You are on page 1of 1

KEY PLAN:

NOTE:
AS THE LOAD DEVELOPS IN PHASE1 AND
KM GRID KM GRID
REACHES THE CAPACITY OF 12 FEEDERS

GOLF
310

DISTRICT
GDW-01
GOLF

580.326
COURSE

WEST
213593.8
GCR-01
RESIDEN
06
TIAL

T 1/6 R50
T 1/6 R50

FUTURE WFR-03
WATERFRONT
212097.142
RESIDENTIAL

T 1/6 R50
T 1/6 R50

(12 4.3 MVA/ FEEDER, 51.6 MVA), THE

WATERFRONT092.967
211
WFR-02
RESIDENTIAL
EXISTING PRIMARY SUBSTATION 66/11kV - LDS-2 PSS-ND-01 SHALL BE ENERGIZED AND PSS-ND-01
GSD-03
T 1/6 R50
GOLF
DISTRICT
GSD-03
612
030.712
T 1/6 R50

GOLF
611GDS-02
DISTRICT
233.550

T 1/6 R50

FOX
412
FXH-05
HILLS
321.987

WATERFRONT
MDL=0.9x ΣFMDL = 82.82x0.9= 74.54MVA

210046.655
WFR-01
RESIDENTIAL
GOLF
610 DISTRIC

GDS-01
485.738
T

T 1/6 R50

R50
1/6
T
EDUCATION
LOOPED IN TO THE NETWORK AS PER

510 844.130
EDD-03
MEDICAL

DISTRICT
WITHIN PROJECT

312 728.251

MEC-01
DISTRICT
T 1/6 R50

R50
1/6
T
T 1/6 R50

T 1/6 R50

FOX
411
FXH-04
HILLS
843.970
T 1/6 R50

DISTRICT
EDUCATION
EDD-02
313 342.335

WATERFR
112 WFC-04
ONT
416.575
T 1/6 R50

COMMER
T 1/6 R50

CIAL
411

FOX
FXH-03
337.899

HILLS
ELECTRICAL DISTRIBUTION 11kV NETWORK SLD THE SCHEME.

05R 6/1 T
BOUNDARY

EDUCATION

T 1/6 R50
314 176.193
EDD-01

05R 6/1 T
DISTRICT

WATERFRONT
111 799.483
WFC-03
CENTRAL

810 000.000

COMMERCIAL
PZC-01
PZC-01
PLAZA
NORTH
BLN-01
BOULEVARD
810 921.731

T 1/6 R50

T 1/6 R50
410 850.520

FOX HILLS
FXH-02
NORTH
BLN-02
BOULEVARD
264.678
811

810 911.858
BLS-01
SOUTH
BOULEVARD

T 1/6 R50
811 254.805
T 1/6 R50 BLS-02 SOUTH
BOULEVARD

T 1/6 R50
T 1/6 R50 T 1/6 R50

05R 6/1 T
05R 6/1 T

T 1/6 R50
T 1/6 R50

R50
1/6
T

WATER
T
1/6
R50
T
6/
1
05R 6/1 T

05
R
T 1/6 R50

FRONT
111
WFC-02

COMME
196.254

RCIAL
05R 6/1 T

410 355.752

FOX HILLS
FXH-01
05R 6/1 T

WATERF
ENERGY

RONT
512 678.033
EC2-01

110

WFC-01

COMME
786.935
CITY

RCIAL

QATAR
ENTERTAINMEN
110

QEC-02
231.879

T CITY
EXISTING LDS-2 SUPER SS

40 T1 40 T2 40 T3 40 T1 40 T2 40 T3
MVA 66/11kV MVA 66/11kV MVA 66/11kV MVA 66/11kV MVA 66/11kV MVA 66/11kV
Z=16.00% Z=16.00% Z=16.00% Z=16.00% Z=16.00% Z=16.00%

B1 (11kV, 3150A, 31.5kA/3 Sec) B2 (11kV, 3150A, 31.5kA/3 Sec) B3 (11kV, 3150A, 31.5kA/3 Sec) B1 B2 B3 (11kV, 3150A, 31.5kA/3 Sec) NOTES:
- THE LOCATION OF PRIVATE SUBSTATIONS ARE
A150 A130 A110 A90 A70 A50 A30 A10 A20 A40 A60 A80 A100 A120 A140 A160 A170 A190 A210 A270 A290 A310 A330 A350 INDICATIVE ONLY. THE EXACT LOCATION SHALL BE
FINALIZED DURING RESPECTIVE BP PROCESSING.
CL= 15290, MDL=9724

CL=15902, MDL=10175
- ALL 11KV CABLES ARE 3C-300mm² XLPE+ FO CABLES.

CL= 14623, MDL=9296

CL= 12450, MDL=7875

CL= 12029, MDL=7640

CL= 15154, MDL=9675

CL= 12023, MDL=7655

CL= 12459, MDL=7884

CL= 13266, MDL=8448

CL= 15476, MDL=9805


CL= 15547, MDL=9890
CL=14027, MDL=9089

CL=15369, MDL=9758

CL=11309, MDL=7168

CL=11272, MDL=7252

CL=12803, MDL=8130

CL=15735, MDL=9987

CL=12948, MDL=8190

CL=11584, MDL=7325

CL=12257, MDL=7766
THE 3C-300mm² CABLES ARE LAID AT A SPACING OF
50CM THUS REDUCING THE CURRENT CARRYING
FMDL= 3072 kVA

FMDL= 4188 kVA

FMDL= 3143 kVA

FMDL= 4275 kVA

FMDL= 4409 kVA

FMDL= 3510 kVA

FMDL= 4300 kVA

FMDL= 3509 kVA

FMDL= 3138 kVA

FMDL= 3327 kVA


FMDL= 4187 kVA
FMDL= 4082 kVA

FMDL= 4000 kVA

FMDL= 3374 kVA

FMDL= 3291 kVA

FMDL= 4184 kVA

FMDL=3316 kVA

FMDL=3379 kVA

FMDL=3658 kVA

FMDL=4203 kVA
CAPACITY TO THAT OF 3C-240mm².
- IN ALL SECONDARY SUBSTATION FEEDER BREAKERS
SHALL BE PROVIDED WITH DIRECTIONAL
OVER CURRENT AND DIRECTIONAL EARTH FAULT
PROTECTION (TYPE4).
- THE LOCATION OF ALL ELECTRICAL EQUIPMENT SUCH
AS FEEDER PILLAR, KWHR METER, SERVICE CABINET,
CE CE CE CE CE CE CE CE CE CE PSS-ND-01 MINI PILLAR ETC, ARE INDICATIVE ONLY. THE EXACT
PLOT BOUNDARY
LOCATION WILL BE AS PER THE AS-BUILT DRAWINGS.
PHASE-1 LOW - IN CASE DETAILS/ MATERIALS ON THE DRAWINGS
(PLOT BOUNDARY) CONTRADICT WITH KM STANDARDS AND
SPECIFICATION, THEN THE LATER SHALL PREVAIL.
- COMPLETE DISTRIBUTION DESIGN RESPONSIBILITY TO
THE INFRASTRUCTURE CONSULTANT.
- CLIENT TO APPOINT A KM APPROVED
CONTRACTOR TO EXECUTE WORK AT SITE.
- TARIFF METERING FOR ALL LUSAIL PROJECTS ARE AT
THE LV SIDE, EXCEPT OTHERWISE STATED.
ALL THESE CONNECTIONS TO BE - LV CABLES ARE LAID AT A SPACING OF 40CM.
TRANSFERRED TO - ALL PERMANENT SECONDARY SUBSTATIONS ARE
PRIMARY S/S PSS-ND-01(FUTURE) INDOOR TYPE.
ONCE CONSTRUCTED - ALL 11KV SWITCHGEARS SHOULD BE KM STANDARD
WITH 31.5 KA/3SEC FAULT RATING.
- THIS SCHEME IS SUBJECT TO ALL CONDITIONS
MENTIONED IN THE APPROVAL LETTER REF.NO.
EP/MO/3378/2023. DATED: 24-09-2023.
- ALL DISTRIBUTION SUBSTATIONS ARE STANDARD
NOTES: DOUBLE INDOOR TYPE WITH 4x 1600 KVA OIL TYPE Tx,
1. ALL LOADS ARE IN kVA. 4x 6W FSFP, WITH NATURAL VENTILATION,
SS.40477 SS.40463 SS.40464 STANDALONE AT GROUND FLOOR.
SS.40474

TIE IN FOR FUTURE PHASE-4

TIE IN FOR FUTURE PHASE-2


2. PLOT LOAD IS MAXIMUM DEMANDED LOAD INDICATED FOR THE PLOT. FURTHER
DIVERSITIES ARE APPLIED AT 11kV FEEDER AND PRIMARY SUBSTATION LEVELS AS INFRASTRUCTURE PROJECT.
3631kVA 2923kVA 3094kVA 3428kVA 4232kVA 3093kVA 3486kVA 2974kVA DETAILED IN TABLE-1. ALL MATERIAL & LABOR BY CLIENT.
ALL COST TO CLIENT. NO COST TO KM.
3. FMDL FOR THE FUTURE BULK CONNECTIONS ARE SHOWN AS AVERAGE FEEDER LOAD,
FINAL LOAD BALANCING TO BE DONE AT LATER STAGE.
SS.40476 SS.40473 SS.40465 SS.40468
4. MAX. ALLOWED 11kV FEEDER LOADING IS 4.3 MVA. ONCE THE FEEDER LOADING IS TO
EXCEED 4.3 MVA ON FEEDERS FROM LDS-2, CLIENT TO DO ALL THE NECESSARY
3434kVA (NO) 2772kVA 3066kVA (NO) 3238kVA 4095kVA 3788kVA 3345kVA (NO) 3217kVA
ARRANGEMENTS TO ENERGIZE THE FEEDERS FROM ND01 PRIMARY.

5. MV CONNECTIONS TO SECONDARY SUBSTATIONS SHOWN IN THIS SLD ARE TEMPORARY


SS.40472 SS.40467 SS.40471 SS.40479 POWER CONNECTION SCHEME FOR CP28B PHASE-1, HUZOOM DISTRICT.
e : T e, 3 Oc 2023 08:42

3312kVA 3212kVA 3355kVA 3469kVA 3474kVA 3444kVA 3124kVA 3384kVA 6. ALL SUBSTATIONS (EXCEPT SS.40485-PRIVATE) SHOWN HERE ARE LUS-CP28B-QDSBG-DWG-EL-01302-001
DESIGNED TO SUPPLY RESIDENTIAL LOADS BY CONSIDERING LESS
THAN 50% MOTOR LOAD CONTRIBUTION.

SS.40469 SS.40475 SS.40482 7. SS.40485 IS PRIVATE INDOOR SS SUPPLYING UTILITY PUMP STATION LOADS DIVERSITY
SS.40470
FACTOR 1.0.

3780kVA 3474kVA 4044kVA 3596kVA 3258kVA (NO) 3236kVA 4041kVA 4090kVA 8. ALL RESIDENTIAL PLOTS ARE LOCALLY COOLED.

9. ALL SECONDARY S/S TO FOLLOW KM STANDARD DOUBLE INDOOR DISTRIBUTION S/S


L

DESIGN.
SS.40466 SS.40462 SS.40483 SS.40481
TABLE-1: DIVERSITY FACTORS APPLICABLE FOR PLOT LOAD CALCULATION
Sc e e LUSAIL 4-415-2023 4-415-2023-P3-P4.

P D c C ( A/C L e 50% T M De )
3908kVA 4368kVA 4095kVA 4095kVA 2918kVA 3521kVA 4300kVA 4148kVA
D e Re ec e D e D e Ne D e D e Ne D e
L e 11kV LV T e S/S 11kV Fee e 11kV Fee e P
S e
Re e 0.70 0.85 0.80 0.48 0.90 0.43
PRIVATE SS.40485 SS.40461 SS.40478 SS.40480
S M e 0.75 0.85 0.80 0.51 0.90 0.46
Re S 0.80 0.85 0.80 0.54 0.90 0.49
814kVA 3780kVA 4095kVA 3636kVA 3532kVA 3996kVA 3770kVA O e ce 1.00 0.85 0.80 0.68 0.90 0.61
Ve c e C 1.00 0.85 0.80 0.68 0.90 0.61
U e 1.00 0.85 0.80 0.68 0.90 0.61
SS.40484
TABLE-2: DIVERSITY FACTORS APPLICABLE FOR PSS LOAD CALCULATION
SUPPLY TO HUZOOM DISTRCIT PHASE 1
3818kVA 3837kVA HUZOOM PH.1 PROJECT IN LUSAIL CITY
TCL MDL PL 11 FMDL PSS 11 KV SCHEMATIC FOR INTERIM SUPPLY
01 R

CP / AREA
(kVA) (kVA) (kVA) (kVA) (kVA) (FROM LDS2 PRIMARY)
AN/SSS 26-09-2023 N.T.S
DIVERSITY FACTOR - - 0.85 0.80 0.90
CAD Re : e ec

YA HW
CP28B 271524 172732 103534 82827 74544 AA For/ MM

ZONE: 69
4-415-2023
0 3/158

IN CO-OPERATION WITH ALL GIS AGENCIES

You might also like