
1. General

A. Reason for the Job


Self Explanatory

2. Job Set-Up Information

A. Work Zones.

ZONE ZONE DESCRIPTION


CENTER WING BOX,AIR CONDITION AND
HYDRAULIC COMPARTMENT; MAIN
LANDING GEAR BAY,FWD PRESSURE
BULKHEAD OF WING CENTER BOX TO
140
FORWARD PARTITION OF AFT CARGO
COMPARTMENT, FUSELAGE AREA
BETWEEN CENTER WING BOX AND
PASSENGER COMPARTMENT FLOOR

B. Fixtures, Tools, Test and Support Equipment.

REFERENCE QTY DESIGNATION


HARNESS,SAFETY
98L12003001000 AR

SAFETY CLIP - CIRCUIT BREAKER


No Specific AR

ACCESS PLATFORM 3M (10 FT)-


No Specific 1 ADJUSTABLE

CAP - BLANKING
No Specific AR

C. Consumable Materials.

JCP Title: Installation of the MLG CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 2 of 11
Bay Fire-Detector PRINT DATE: Jan 11/2024
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
JOB CARD REV DATE: Jan 01/2024
Line Maintenance - CES - A350 TASK:
A350-
A-26-11-15-02001-720A-
A
MAINTENANCE
PROCEDURE
Tail Number - MSN - TITLE:
MPD TASK:
FSN: A350-A-26-11-15-02001-720A-A - Installation of the MLG Bay NONE
ALL Fire-Detector

MECH. INSP.

REFERENCE QTY DESIGNATION


04QAB2 AR Coating_- Flexible Structure
Polysulfide Sealant_Low Density Multi
06ACA1 AR
Purpose Brushable -

D. Referenced Information.

REFERENCE DESIGNATION
A350-A-12-XX- MP - Safety Attachment Points in the MLG
XX-04ZZZ-170Z-A Bay
A350-
MP - Preparation for Bonding with Screws/
A-20-51-20-05ZZZ-25
Bolts and Anchor Nuts
0Z-A
A350-
MP - Bonding Completion with Sealant and
A-20-51-20-03ZZZ-25
Blue Paint (Varnish)
BZ-A
A350- MP - Check of the Bonding Value by Four-
A-20-51-20-00ZZZ-34 Point Method with Low-Current Test Method
BZ-A M1
A350-A-24-41- MP - De-energize the Aircraft Electrical
XX-00ZZZ-561Z-A Circuits from External Power Receptacle 1
A350-A-24-41- MP - Energize the Aircraft Electrical Circuits
XX-00ZZZ-761Z-A from External Power Receptacle 1
A350-A-24-71-
MP - Get Access to "C/B Management"
XX-00ZZZ-170Z-A
A350-A-26-11- MP - Visual Inspection of the Fire Detectors of
XX-00ZZZ-310Z-A the Main Landing Gear Bay (MLGB)
A350-A-32-12-
MP - Open the MLG Doors for Maintenance
XX-00ZZZ-397Z-A
A350-A-32-12-
MP - Close the MLG Doors after Maintenance
XX-01ZZZ-397Z-A

JCP Title: Installation of the MLG CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 3 of 11
Bay Fire-Detector PRINT DATE: Jan 11/2024
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
JOB CARD REV DATE: Jan 01/2024
Line Maintenance - CES - A350 TASK:
A350-
A-26-11-15-02001-720A-
A
MAINTENANCE
PROCEDURE
Tail Number - MSN - TITLE:
MPD TASK:
FSN: A350-A-26-11-15-02001-720A-A - Installation of the MLG Bay NONE
ALL Fire-Detector

MECH. INSP.

MP - Get Access to the "MAINTENANCE


A350-A-45-XX-
HOME PAGE" Page and to the Maintenance
XX-00ZZZ-132Z-A
Applications
A350-A-45-XX-
MP - Close Maintenance Session
XX-00ZZZ-133Z-A

3. Job Set-Up
SUBTASK 261115-10100030001
A. Aircraft Maintenance Configuration
(1) Make sure that the aircraft electrical circuits are energized
Ref. MP A350-A-24-41-XX-00ZZZ-761Z-A.

