schedule

2023 2024 2025

juli 2024
start construction
mzis - ypj new building
sept/okt 2023 juli 2025 ?
planning handed over mzis & ypj
mei 2024
expected handed over mzis & ypj new building
temporary school

CENTRAL SERVICE ENGINEERING | 2023


AREA CALCULATION
EXISTING MZS - YPJ SCHOOL

mzis : 2.041
ypj : 4.821
MZIS - YPJ : 1.036
TOTAL : 7.899
MZIS TEMPORARY SCHOOL

mzis : 1.596
ypj : 3.360
TOTAL : 5.030

LOCATION : WEST
MZIS TEMPORARY SCHOOL YPJ TEMPORARY SCHOOL

CENTRAL SERVICE ENGINEERING | 2023


AREA CALCULATION NEW MZS - YPJ SCHOOL
MZIS YPJ
number of student 90 320
sqm per student in old school 22.67/SQM 15/SQM
sqm per student in new school 28.5/SQM 20.5/SQM

sharing area MZIS YPJ TOTAL


1ST FLOOR ON NEW BLOCK 1.345 2.869 4.214
1ST FLOOR ON renovated block c 1.066 1.066
2ND FLOOR ON NEW BLOCK + RENOVATED BLOCK C 1.732 2.566 4.298
2ND FLOOR ON RENOVATED BLOCK C 1.066 1.066
RENOVATED BLOCK D 1.577 1.577
NEW BUILDING FOOt PRINT ( NEW BLOCK) 3.077 2.566 2.869 8.512
total school area + renovation 3.077 2.566 6.578 12.221

mzis : 2.566
ypj : 6.578
MZIS - YPJ : 3.077
TOTAL : 12.221
GROUND FLOOR
MZS AREA 2ND FLOOR
YPJ AREA
MZS - YPJ AREA MZS - YPJ AREA
CENTRAL SERVICE ENGINEERING | 2023
SUPERIMPOSED EXISTING

CENTRAL SERVICE ENGINEERING | 2023


SUPERIMPOSED DESIGN

CENTRAL SERVICE ENGINEERING | 2023


GROUND FLOOR
YPJ AREA
MZS - YPJ AREA

CENTRAL SERVICE ENGINEERING | 2023


2ND FLOOR
MZS AREA
MZS - YPJ AREA

CENTRAL SERVICE ENGINEERING | 2023


TEMPORARY
SCHOOL
SITE SURVEY

CENTRAL SERVICE ENGINEERING | 2023


SUPERIMPOSED
OPTION 1

CENTRAL SERVICE ENGINEERING | 2023


GROUND FLOOR
OPTION 1

SERVICE AREA
CORRIDOR

ADMIN, TEACHER, ETC


WC / SANITARY

CLASS ROOM

CENTRAL SERVICE ENGINEERING | 2023


2ND FLOOR
OPTION 1

SERVICE AREA
CORRIDOR

ADMIN, TEACHER, ETC


WC / SANITARY

CLASS ROOM

CENTRAL SERVICE ENGINEERING | 2023


CONCEPTUAL CLASSROOM PERSPECTIVE
EXISTING SHELTER
OPTION 1

EXISTING HOUSE

OUTDOOR PLAYGROUND

CLASSROOM
WEST STREET

CENTRAL SERVICE ENGINEERING | 2023


CONCEPTUAL PERSPECTIVE
OPTION 1

FRONT VIEW

EXISTING SHELTER FOR STUDENT ACTIVITY


CENTRAL SERVICE ENGINEERING | 2023
CONCEPTUAL SECTION CUT
OPTION 1

A - A’

LIBRARY
WEST TEACHER OFFICE, ETC
CLASSROOM OPEN SPACE

B - B’
MUSIC ROOM
CLASSROOM
WEST ASSEMBLY ROOM
CLASSROOM OPEN SPACE

B - B’ A - A’
CENTRAL SERVICE ENGINEERING | 2023
PLAN
OPTION 2

CENTRAL SERVICE ENGINEERING | 2023

You might also like