You are on page 1of 20

SALIENT FEATURES

Page 1 of 20
SALIENT FEATURES

:
Name of the Project Authority Shree Godham Mahatirth Pathmeda
:
Name of the state Rajasthan
:
Name of the District Sanchore
:
Name of the Location Nandgaon
:
Name of the Progremme Rain water Harvesting Scheme
:
Name of the Location Shree Manorama Golok Tirth

Annual Rain fall of the city


: 760.02 mm

Total Number of Structure (Tin Shade & Buildings) : 59 Nos

No of CWR's
: 3 Nos

CWR-1 3600 KL

CWR-1 4500 KL

CWR-1 4500 KL

No of OHSR
: 3 Nos

Raw Water Reservoir (Talab)


: 1 Nos

No of Pump House : 1 Nos

Pumping Plant of Tube well

a) No. and Type of Plant : 1 Number of Submersiblw Pump

b) Anticipated Discharge : 500 LPM

c) Total working Head : 29 m

d) Motor (HP) : 10.0 HP

Service Storage

a) Quantity : 3 No.

b) Capacity : 100 KL

c) Staging : 18 m

Pipeline Summary
Table 1: Rising Main Summary
Diameter
Pipeline Type Material Class Length (m)
(mm)-OD
Rising Mains HDPE Pipe PN-6 PE100 110 1000
Total Length (m) 1000
Above length also includes By-Pass

Table 4: Collection Pipe Summary


Pipeline Type Material Class Dia in mm Length in m
Collection Pipe PVC-O pipe Class 500 PN-16 110 5000.00
Collection Pipe PVC-O pipe Class 500 PN-16 160 2000.00
Total Length (m) 7000.00

Page 2 of 20
PROJECT
TECHNICAL REPORT

Page 3 of 20
Zone-1 Area 91 & 107 of BARSANA DIVISION
Rain Water harvesting potential Calculation:-

(A.) Building and Tin Shade

S. No Tin Sheds No. Size (in Ft) Size (sq ft) Approx. Size (sq mtr) Approx.
1 36 121' x 91' 11,011 1,023.0
2 37 181' x 91' 16,471 1,530.2
3 38 122' x 91' 11,102 1,031.4
4 39 73'6" x 39' 2,886.50 268.2
5 40 74' x 39' 2,886 268.1
6 41 73'6" x 39' 2,886.50 268.2
7 42 74' x 39' 2,886 268.1
8 43 74' x 40' 2,960 275.0
9 44 74' x 40' 2,960 275.0
10 45 73'9" x 40'6' 2,987 277.5
11 46 74' x 40'6' 2,997 278.4
12 47 74' x 40' 2,960 275.0
13 A 74' x 40' 2,960 275.0
14 B 74' x 40' 2,960 275.0
15 C 74' x 35' 2,590 240.6
16 48 74' x 40' 2,960 275.0
17 49 74' x 35' 2,590 240.6
Approx 79,053 sft 7,344.3

Rain Water harvesting potential = Rain Fall (mm) x collection efficien


Annual Rain fall of the city = 760.02 mm

Total Catchment area = 7,344 Sqm

Height of rain fall = 0.76 m


Vol of Rain fall over the tin shed = Area Plot x height of rain fall
Vol of Rain fall over the tin shed = 5,582 cum
= 55,81,788 liters

Calculation for effectively harvested water from total rainfall

(i) Considering roof catchment is having tin shade (Corrugated metal sheets) so coefficient for roof surface can
be adopted as 0.8 (Ref Table No.2)

(ii) Another constant coefficient for evaporation, spillage and first flush wastage can be considered as 0.80 (for
all situations)

Statistically and approximately only effectively harvested water quantity may be considered as = Rain water
endowment of that area ('A') x 0.80 x Surface efficient (to be obtained from Table no.2)
= 5581788 x 0.80 x 0.80
= 35,72,344 liters
Say = 3,600 KL

Therefore, 1 underground and open service reservoir (Diggi) of 3600 kl capacity has been proposed in the
campus.