(2) On a maintenance terminal, get access to the “MAINTENANCE


HOME PAGE”
Ref. MP A350-A-45-XX-XX-00ZZZ-132Z-A.

(3) On the “MAINTENANCE HOME PAGE”, select “C/B


Management”
Ref. MP A350-A-24-71-XX-00ZZZ-170Z-A.

SUBTASK 261115-86500020001
B. Make sure that the circuit breaker(s) that follow(s) is (are) open,
safetied/locked and tagged. Use the SAFETY CLIP - CIRCUIT
BREAKER as necessary.

PANEL DESIGNATION FIN LOCATION


FOR FIN 2WP (DET-FIRE,MLG BAY R LOOP A), 3WP (DET-
FIRE,MLG BAY L LOOP A)
CBP1 C/B-CM/A MLG BAY 3201WP 5AA04
FOR FIN 4WP (DET-FIRE,MLG BAY R LOOP B), 5WP (DET-
FIRE,MLG BAY L LOOP B)
CBP2 C/B-CM/B MLG BAY 3202WP 6AA15

SUBTASK 261115-10100060001

JCP Title: Installation of the MLG CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 4 of 11
Bay Fire-Detector PRINT DATE: Jan 11/2024
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
JOB CARD REV DATE: Jan 01/2024
Line Maintenance - CES - A350 TASK:
A350-
A-26-11-15-02001-720A-
A
MAINTENANCE
PROCEDURE
Tail Number - MSN - TITLE:
MPD TASK:
FSN: A350-A-26-11-15-02001-720A-A - Installation of the MLG Bay NONE
ALL Fire-Detector

MECH. INSP.

C. Get Access
(1) Make sure that the MLG doors are open for maintenance Ref.
MP A350-A-32-12-XX-00ZZZ-397Z-A.

(2) Make sure that the ACCESS PLATFORM 3M (10 FT)-


ADJUSTABLE is in position at zone 140 to get access to the
MLG bay.

WARNING: YOU MUST PUT ON AND ATTACH A SAFETY


HARNESS BEFORE YOU START WORK:
-IN THE NLG OR MLG BAYS
-ON THE THS OR IN THE REAR FUSELAGE
-ON TOP OF THE WINGS OR PYLONS
-ON THE VERTICAL STABILIZER.
WITHOUT A SAFETY HARNESS, YOU CAN FALL.
THIS CAN KILL YOU OR CAUSE YOU INJURY.

(3) Put on and attach the HARNESS,SAFETY (98L12003001000)


before you start work in the work area
Ref. MP A350-A-12-XX-XX-04ZZZ-170Z-A.

4. Procedure
Ref. Fig. MLG Bay Fire-Detectors

SUBTASK 261115-40100020001
A. Installation of the MLG Bay Fire-Detector
(1) Do a visual inspection and clean the component interfaces and
the adjacent area.

(2) Make sure that the parts retained from the removed component
are clean and in the correct condition.

(3) Prepare the electrical bonding of the responder assembly (5)


with the clamps (1), the washers (2) and the bolts (3)
Ref. MP A350-A-20-51-20-05ZZZ-250Z-A.

JCP Title: Installation of the MLG CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 5 of 11
Bay Fire-Detector PRINT DATE: Jan 11/2024
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
JOB CARD REV DATE: Jan 01/2024
Line Maintenance - CES - A350 TASK:
A350-
A-26-11-15-02001-720A-
A
MAINTENANCE
PROCEDURE
Tail Number - MSN - TITLE:
MPD TASK:
FSN: A350-A-26-11-15-02001-720A-A - Installation of the MLG Bay NONE
ALL Fire-Detector

MECH. INSP.

