You are on page 1of 13

Journal of Cleaner Production 286 (2021) 124944

Contents lists available at ScienceDirect

Journal of Cleaner Production


journal homepage: www.elsevier.com/locate/jclepro

Implementing lean construction techniques and management


methods in Chinese projects: A case study in Suzhou, China
Weiqi Xing a, Jian Li Hao b, *, Liang Qian c, Vivian W.Y. Tam d, Karol S. Sikora e
a
School of Built Environment, Western Sydney University, Sydney, Australia
b
Department of Civil Engineering, Xi’an Jiaotong-Liverpool University, Suzhou, China
c
Corporate Real Estate Realization - Asia Pacific, BOSCH China Investment Ltd., Shanghai, China
d
School of Built Environment, Western Sydney University, Sydney, Australia, Honorary Professor, School of Civil Engineering, Hefei University of Technology,
Hefei, China
e
Civil Engineering Department, University of Wollongong in Dubai, Dubai, United Arab Emirates

a r t i c l e i n f o a b s t r a c t

Article history: Aimed at maximizing project value while reducing waste and cost, the lean construction (LC) approach
Received 5 June 2020 was formally and successfully introduced to the architecture, engineering and construction (AEC) in-
Received in revised form dustry in 1993. Although LC has rapidly developed since that time, it was not applied to a Chinese
29 October 2020
construction project until 2005. However, due to insufficient knowledge and poor execution, this first
Accepted 2 November 2020
Available online 5 November 2020
attempt at lean construction in China was inadequate. The aim of this study was therefore to discover if
the Chinese construction industry has since discovered how to use lean practices to maximize project
^as de
Handling editor: Cecilia Maria Villas Bo value, shorten the project schedule, improve project quality, and reduce waste. This was achieved by
Almeida conducting a case study of a LC project in Suzhou, China. The case study revealed that implementation of
lean practices during the project, including Last Planner System (LPS), Kanban system, Just-In-Time (JIT),
Keywords: prefabrication, Internet of Things (IoT), quality and safety management, and continuous improvement, all
Case study contributed to the improvement of project performance. To supplement the case study and to provide
Kanban system insights on the differences between Chinese and international LC, interviews with project stakeholders
Last planner system
and a questionnaire survey of global lean experts were conducted. Results indicated that interviewees
Lean construction management
and survey respondents both held the view that project waiting times and defects can be greatly reduced
through the implementation of LC, and that improvement of construction workflow along with project
productivity and quality were the two most valuable benefits of using lean practices; there was also a
consensus that lack of trust and the abilities of stakeholders are the biggest challenges.
© 2020 Elsevier Ltd. All rights reserved.

1. Introduction urbanization and the gross domestic product (GDP), there are those
in the industry who complain about the low profit margins (Gao
The architecture, engineering and construction (AEC) industry and Low, 2014). It has been claimed that the dynamic and com-
in China has developed rapidly and successfully over the past fifty plex properties of the AEC industry, extensive management
years and is now one of the country’s pillar industries. The gross methods, and insufficient construction technology has resulted in
output of China’s AEC industry was USD3.5 trillion in 2018 (NBS, rapid expansion at the expense of low profit (Wang, 2015). Along
2019), which was 20 times more than in 1978 (Xing et al., 2019), with this unsatisfactory economic pattern, reverse social and
accounting for 54% of the social fixed assets, and employing 55.6 environmental impacts are two areas of public concern. For
million people (Wang, 2019). instance, some Chinese construction companies are exposed to the
Even though the AEC industry is prosperous and underpins both risks of project delays, quality flaws, cost overrun, and safety haz-
ards when they undertake a construction project (Li et al., 2017). In
addition, construction related activities in China cause more than
* Corresponding author.
one third of national raw material and energy consumption (Zhou
E-mail addresses: 19918642@student.westernsydney.edu.au (W. Xing), JIANLI. et al., 2018), and 1.5 billion tons of waste generation (Hao et al.,
HAO@xjtlu.edu.cn (J.L. Hao), Liang.Qian@cn.bosch.com (L. Qian), v.tam@ 2019). These statistics suggest that traditional construction
westernsydney.edu.au (V.W.Y. Tam), KarolSikora@uowdubai.ac.ae (K.S. Sikora).