Page 4 of 20
Length of downpipe for each Tin Shed = 5m
No of downpipe for each Tin Shed = 2 Nos
Average discharge in each downpipe = 5581.79/17/2
= 164.17 cum
Assume Maximum peak discharge hours in pipe network = 4.00 cum
Average discharge in each downpipe per hour = 164.17/4
= 41.04 cum
Recommended Velocity = 1.50 m/s
Dia required = SQRT((41.04/3600)/1.5*4/PI())*1000
= 98.37 mm
Pipe Proposed = 110.00 mm

Page 5 of 20
Zone-2 Ramanreti West & North-West Area -1 (114,
115,128,129,118 & 119)
Rain Water harvesting potential Calculation:-

(i) Area 114


(A.) Building and Tin Shade Area 114 (Gosewa Sadan)

S. No Tin Sheds No. Size (in Ft) Size (sq ft) Approx. Size (sq mtr) Approx.
1 4 70' x 36' 2,520 936.5
Approx 2,520 936.5

(ii) Area 118


(A.) Building and Tin Shade Area 118 (Prjapati)

S. No Tin Sheds No. Size (in Ft) Size (sq ft) Approx. Size (sq mtr) Approx.
1 2 85' x 35' 2,975 552.8
Approx 2,975 552.8

(B.) Building and Tin Shade Area 118 (Shri Gve)

S. No Tin Sheds No. Size (in Ft) Size (sq ft) Approx. Size (sq mtr) Approx.
1 2 85' x 35' 2,975 552.8
Approx 2,975 552.8

(C.) Building and Tin Shade Area 118 (Vatsala)

S. No Tin Sheds No. Size (in Ft) Size (sq ft) Approx. Size (sq mtr) Approx.
1 2 85' x 35' 2,975 552.8
Approx 2,975 552.8

(D.) Building and Tin Shade Area 118 (Rohini)

S. No Tin Sheds No. Size (in Ft) Size (sq ft) Approx. Size (sq mtr) Approx.
1 2 85' x 35' 2,975 552.8
Approx 2,975 552.8

(iii) Area 119


(F.) Building and Tin Shade Area 119 (Harisanidhay Karini)

S. No Tin Sheds No. Size (in Ft) Size (sq ft) Approx. Size (sq mtr) Approx.
1 2 85' x 35' 2,975 552.8
Approx 2,975 552.8

(G.) Building and Tin Shade Area 119 (Ananta)

S. No Tin Sheds No. Size (in Ft) Size (sq ft) Approx. Size (sq mtr) Approx.
1 2 85' x 35' 2,975 552.8
2 1 99' x 32' 3,168 294.3
3 1 98'6" x 31' 3,054 283.7
Approx 9,197 552.8

Page 6 of 20
(iv) Area 120
(F.) Building and Tin Shade Area 120

S. No Tin Sheds No. Size (in Ft) Size (sq ft) Approx. Size (sq mtr) Approx.
1 11 88' x 35' 3,080 3,147.6
2 1 63' x 35' 2,205 204.9
Approx 5,285 3,352.4

(v) Area 121


(F.) Building and Tin Shade Area 120

S. No Tin Sheds No. Size (in Ft) Size (sq ft) Approx. Size (sq mtr) Approx.
1 12 88' x 35' 3,080 3,433.7
Approx 3,080 3,433.7

Total Structure = 42
Rain Water harvesting potential = Rain Fall (mm) x collection efficiency
Annual Rain fall of the city = 760.02 mm

Total Catchment area = 11,039 Sqm

Height of rain fall = 0.76 m


Vol of Rain fall over the tin shed = Area Plot x height of rain fall
Vol of Rain fall over the tin shed = 8,390 cum
= 83,90,016 liters

Calculation for effectively harvested water from total rainfall

(i) Considering roof catchment is having tin shade (Corrugated metal sheets) so coefficient for roof surface can be
adopted as 0.8 (Ref Table No.2)

(ii) Another constant coefficient for evaporation, spillage and first flush wastage can be considered as 0.80 (for all
situations)

Statistically and approximately only effectively harvested water quantity may be considered as = Rain water
endowment of that area ('A') x 0.80 x Surface efficient (to be obtained from Table no.2)
= 8390016 x 0.80 x 0.80
= 53,69,610 liters
Say = 5,400 KL

Therefore, 1 underground and open service reservoir (Diggi) of 5400 kl capacity has been proposed in the campus.