(4) Install the clamps (1) in the correct position on the responder
assembly (5).

NOTE: If the clamps (1) are in the correct position, the


sensing element (6) will correctly align with all the
clamps (8).

(5) Put the responder assembly (5) in position on the support (10).

(6) Install the washers (2) and the bolts (3) on the clamps (1).

(7) Tighten the bolts (3).

(8) Put the bushings (9) on the sensing element (6).

CAUTION: REMOVE OR INSTALL THE SENSING ELEMENTS


CAREFULLY. DO NOT TWIST, BEND OR CAUSE
KINKS IN THE SENSING ELEMENTS.

(9) Install the sensing element (6) with the bushings (9) on the
clamps (8).

(10) Close the clamps (8) and lock them with the fasteners (7).

CAUTION: DO NOT USE ELECTRICAL OR PNEUMATIC


TOOLS TO LOOSEN OR TIGHTEN THE QUARTER-
TURN SCREWS ON THE FIRE DETECTOR CLAMP.
ONLY USE A MANUAL SCREWDRIVER.
ELECTRICAL OR PNEUMATIC TOOLS WILL
CAUSE THE SCREW TO TURN TOO MUCH AND
POSSIBLY TO BREAK.

(11) Turn the fasteners (7) one quarter turn clockwise.

JCP Title: Installation of the MLG CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 6 of 11
Bay Fire-Detector PRINT DATE: Jan 11/2024
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
JOB CARD REV DATE: Jan 01/2024
Line Maintenance - CES - A350 TASK:
A350-
A-26-11-15-02001-720A-
A
MAINTENANCE
PROCEDURE
Tail Number - MSN - TITLE:
MPD TASK:
FSN: A350-A-26-11-15-02001-720A-A - Installation of the MLG Bay NONE
ALL Fire-Detector

MECH. INSP.

(12) Remove the CAP - BLANKING from each electrical connector


and receptacle. Make sure that all the electrical connections
are clean and in the correct condition.

CAUTION: MAKE SURE THAT THE ELECTRICAL


CONNECTORS AND RECEPTACLES ARE CLEAN
BEFORE YOU CONNECT THEM. CONTAMINATION
ON THE ELECTRICAL CONNECTORS CAN CAUSE
DAMAGE TO THE EQUIPMENT.

(13) Connect the electrical connector (4) to the responder assembly


(5).

CAUTION: CAREFULLY OBEY ALL THE INSTRUCTIONS OF


THE BONDING TEST. IF YOU DO NOT OBEY THEM
CAREFULLY, THE FIRE DETECTOR WILL NOT BE
SERVICEABLE.

(14) Do a check of the bonding value Ref. MP A350-


A-20-51-20-00ZZZ-34BZ-A.

(15) Make sure that the bonding value is not more than 10
milliohms.

(16) Complete the electrical bonding procedure of the responder


assembly (5) as follows:

(a) On the bolts (3), the washers (2) and the clamps (1)
Apply a thin layer of 06ACA1 (Polysulfide
Sealant_Low Density Multi Purpose Brushable -), then
apply a layer of 04QAB2 (Coating_- Flexible Structure)
Ref. MP A350-A-20-51-20-03ZZZ-25BZ-A.

SUBTASK 261115-86500030001

JCP Title: Installation of the MLG CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 7 of 11
Bay Fire-Detector PRINT DATE: Jan 11/2024
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
JOB CARD REV DATE: Jan 01/2024
Line Maintenance - CES - A350 TASK:
A350-
A-26-11-15-02001-720A-
A
MAINTENANCE
PROCEDURE
Tail Number - MSN - TITLE:
MPD TASK:
FSN: A350-A-26-11-15-02001-720A-A - Installation of the MLG Bay NONE
ALL Fire-Detector

MECH. INSP.

