2. Schedule Variance (SV): SV = EV - PV 3. Cost Performance Index (CPI): CPI = EV/AC 4. Schedule Performance Index (SPI): SPI = EV/PV 5. Estimated at Completion (EAC): EAC = BAC/CPI 6. Estimated Time to Complete (ETC): ETC = (BAC - EV)/CPI
Dựa trên thông tin đã cung cấp:
● PV (Planned Value) = $46,000
● EV (Earned Value) = $43,333 ● AC (Actual Cost) = $53,000 ● BAC (Budget at Completion) = $120,000
Tính toán:
Cost Variance (CV):
CV = EV - AC
1. CV = $43,333 - $53,000 = -$9,667
Schedule Variance (SV):
SV = EV - PV
2. SV = $43,333 - $46,000 = -$2,667
Cost Performance Index (CPI):
CPI = EV / AC
3. CPI = $43,333 / $53,000 ≈ 0.817
Schedule Performance Index (SPI):
SPI = EV / PV
4. SPI = $43,333 / $46,000 ≈ 0.942
Estimated at Completion (EAC): EAC = BAC / CPI
5. EAC = $120,000 / 0.817 ≈ $146,863
Estimated Time to Complete (ETC):
ETC = (BAC - EV) / CPI
6. ETC = ($120,000 - $43,333) / 0.817 ≈ $90,166
Giờ ta trả lời từng câu hỏi:
● Dự án đi trước hay đi sau lịch biểu?: SV là -$2,667, vậy dự án đang đi sau
lịch biểu. ● Dự án trong phạm vi ngân sách hay vượt ngân sách?: CV là -$9,667, vậy dự án vượt quá ngân sách. ● Dùng CPI để tính giá trị EAC cho dự án này: EAC là $146,863 (đã tính trước đó). ● Dự án được thực hiện tốt hơn hay xấu hơn so với kế hoạch?: CPI là 0.817, vậy dự án đang thực hiện kém hơn kế hoạch. ● Dùng SPI để ước lượng dự án sẽ kết thúc sau bao lâu: SPI là 0.942, vậy dự án sẽ kết thúc sau một thời gian dài hơn so với kế hoạch ban đầu. Để biết thời gian cụ thể, bạn cần biết thông tin về lịch biểu tổng cộng của dự án.