Length of downpipe for each Tin Shed = 5m


No of downpipe for each Tin Shed = 2 Nos
Average discharge in each downpipe = 8390.02/42/2
= 99.88 cum
Assume Maximum peak discharge hours in pipe network = 4.00 cum
Average discharge in each downpipe per hour = 99.88/4
= 24.97 cum
Recommended Velocity = 1.50 m/s
Dia required = SQRT((24.97/3600)/1.5*4/PI())*1000
= 76.73 mm
Pipe Proposed = 110.00 mm

Page 7 of 20
Shree Manorama Golok Tirth
RAIN WATER COLLECTION TANK (DIGGI)
Demand = 14 ML
Detention Time = 1 Days
Required Capacity of RWR = 14 ML
Say ~ 14 ML
Dimensions of RWR
Slope = 1:2
Height of Water = 4m
Horizontal Length of Slope in water = 6.00 m
Top Length at Water Top = Lt = 82.5 m
Top Width at Water Top = Bt = 55 m
Bottom Length at Water Bottom = Lb = 70.50 m
Bottom Width at Water Bottom = bb = 43.00 m

Area of Top A1 = 4537.50 m2


Area of Bottom A2 = 3031.5 m2
H = 4m

Volume = H/3 x (A1 + A2 + sqrt(A1 x A2))


Volume = 15037.11 m3

Evaporation Loss = 0 mm/day


Total Loss in 1 Day = Evaporation Loss per day x Area at Top
= 0/1000 x 4537.5
Total Loss in 1 Day as Evaporation = 0 m3
Total Loss in 1 Day as Evaporation = 0 m3

Net Volume of RWR = 15037.11 - 0


= 15037.11 m3
i.e. = 15.0 ML
> 14 ML
Hence OK

Taking Free Board = 1m


Total Height of RWR = 5m
Net Length Slope of RWR (Horizontal) = 10 m
Top Length at Water Top = L = 90.50 m
Top Width at Water Top = B = 63.00 m

Page 8 of 20
Note: Solar panels shall be installed to meet power requirements for intermediate stage, subject to availability of the required land
area in the premises.

1.8 Head of Pumping Plant

Total Head of pumping plant has been worked out as below:

Head calculation
Sr.No. Particulars Head Unit

A Static Head m

1 Depth of water label below G.L. 4 m

Sub-Total 4 m

Static Head/friction losses Above ground Level m

4 Staging of O.H.T. 18 m

5 Depth of water in tank 4.5 m

6 Friction losses in rising main & fitting 0.08 m

7 Terminal Head 1 m

8 Losses in the Pipe 1 m

Sub-Total 24.58 m

Total 28.58 m

Say 29 m

Note: Depth of water availability below ground level may vary depending upon the actual water level at that particular location of
drilling, which will lead to change in required pump head.

Pumping Plant

At the tubewell Submersible type pumping plant have been provided of following rating

Required discharge 500 LPM

Pump Discharge 500 LPM

Pump Operating head 29 M

Pump Break Horse Power = (QxH)/(4500X67%) 4.81 HP

1 H.P. = 0.7457 KW 3.59 KW

Multiplying factor for BKW to decide motor rating (as per manual of Water Supply Treatment Table11.4) 1.4 5.02 KW

6.73 HP

Adopting available submersible pump motor HP from SOR 10.0 HP

Note:- The Motor Capacity & combine efficiency may vary as per pump and motor manufacturer. Hence manufacturers motor
capacity and combined efficiency will be considered as final.

Page 9 of 20
ESTIMATES

Page 10 of 20
Estimate of Construction of Rain Water Harvesting System of Shree Manorama Golok Tirth

Item BSR-JPR Particulars of items and details of works No. Length,m Bredt Height Quantity Unit Rate Amount
No. CLAUSE h,m or
Depth,
m
A. Civil Works
1 PHED BSR Earth work in excavation by mechahical means
2021\4.1 (Hydraulic Excavator )/ manual means in trenches of
required width and gradient for laying and jointing
of pipe line including excavation for sockets, and
dressing of sides, ramming-of bottoms, depth up to
1.S Mtr. including taking out the excavated soil, and
then returning the soil as required in layers not
exceeding 20cm in depth including consolidating
each deposited layer by ramming, watering etc. and
disposal of surplus excavated soil as directed within a
lead of 50 Mtr. including required all safety provisions
etc.:
AII kinds of soil