B. Remove the tag(s) and/or the SAFETY CLIP - CIRCUIT BREAKER and
close/unlock this (these) circuit breaker(s):

PANEL DESIGNATION FIN LOCATION


FOR FIN 2WP (DET-FIRE,MLG BAY R LOOP A), 3WP (DET-
FIRE,MLG BAY L LOOP A)
CBP1 C/B-CM/A MLG BAY 3201WP 5AA04
FOR FIN 4WP (DET-FIRE,MLG BAY R LOOP B), 5WP (DET-
FIRE,MLG BAY L LOOP B)
CBP2 C/B-CM/B MLG BAY 3202WP 6AA15

SUBTASK 261115-50000010001
C. Do the visual inspection of the MLGB fire detectors Ref. MP A350-
A-26-11-XX-00ZZZ-310Z-A.

5. Close-Up
SUBTASK 261115-10200020001
A. Close Access
(1) Make sure that the work area is clean and clear of tools and
other items.

(2) Close the MLG doors after maintenance Ref. MP A350-


A-32-12-XX-01ZZZ-397Z-A.

SUBTASK 261115-10200030001
B. Put the aircraft back to its initial configuration.
(1) Remove all the fixtures, tools, test and support equipment used
during this procedure.

(2) Close the maintenance session


Ref. MP A350-A-45-XX-XX-00ZZZ-133Z-A.

(3) De-energize the aircraft electrical circuits


Ref. MP A350-A-24-41-XX-00ZZZ-561Z-A.

JCP Title: Installation of the MLG CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 8 of 11
Bay Fire-Detector PRINT DATE: Jan 11/2024
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
JOB CARD REV DATE: Jan 01/2024
Line Maintenance - CES - A350 TASK:
A350-
A-26-11-15-02001-720A-
A
MAINTENANCE
PROCEDURE
Tail Number - MSN - TITLE:
MPD TASK:
FSN: A350-A-26-11-15-02001-720A-A - Installation of the MLG Bay NONE
ALL Fire-Detector

MECH. INSP.

Figure ICN-A350-A-261115-A-FAPE3-006W9-A-002-01 SHEET 1/2 - MLG Bay


Fire-Detectors
Figure ICN-A350-A-261115-A-FAPE3-006WA-A-002-01 SHEET 2/2 - MLG Bay
Fire-Detectors

JCP Title: Installation of the MLG CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 9 of 11
Bay Fire-Detector PRINT DATE: Jan 11/2024
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
JOB CARD REV DATE: Jan 01/2024
Line Maintenance - CES - A350 TASK:
A350-
A-26-11-15-02001-720A-
A
MAINTENANCE
PROCEDURE
Tail Number - MSN - TITLE:
MPD TASK:
FSN: A350-A-26-11-15-02001-720A-A - Installation of the MLG Bay NONE
ALL Fire-Detector

MECH. INSP.

E E

B E

E
C
B
D

E B

Figure ICN-A350-A-261115-A-FAPE3-006W9-A-002-01 (SHEET 1/2) - MLG Bay Fire-


Detectors
ON A/C MSN ALL

JCP Title: Installation of the MLG CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 10 of 11
Bay Fire-Detector PRINT DATE: Jan 11/2024
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
JOB CARD REV DATE: Jan 01/2024
Line Maintenance - CES - A350 TASK:
A350-
A-26-11-15-02001-720A-
A
MAINTENANCE
PROCEDURE
Tail Number - MSN - TITLE:
MPD TASK:
FSN: A350-A-26-11-15-02001-720A-A - Installation of the MLG Bay NONE
ALL Fire-Detector

MECH. INSP.

3
2
1

9
4 6
6

C
7

8 8
7
9
6
8
7
9
6
6
9

6
D 9

8 7

Figure ICN-A350-A-261115-A-FAPE3-006WA-A-002-01 (SHEET 2/2) - MLG Bay Fire-


Detectors
ON A/C MSN ALL
© *** END OF CARD ***

JCP Title: Installation of the MLG CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 11 of 11
Bay Fire-Detector PRINT DATE: Jan 11/2024
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE