JSA (Job Safety Analysis) Sheet

Activity Name:- Pit Cleaning Ref-

Location:- Date :

Sr.No. Sub-Activity Name Type Of Hazard Risk(s) Involved Risk Control measures
Untrained worker,lack Only inducted worker shall be deputed at the work place.
1 Manpower Mobilization Personal injury
of skill awareness Given Tool Box Talk to all workers.

1.Only approved standard ladder to be used.


2.Placing ladder on the stiff firm base surface.
a.Fall Hazard Personnel Injury 3.Resting ladder against the stiff surface.
4.Top of the ladder to project at least 1 mtr outside the pit
5.While ascending and descending on the ladder always f

Use of required PPEs such as Helmet, Jacket, Safety shoes.


Pit cleaning
(a.Use of ladder to enter the pit Excavated material shall be kept min.2mtr.away from the Pit /
b.Collecting material and Trench edge.
b.Collapse of sides Injury Loose material along the edge shall be removed.
charging in the collection
vessel Vertical cutting of the pit will be done by giving slops / caving of
2
c.Lifting and sending it to the pits.
top of pit Work will be carried out under supervision.
d.Charging the material into
Back stress and Heat a.Instructing for drinking water at regular intervals.
stack Stress
Health hazard
b.Provide the drinking water at each individual location
e.Comming out of pit.)
Improper use of Use proper ppe as per work requirement.
Injury
handling tools. Use only inspected tools .
Ladder to be anchored using clamp and 1m above pit.
Loose material along the edge shall be removed.
Fall of person, Cut &
Improper use of Ladder On the top, angle of repose shall be maintained.
Injury
Supervision should be present at the time of loading &
unloading.
Night work permit to be taken from concern engg.and safety
Darkness, fall of dept.
Personal injury, Ensure proper illumination during dark hours.
3 Work during dark hours person, fall of Electrical cable should lead min 2 m height. No exposed electrical
damage to property
machinery wire.Earthing.
Route shall be illuminated.