Excavation of trench for pipe laying 1 8000.00 0.41 1.11 3640.80


3640.80 Cum
PHED BSR ordinary soil 2912.64 Cum 172 500974.08
2021\4.1
PHED BSR ordinary rock 728.16 Cum 322 234467.52
2021\4.1

2 PHED BSR Dismantling of cement concrete pavement for 364.08 Cum 653 237744.24
2021\4.5 pipe line line and chambers by mechanical means
using pneumatic tools, cutting the peripheral edge by
CC cutter, breaking to pieces not exceeding 0.02 cum
in volume and stock piling at designated locations and
disposal of dismantled materials up to a lead of
1000 meters Measurement for dismantled trench
to be made as per standard trench width specified
in tender document and no extra payment shall be
made be made for trench width more than
specified, re-handling of material/earth to
complete the tasks as per technical specification and
scope of work.

10% of earth work Quantity


3 PHED BSR Dismantling of flexible pavement for pipe line line
2021\4.6 and chambers by mechanica means using pneumatic
tools, breaking to pieces not exceeding 0.02 cum in
volume and stock piling at designated locations and
disposal of dismantled materials up to a lead of 1000
meters. Measurement for dismantled trench to be
made as per standard trench width specified in
tender document and no extra payment shall be
made be made for trench width mure than specified,
re- handling of material/earth to complete the tasks
per technical specification and scope of work.

PHED BSR 10% of earth work Quantity 364.08 Cum 362 131796.96
2021\4.6.1

Page 11
4 PHED BSR Construction of RCC Circular Clear Water Reservoirs
2019/3.2 of required capacity including excavation in all types
of strata, foundation concrete, container walls,
bottom slab, top roof slab / dome, 20 mm thick
cement plaster with water proofing compound in CM
1:3 proportion and food grade epoxy paint to inner
face of the container and dome/slab, including
refilling and disposing of surplus stuff , all labour and
material charges, providing and fixing accessories
such as M.S./Alluminium ladder/RCC Stairs inside and
outside, manhole frame and cover, puddle collar,
ventilators, satisfactory hydraulic test and water
tightness test as per IS code and providing three coats
of cement paints to all exposed surface of structure
including dome, etc. complete in all respect as per
design data, criteria, obligatory requirements and
detailed specifications, scope of work and GA drawing.
The job include painting the name of the scheme and
other details on the reservoir and any other work
related to structure as per the directions of Engineer-
in- Charge, Technical Specification and Scope of Work.
The rate indicated below are excluding the cost of
pipes, specials and valves required for inlet, outlet,
washout, overflow arrangement.

3.2.4 For capacity above 2500 KL and up to 4000 KL.


3600 kl 1 3600.00 3600 Litre 3.5 12600000
4500 kl 1 4500.00 4500 Litre 3.5 15750000
4500 kl 1 4500.00 4500 Litre 3.5 15750000

5 1.29 Providing, lowering, laying and jointing in trenches,


standard lengths ISI marked Rigid PVC-O S/S Pipes
(push on joints) as per IS-16647: 2017 (amended
upto date) with EPDM Gasket seals on joints
including all taxes , transportation and freight
charges, inspection charges, loading/ unloading
charges, stacking of pipes, laying of pipes, including
cost of labour and material, specials (Tee, bend
etc.), satisfactory hydraulic testing, disinfection
etc. complete as per technical specifications and
01:29:01 PVC-O pipe Class 500 PN-16
1.29.1.1 110 mm 1 5000.00 5000 rmt 959 4795000.00
1.29.1.2 160 mm 1 2000.00 2000 rmt 1558 3116000.00

6 uPVC/ PVC Pipes (Class- 3/ 4) specials


5% of pipe cost 1 395550.00

7 RUIDP Design, construction, (including topographical survey,


2022\19.106 geotechnical investigation and other surveys as
required) for specified capacity of WTP based on 22
Hrs. operation including inlet chamber, aeration
fountain / cascade, inlet channels including
mechanical/manual fine/coarse screens, flash mixer,
mixing channel with Parshall flume and flow
measuring arrangement, clariflocculator with
conventional, filter house and filter plant including

Page 12
back wash tank and back wash pumps with 100%
standby, chemical house, coagulant feed tank with
feed mechanism, poly aluminium chloride (PAC) or
other coagulant tank of specified capacity and nos.
with mixing and dosing arrangement complete,
vacuum feed gas chlorinator with 100% standby,
sludge handling unit and recycling of collected water
from sludge, clear water reservoir of specified
capacity, clear water
pumping station including specified number and
capacity of pumps, motors, panels, starters, cables,
transformers, etc. complete, external and internal
electrification, laboratory building with all specified
lab equipment, admin building, Quarter (One no.),
sanitary block with necessary water supply and
drainage arrangement, campus roads, landscaping
and other campus development works, rain water
harvesting etc. all required works complete as per the
direction of Engineer-in-Charge

19.106.1 5 MLD 1 1.00 1 LS 3,00,00,000 30000000.00

8 Unit Estimate Construction of Rain Water Harvesting System of Tin


Shade
59 1.00 59 Job 90,808 5357677.90
9 Following rates are for seismic zone II. For zone III,
these rates shall be increased by 5% and for zone IV,
these rates shall be increased by 10%. Concerned
Executive Engineer shall confirm the seismic zone for
the scheme from seismic zones plan before
estimation and adopt appropriate rates as per actual
seismic zones.

3.1.2.1 100 KL capcity 3 100.00 300 Litre 15.5 4650000

10 Unit Estimate RAIN WATER COLLECTION TANK (DIGGI) 1 1.00 1 Job 56,50,524 5650523.91

11 Supply & Installation of 3 phase ISI marked


submersible motor pump set of three star or better
rating of BEE and as per IS: 8034-2018 (pump) and IS
9283- 2013 (motor) or as amended up to date of
approved make of following duty condition with
required accessories including making connection
suitable for tube well/DCB. The job includes
lowering of motor pump, installation of complete
fitting & accessories, jointing of electrical cables up
to switch board, testing of submersible pump set
and interconnection up to water mains, complete in
all respect.

2.15.4 7.5 KW (10 HP) & head above 120 mtr. 1 7.50 7.5 kw 7330 54975000

Grand Total of RWH system Cost 154144734.6


Grand Total of RWH system Cost, in crore 15.41

Page 13
Estimate of Construction of Rain Water Harvesting System of Area 91 & 107 of BARSANA DIVISION

Item BSR-JPR Particulars of items and details of works No. Length,m Bredt Height Quantity Unit Rate Amount
No. CLAUSE h,m or
Depth,
m
A. Civil Works
1 PHED BSR Earth work in excavation by mechahical means
2021\4.1 (Hydraulic Excavator )/ manual means in trenches of
required width and gradient for laying and jointing
of pipe line including excavation for sockets, and
dressing of sides, ramming-of bottoms, depth up to
1.S Mtr. including taking out the excavated soil, and
then returning the soil as required in layers not
exceeding 20cm in depth including consolidating
each deposited layer by ramming, watering etc. and
disposal of surplus excavated soil as directed within a
lead of 50 Mtr. including required all safety provisions
etc.:
AII kinds of soil

Excavation of trench for pipe laying 1 1000.00 0.41 1.11 455.10


455.10 Cum
PHED BSR ordinary soil 364.08 Cum 172 62621.76
2021\4.1
PHED BSR ordinary rock 91.02 Cum 322 29308.44
2021\4.1

2 PHED BSR Dismantling of cement concrete pavement for 45.51 Cum 653 29718.03
2021\4.5 pipe line line and chambers by mechanical means
using pneumatic tools, cutting the peripheral edge by
CC cutter, breaking to pieces not exceeding 0.02 cum
in volume and stock piling at designated locations and
disposal of dismantled materials up to a lead of
1000 meters Measurement for dismantled trench
to be made as per standard trench width specified
in tender document and no extra payment shall be
made be made for trench width more than
specified, re-handling of material/earth to
complete the tasks as per technical specification and
scope of work.

10% of earth work Quantity


3 PHED BSR Dismantling of flexible pavement for pipe line line
2021\4.6 and chambers by mechanica means using pneumatic
tools, breaking to pieces not exceeding 0.02 cum in
volume and stock piling at designated locations and
disposal of dismantled materials up to a lead of 1000
meters. Measurement for dismantled trench to be
made as per standard trench width specified in
tender document and no extra payment shall be
made be made for trench width mure than specified,
re- handling of material/earth to complete the tasks
per technical specification and scope of work.

PHED BSR 10% of earth work Quantity 45.51 Cum 362 16474.62
2021\4.6.1

Page 1 4 of
4 PHED BSR Construction of RCC Circular Clear Water Reservoirs
2019/3.2 of required capacity including excavation in all types
of strata, foundation concrete, container walls,
bottom slab, top roof slab / dome, 20 mm thick
cement plaster with water proofing compound in CM
1:3 proportion and food grade epoxy paint to inner
face of the container and dome/slab, including
refilling and disposing of surplus stuff , all labour and
material charges, providing and fixing accessories
such as M.S./Alluminium ladder/RCC Stairs inside and
outside, manhole frame and cover, puddle collar,
ventilators, satisfactory hydraulic test and water
tightness test as per IS code and providing three coats
of cement paints to all exposed surface of structure
including dome, etc. complete in all respect as per
design data, criteria, obligatory requirements and
detailed specifications, scope of work and GA
drawing. The job include painting the name of the
scheme and other details on the reservoir and any
other work related to structure as per the directions
of Engineer- in- Charge, Technical Specification and
Scope of Work. The rate indicated below are
excluding the cost of pipes, specials and valves
required for inlet, outlet, washout, overflow
arrangement.

3.2.4 For capacity above 2500 KL and up to 4000 KL.


3600 kl 1 3600.00 3600 Litre 3.5 12600000

5 1.29 Providing, lowering, laying and jointing in trenches,


standard lengths ISI marked Rigid PVC-O S/S Pipes
(push on joints) as per IS-16647: 2017 (amended
upto date) with EPDM Gasket seals on joints
including all taxes , transportation and freight
charges, inspection charges, loading/ unloading
charges, stacking of pipes, laying of pipes, including
cost of labour and material, specials (Tee, bend
etc.), satisfactory hydraulic testing, disinfection
etc. complete as per technical specifications and
01:29:01 PVC-O pipe Class 500 PN-16
1.29.1.1 110 mm 1 700.00 700 rmt 959 671300.00

6 uPVC/ PVC Pipes (Class- 3/ 4) specials


5% of pipe cost 1 33565.00

7 Unit Estimate Construction of Rain Water Harvesting System of Tin


Shade
17 1.00 17 Job 90,808 1543737.70
8 Following rates are for seismic zone II. For zone III,
these rates shall be increased by 5% and for zone IV,
these rates shall be increased by 10%. Concerned
Executive Engineer shall confirm the seismic zone for
the scheme from seismic zones plan before
estimation and adopt appropriate rates as per actual
seismic zones.

3.1.2.1 100 KL capcity 1 100.00 100 Litre 15.5 1550000

Grand Total of RWH system Cost 16536725.6


Grand Total of RWH system Cost, in crore 1.65

Page 1 5 of
Unit Estimate of Construction of Rain Water Harvesting System of Tin Shade
Item BSR-JPR Particulars of items and details of works No. Length,m Bredt Height Quantity Unit Rate Amount
No. CLAUSE h,m or
Depth,
m
A. Civil Works
1 RUIDP SOR Providing and fixing 15 cm wide 45 cm over all semi
2022/31.7 circular plain G.S. sheet gutter with iron brackets
40x3mm size, bolts, nuts and washers etc. including
making necessary connections with rain water pipes
complete.
31.7.1 0.80mm thick with zinc coating not less than 1 80.00 80.00 metre 768 61440.00
275gm/m²

2 RUIDP SOR Providing and fixing 100 mm diameter and 60 cm long


2022/31.37 rain water spout in cement mortar 1:4 (1 cement : 4
fine sand)

31.37.1 Stone ware spout 1 4.00 4.00 each 85.9 343.60


3 RUIDP SOR Providing and fixing M.S. holder bat clamps of
2022/31.38 approved design to C.I. or S.C.I. rain water pipes
embedded in and including cement concrete blocks
10x10x10cm of 1:2:4 mix (1 cement : 2 coarse sand
: 4 graded stone aggregate 20 mm nominal size) and
cost of cutting holes and making good the walls etc. :

31.38.1 100 mm diameter 1 10.00 10.00 each 237.5 2375.00

4 RUIDP SOR Providing and fixing on wall face Unplasticised Rigid


2022/31.41 PVC Single socketed pipes rain water pipes
conforming to IS : 13592 Type A including jointing
with seal ring conforming to IS : 5382 leaving 10 mm
gap for thermal
expansion.
31.41.2 110 mm diameter 1 10.00 10.00 metre 303 3030.00

5 RUIDP SOR Providing and fixing on wall face Unplasticised - PVC


2022/31.42 moulded fittings/ accessories for Unplasticised Rigid
PVC rain water pipes conforming to IS : 13592 Type A
including jointing with seal ring conforming to IS :
5382 leaving 10 mm gap for thermal expansion.

31.42.1 Coupler
31.42.1.2 110 mm 1 15.00 15.00 each 175 2625.00
31.42.3 Single tee with door
31.42.3.2 110x110x110 mm 1 15.00 15.00 each 363.5 5452.50
31.42.5 Bend 87.5°
31.42.5.2 110 mm bend 1 4.00 4.00 each 158 632.00
31.42.6 Shoe (Plain)
31.42.6.2 110 mm Shoe 1 4.00 4.00 each 357.5 1430.00

Page 1 6 of
6 RUIDP SOR Constructing brick masonry chamber for underground
2022/35.16 C.I. inspection chamber and bends with 75 class
designation bricks in cement mortar 1:4 (1 cement : 4
coarse sand) C.I. cover with frame (light duty)
455x610 mm internal dimensions, total weight of
cover with frame to be not less than 38 kg (weight of
cover 23 kg and weight of frame 15 kg) R.C.C. top slab
with 1:2:4 mix (1 cement :2 coarse sand : 4 graded
stone aggregate 20 mm nominal size) foundation
concrete 1:5:10 (1 cement : 5 fine sand : 10 graded
stone aggregate 40 mm nominal size), inside
plastering 12 mm thick with cement mortar 1:3 (1
cement : 3 coarse sand) finished smooth with a
floating coat of neat cement on walls and bed
concrete etc. complete as
per standard design :
35.16.3 Inside dimensions 600x 850 mm and 45 cm deep for
pipe line with three or more inlets :
35.16.3.1 With bricks 1 2.00 2.00 each 6740 13480.00

Grand Total of RWH system Cost 90808.1

Page 1 7 of
Shree Manorama Golok Tirth
RAIN WATER COLLECTION TANK (DIGGI) Quantity Calculation
S.No. Particulars Unit Qty
Excavation
1 Storage Tank Earth work in excavation over area ( for Sedimentation cum
storage tank) Exceeding 30 cm in depth 1.5 Mtrs in width as well as 10 Sqm
on plan) including disposal of excavated earth lead up to 50 M and all lift.
Disposed earth to be levelled and neatly dressed including stacking of useful
material if any available during excavation for all kind of soil. Earth work to
be carried out by means of mechanical system i.e. Tractor craw or any other
mechanical system. No extra payment shall be done for lift of any limit. This
work also involves dressing of sides and bottom for lining purpose which is
to be done manually, slope of sides to be maintained as per specification.
Work is to be done as per direction of
Engineer In Charge and technical specifications.

Height of Excavation metre 4


Horizontal Length of Excavation metre 8
Bottom Length metre 70.50
Bottom Width metre 43.00
Top Length metre 87
Top Width metre 59
Top Area A1 sqm 5104
Bottom Area A2 sqm 3032
Volume of Excavation = H/3 x (A1 + A2 + sqrt(A1 x A2)) cum 16091 16091.14
Area for Lining
2 SINGLE FLAT BRICK LINING WITH 250 MICRON LDPE FILM:- Preparing surface
levelled and dressed to proper slope and laying over it on sand properly
rammed and watered in 2 Layers of 5 cm each. Providing and laying 250
micron LDPE film as per ISS:2506-1984 including overlapping on the finished
surface of compacted sand. Over LDPE film 15 mm thick cement sand
mortar 1:3 shall be provided and laid which shall be cured properly. Over
the base mortar single layer Ist class brick lining in cement sand mortar 1:3
shall be provided with joints not more than 8 mm wide and curing shall be
done for 14 days. This also includes providing weedicides and anti-termite
treatment, complete work as per
technical specifications.
Horizontal Length of Slope metre 10
Slope length = sqrt ( LxL + HxH) metre 11.18
Considering Extra Length on Single Side metre 3.00
Bottom Length metre 70.50
Bottom Width metre 43.00
Top Length of Brick Lining metre 99
Top Width of Brick Lining metre 71
Area of Lining sqm 7055 7054.77