https://doi.org/10.1016/j.jclepro.2020.124944
0959-6526/© 2020 Elsevier Ltd. All rights reserved.
W. Xing, J.L. Hao, L. Qian et al. Journal of Cleaner Production 286 (2021) 124944

methods and management approaches have serious drawbacks performances through focusing customer requirements, learning
that are in urgent need of attention, since both quality and safety and innovating, and eliminating non-value adding activities. Such
are more important than construction speed and output. As a advantages are in accord with the sustainability agenda, although
consequence, government, scholars, and industrialists need to help the economic benefits are claimed to be the primary motivator for
innovate the AEC industry in terms of policy, concept and the AEC industry (Carvajal-Arango et al., 2019).
technology. The current trend in construction projects is to integrate lean
With a deeper understanding of sustainable development and philosophy with other techniques and concepts. Such synergies
environmental protection, advanced theories and practices such as have been demonstrated to be mostly positive to obtain higher
green building and lean construction management (LCM) have productivity in construction projects (Tezel et al., 2020). According
become more closely aligned with corresponding policies. For to Li et al. (2019), research interests and visualizations of LC have
instance, Ministry of Housing and Urban-Rural Development of the shifted from cost management to a combination of BIM and pre-
People’s Republic of China (MOHURD, 2020) informed all regions fabrication. Saieg et al. (2018) explored the combination of lean,
within China that green construction strategies should be imple- green and BIM to strengthen the synergies and interrelationships of
mented in accordance with local conditions. The transition to lean these concepts/tools within the AEC industry, which allows for
development of the AEC industry promotes industry reform and more complicated and sustainable construction projects. The pos-
stimulates economic growth (Yang, 2017). itive effects on energy consumption and carbon emission re-
However, implementing LCM in China’s AEC industry is at the ductions through integration of prefabrication and lean practices
initial stage for residential and commercial buildings. Relevant have also been studied (Heravi et al., 2020).
studies focusing on the domestic market are rare, since local con-
struction firms tend to use traditional construction methods. 2.2. Implementation of lean practices in China
Consequently, this study chose a lean practice case study from the
industrial sector to examine the implementation of LC and LCM in Having witnessed the advantages of lean practices applied the
Suzhou, China. Interviews with stakeholders in the case project and AEC industry in many parts of the world, some Chinese scholars and
a questionnaire survey of global lean practitioners and scholars local construction firms considered that this new approach could
were conducted to obtain opinions of LCM from both a local and be adopted by China’s AEC industry (Li et al., 2020). Despite LC
global perspective. This allowed for a comparative analysis to better having been introduced in 1993 (Koskela, 1993), the first attempt at
understand the opportunities and threats of LC implementation in implementing lean thinking in China’s AEC industry was not until
China. 2005 (Low and Min, 2005). Also, only a few large firms in China
This research addresses LC implementation in a Chinese in- have the ability and resources to apply LC techniques and LCM to
dustrial construction project to fill a knowledge gap. Findings from projects, since initial investigations and preliminary work are
the study provide a means by which lean principles and techniques extensive and resource consuming. The attitude towards making
can be adapted to construction projects in China, provide a mech- changes (Liao, 2018), insufficient theoretical support (Li et al.,
anism for stakeholder cooperation, and identify the lessons learned 2020), and delayed planning information (Li et al., 2017) are
for future improvements. It also provides both theoretical and several more impediments to implementing lean practice in China.
practical guidance to the construction firms that intend to imple- Consequently, the delayed adoption and slow impediment-laden
ment LCM in future projects. development has created a giant gap between China and other
countries with regard to the practice of LC.
2. Literature review Early LC research in China was more on the theoretical level than
the practical level, and the majority of studies emphasized indi-
2.1. Worldwide lean practice implementations vidual LC techniques rather than LCM. The first systematic research
on LCM in China was in 2004 (Jiang and Su, 2004) and focused on
Formally put forward by Koskela (1993), LC received great LCM’s potential for China’s construction market and local enter-
attention from the AEC sector. It aimed to implement lean thinking prises (Li et al., 2020). In 2007, Min and Su (2007) developed a
from manufacturing to construction for improving project quality construction management model based on the transformation,
and efficiency, while reducing construction costs and waste gen- flow, and value (TFV) theory, adapting a lean practice from
eration. Along with the LC concept, scholars have concentrated on Denmark to investigate the suitability of it to China. They found
LC techniques to achieve higher productivity. For example, LPS that changing the constructors’ mind, pursuing continuous
(Ballard, 1994), JIT (Ballard and Howell, 1995), pull-scheduling improvement, and adjusting the methods to local condition were
(Tommelein, 1998), and Lean Project Delivery System (LPDS) three key points for successful implementation of LCM in China.
(Ballard and Howell, 2003). Feng and Liu (2008) presented LCM through the lens of theoretical
LC has been successfully utilized in the AEC industry globally. and practical knowledge and identified the challenges China’s AEC
Among 32 lean practices identified from the literature, the most industry face when implementing LCM. For instance, a lack of
common one applied to construction project was LPS, with JIT and implementing time, personnel training, effective organization and
pull-scheduling used in building and infrastructure planning, critical thinking are possible threats when adopting LC techniques
design and construction activities (Babalola et al., 2019). Other such as the LPS, value engineering and JIT. Starting in 2010, more
more comprehensive lean practices have been attempted to comprehensive investigations on LC applications and LCM were
improve project performance, including concurrent engineering (Li carried out in China, usually combined with other sustainable and
et al., 2017), visualization (Dave et al., 2016), Kanban (Sarhan et al., advanced concepts. Aiming to strengthen the efficiency of the do-
2017), and the 5S method (Sort, Straighten, Standardize, Shine, and mestic AEC industry, Zhao et al. (2011) explored interactions be-
Sustain) (Salem et al., 2006). The positive economic, environmental tween LCM and BIM by constructing an interactive matrix. Twenty
and social impacts of implementing lean practices have been well one interaction points were summarized and suggestions provided
recognized by scholars. For example, Issa (2013) found that the but no case was studied to validate how the suggestions could be
implementation of lean practice effectively minimized the risks of implemented in a project. Huang and Gao (2011) integrated lean
time overrun, while Meng (2019) found LC with supply chain principles with the unique characteristics of China’s AEC industry to
collaboration helped to significantly boost time, cost and quality find ways of making LC and LCM suitable for China.
2
W. Xing, J.L. Hao, L. Qian et al. Journal of Cleaner Production 286 (2021) 124944

