You are on page 1of 8

HAZARD IDENTIFICATION &

RISK
Process & Erection,testing and comisssioning of
Location: High mast lighting tower
Risk Assessment Team: Assessment Date:
Leader: Mr.A.K.Maurya Last review date:
Member 1 Mr.Balasubramanian Next review date:
Member 2 Mr.A.Amalraj Approved By : Mr. Sandipan Ghosh
Signature

HAZARD IDENTIFICATION
Consequence
Work Activity
(Possible Risk Level (Low- L;
S.N. (Job steps in Hazards
injury/Ill- Medium- M; High- H)
sequence)
Health/ Persons-at-Risk
& Environmental)

1. Person trap inside the pit


1.Electricution
Excavation by mechanical
1
equipment
2. Body parts burns H
2.cabin 3. serious body part
3. Trap between two objects injury

Preparation of 1.Body parts injury


1.serious injury
2 reinforcement and fixing
2.Amputation H
of foundation bolts.

Concrete casting (PCC &


3
RCC)
1.Dermitices 1.Skin deases M
1. Trap with moving vehicles
Transporatation of High 2. Falling of
4
mast. material 3.slip,trip,toppling
1.Serious body part damage H
4.Hit by object
1.Chain pulley block chain give
5 Asembly of High mast
away 2.Hit by object
Body Injury H

1. Falling Hazard
1.Serious body part injury 2.Property
6 Erection of High mast 2. Lift gear give away. 3.Hydra
damage H
topple 4.Amputation

Installation of illumination 1.Falling of object 2.Person hit by


1.Body part burnt . 2.Serious body part
7 system and hoisting to the object 3.Failure of hoisting
injury H
proper position. mechanism 4.electricution
Check and
1.Serious body part burnt. 2.property
8 commissioning of the 1.Electricution. 2.Short circuit
damage H
illumination system.
Rev. No.: 0
ASSESSMENT (HIRA)/JSA Ref. No. : BGR/PPD/0208/GN/PRO/ -Rev 00
GENERAL NOTES:
1- All necessary permits to be obtained from BGRE/OPGC.
2-All persons must be Safety Inducted.
3- Mandatory PPEs are Safety helmet, Hard toe safety shoes/Gum Boot, Safety glasses, Reflective vest,
Full/half sleeve (at least 4 inch long) shirt ,Full length pant/trousers
4- Probability, Severity & risk Table is attached for reference

RISK EVALUATION RISK CONTROL


Residual Risk
(Low- L;
Present Control Measures Person responsible
Medium- M;
High- H)
ground utility identification need to be done.
3. Competent excavator operator need to
be deployed. 4.Backs man need to be deployed to control the excavation
activity.
5. Excavated soil need to be dumped two mtr away
from the pit.
6. Dewatering pump need to be arranged . L Site Head (RCM) / Package In charge

1.ELCB and earthing of the machine need to be checked. 2.cutting machine


(rotating part) need to be covered with guard. L Site Head (RCM) / Package In charge

1. Area need to be barricated.


2. Proper approach to be made for movement of concrete vehicles and worksmen.
L Site Head (RCM) / Package In charge
1.Autherised trailor driver need to be deployed for transportion. 2.Speed limit need to be
followed. 3.While loading in hydra
authorised operator need to be deployed.
4.Experince ragging and signal man to be deployed. 5.During
loading of highmast protroding beyond the trailor is not advisable.
6.Loaded L Site Head (RCM) / Package In charge
mast need to be secured to prevent sliding and rolling hazards.
7.During
placing tagline to be used. 8.Unloading
need to be done in a designated mass assemble area.
1.Certified chain pulley blocks need to be used. 2.Hazzard
briefing to be carried out before operation. 3.Mark the lapping/ bearing
length 4.Secure chain pulley block as L Site Head (RCM) / Package In charge
per the engineer instruction 5. Dragging of top mast towards close to
bottom at top most. 6.Ensure lapping/bearing according to the mast design.

1.Autherised hydra operator need to be deployed. 2.JSA


briefing need to be carried out. 3.Certified
lifting gears need to be used for lifting purpose. 4.Lifting points need to be decided
according to the height and weight of the mast.
5.During lifting dragging is not advisable. 6.Tag
name need to be used to control the mast. L Site Head (RCM) / Package In charge
7.During hoisting bring the mast to a vertical position and place the
bottom of the mast above the mast foundation. 8.Tightening the mast
by tightening the nuts using right tools. 9.During tightening mast
verticality need to be checked.

1.Experience electrician need to be deployed. 2.Hazard briefing


need to explained .3.Illumination fitting need to
be assembled and fixing as per vendor manual.
4.Recommeded electrical wire need
to be used 5.The entire electrical wiring system need to
be connect with DB box with proper earthing system. L Site Head (RCM) / Package In charge
6.During hoisting ensure all the illumination fitting need to be in a tight
position along with the mast illumination ring frame. 7. For hoisting
rotate the handle in a clockwise manner with stead and smooth rotation.
8.Ensure the illumiation
system has been reached at the top and the hoisting mechanism has been locked.
1.Appropriate approved electrical PPE need to be used. 2.JSA briefing
need to be carried out.
3. Experienced electrician need to be deployed for this activity. 4.BGRE Electrical
engineer need to be declair with the execution team for shut down for connecting new
illumiation system. 5.Before charging BGRE electrical engineer need to inform to the L Site Head (RCM) / Package In charge
execution team for charging system.
6. Activate MCB to energies the illumination system.
7. Check and ensure the illuminated area which has been covered.

You might also like