Site Clearance
3 Clearing and grubbing road land including uprooting rank vegetation, grass,
bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of
trees cut earlier and disposal of unserviceable materials and stacking of
serviceable material to a lead of 50 metres from road boundary including
removal and disposal of top organic
soil not exceeding 150 mm in thickness as directed by Engineer.
Length of Land metre 191
Width of Land metre 163
Area of Land sqm 31051.50
Minus Area of RWR 90.5 x 63
Minus Area of RWR sqm 5701.50
Net Area sqm 25350
Hect 2.54 2.54

Page 18 of
S.No. Particulars Unit Qty
Turfing
4 Turfing slopes of new banks with rough grassing including preparation of
ground by loosening soil with kassi, flooding with water, rough dressing, fine
dressing, supplying and spreading farm yard manure at the rate of 0.18 cum
per 100 sqm and supplying and
planting doob grass roots at 15 cm apart, complete.

Height of RWR above GL metre 1


Considering Slop of 1: 2
Horizontal Length of Slope metre 2.00
Slope Length metre 2.24
Perimeter Length metre 97
Perimeter Width metre 69
Total Perimeter Length = 2 x (length + Width) metre 331.00
Surface Area for Turfing = Slop Length x Perimeter sqm 740.14 740.14

Page 19 of
Shree Manorama Golok Tirth

RAIN WATER COLLECTION TANK (DIGGI)

S.No. Name of BSR BSR Item No Particulars Unit L (m) B (m) D (m) Qty Rate Amount

1 PHED 12.1 Storage Tank Earth work in excavation over area ( for Sedimentation cum
Pipeline BSR storage tank) Exceeding 30 cm in depth 1.5 Mtrs in width as well as 10
2022-2023 Sqm on plan) including disposal of excavated earth lead up to 50 M and
all lift. Disposed earth to be levelled and neatly dressed including
stacking of useful material if any available during excavation for all kind
of soil. Earth work to be carried out by means of mechanical system i.e.
Tractor craw or any other mechanical system. No extra payment shall be
done for lift of any limit. This work also involves dressing of sides and
bottom for lining purpose which is to be done manually, slope of sides to
be maintained as per specification. Work is to be done as per direction of
Engineer In Charge and technical specifications.

Excavation cum 16091 16091.14 92.0 14,80,384.55

2 PHED 12.3 SINGLE FLAT BRICK LINING WITH 250 MICRON LDPE FILM:- Preparing
Pipeline BSR surface levelled and dressed to proper slope and laying over it on sand
2022-2023 properly rammed and watered in 2 Layers of 5 cm each. Providing and
laying 250 micron LDPE film as per ISS:2506-1984 including overlapping
on the finished surface of compacted sand. Over LDPE film 15 mm thick
cement sand mortar 1:3 shall be provided and laid which shall be cured
properly. Over the base mortar single layer Ist class brick lining in cement
sand mortar 1:3 shall be provided with joints not more than 8 mm wide
and curing shall be done for 14 days. This also includes providing
weedicides and anti-termite treatment, complete work as per technical
specifications.

SINGLE FLAT BRICK LINING WITH 250 MICRON LDPE FILM sqm 7055 7054.77 551.0 38,87,175.69

3 ISOR 2022 2.3 Clearing and grubbing road land including uprooting rank vegetation,
RUIDP grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of
stumps of trees cut earlier and disposal of unserviceable materials and
stacking of serviceable material to a lead of 50 metres from road
boundary including removal and disposal of top organic soil not
exceeding 150 mm in thickness as directed by Engineer.

2.3.1 Site Clearance Light Jungle Hectare 2.5 2.54 56,000.0 1,41,960.00

4 ISOR 2022 39.17 Turfing slopes of new banks with rough grassing including preparation of
RUIDP ground by loosening soil with kassi, flooding with water, rough dressing,
fine dressing, supplying and spreading farm yard manure at the rate of
0.18 cum per 100 sqm and supplying and
planting doob grass roots at 15 cm apart, complete.
39.17.2 of New Banks sqm 740.14 740.14 55.40 41,003.67

5 Add for illumination Lump-Sum 1,00,000.00

TOTAL 56,50,524
Say Rs. In Lac. 56.51

Page 20 of 20

You might also like