LC applications and LCM offer theoretical and methodological implementation globally, the questionnaire was distributed only
support to China’s domestic AEC industry. Research focusing on to potential respondents working outside of China.
Chinese construction enterprises implementing LCM, identified The results from both case project stakeholders and global lean
three forms of LCM: TFV theory, Japanese style management experts were evaluated and compared by statistical analytical
derived from Toyota Production System (TPS), and detailed man- methods including mean value and ranking, standard deviation (SD),
agement aimed at achieving standardization to meet the demands and inter-rater reliability by Cronbach’s alpha (Bajjou and Chafi, 2018;
of customers (Liao, 2018). The periods 2001 to 2007, and 2008 to Aslam et al., 2020). The frequency of lean practices used on con-
2012 were LC in its infancy and the early stage of LC in China struction projects was ascertained, and potential benefits and chal-
respectively. LC in China is now in the third stage called the high- lenges were analyzed. Recommendations to further utilize lean
speed development period, with extended research interests and practices were made according to the comparative results.
areas, and enriched functionality (Li et al., 2020). However, there
are still several barriers that need to be overcome when imple-
menting lean principles in China’s AEC industry (Li et al., 2017). 4. Implementation of lean practice in the case study project

4.1. Project information


3. Research methodology
The case study was conducted on an industrial building con-
The multi-method model of research is recommended to struction site in Suzhou, China from June to August 2019. The case
develop robust research design (Gable, 1994). Further, based on was researched and evaluated as it applies to several LC techniques
Anisimova and Thomson (2012), it is favorable to combine quali- and LCM methods throughout the whole project process. The case
tative and quantitative approaches to conduct the empirical study. study building is a six-storey car park with two spiral ramps that
This work therefore follows the multi-method research occupies 31,349.47 m2 with parking for 1,000 cars. Its structure is
comprising the strategies of case study, interview and question- made up of precast steel beams and reinforced concrete columns,
naire survey, in combination with qualitative and quantitative and the roof is covered with 412 kW photovoltaic panels. The esti-
approaches for data collection, and statistical methods for data mated budget to construct the building was approximately USD12
analysis. Fig. 1 shows the research framework regarding the million, and it took 360 calendar days to complete from the start of
phases and objectives.a semi-structured questionnaire survey was construction in December 2018.
conducted containing six questions with a choice of answer, two A temporary LCM group was established to manage issues
scoring questions using 5-point Likert scale, and two open-ended occurring on site during the project. The group included represen-
questions. The purpose of the survey was to test the validity of the tatives from the client, the design institute, the management com-
LCM group members’ perspectives by comparing their experience pany, the site supervision company, the main contractor, and
of LC implementation with experiences from global lean practi- subcontractors. The aforementioned stakeholders were selected
tioners. The survey was delivered to members of the Lean Con- based on their understanding of LCM and their acceptance of it being
struction Institute, to scholars who had published peer-reviewed implemented on the case study project. The management company
articles in the LC field, and to practitioners currently working on undertook to equip all their personnel working on the construction
LC projects. Since the aim of the study was to investigate the site with basic knowledge of LCM. Fig. 2 shows the personnel allo-
difference between implementation of LC in China and LC cation of the 25 members of the temporary LCM group.

Fig. 1. Research methodology procedures.

3
W. Xing, J.L. Hao, L. Qian et al. Journal of Cleaner Production 286 (2021) 124944

Fig. 2. Personnel allocation of on-site temporary LCM group.

4.2. Last Planner System and Kanban system week. During the assembly, the PPC and weekly plan for each ac-
tivity were reported by the corresponding disciplines, such as civil
As shown by Fig. 3, the LPS and the Kanban system were closely engineering, mechanical, electrical and plumbing, and decoration.
associated in the case study project, since LPS was used for plan- This follows the principle of the LPS that construction plans should
ning and scheduling while Kanban was used as a visual tool to show be established by the construction personnel as the last planners,
detailed daily and weekly schedules. Both techniques were inten- which involves them more closely in production of the project
ded to reduce variances and improve the project’s workflow. schedule. After the assembly, representatives from the stakeholders
The master schedule was prepared based on forecasts from the would hold an extra meeting to draw up a plan for the next month,
LCM group and the contract handover deadline. Phase planning, namely the 4-week look-ahead. Discussions during this meeting
presented as ‘pull-scheduling’ in this project, was also imple- was not as detailed as the weekly plan but more prospective and
mented to connect to more detailed plans, takt time planning, and holistic, assisting with the layout of future works. Stand-up meet-
percentage of plan completed (PPC). On the construction site, a ings, the smallest unit in LPS, is one of the most significant supports
method similar to concurrent engineering but focusing more on the for operation of the LPS and the Kanban system, since it strengthens
workflow than takt planning, was adopted. It divided construction the communications among the managers and construction
assignments into a series of tasks and coordinated operations of the personnel at an operation level. LCM group members convened at
LPS, achieving an optimal workflow sequence and synchronize the end of each day to review the status of the day’s activities and
production of the project. Based on the characteristics of the discuss the issues detected on-site. Issues that need to be solved
building structure, the multi-storey car park was separated into two within the week were recorded by post-it notes attached to the
construction regions: the parking area and the spiral ramp. The moveable Kanban time box, while those that had been addressed
construction tasks within the parking area were further divided were removed. Different colored post-it notes represented different
into practical areas, considering the target-takt-time, the time per disciplines.
output unit, and the capacity needed.
The 4-week look-ahead, weekly plan, daily stand-up meetings, 4.3. Just-In-Time and prefabrication
and the Kanban system were interconnected in this project by us-
ing a moveable Kanban. The weekly assembly was an opportunity One important reason for implementing LCM in this project was
to give an account of construction progress and issues encountered to fully utilize resources without waste, because the available on-
over the past week and to put forward a plan for the upcoming site space was not sufficient for material production and storage.

Fig. 3. Components and relationships of LPS and Kanban system in the case.

4
W. Xing, J.L. Hao, L. Qian et al. Journal of Cleaner Production 286 (2021) 124944

Fig. 4. JIT logistics for resource management in the case study project.

Accordingly, prefabricated components were widely adopted and preceding assignments have been completely finished. The con-
the JIT logistics principle applied to accommodate the character- tractor’s daily report records the intraday work, outlines plans for
istics of this construction method. See Fig. 4. the next day, including arrangements of labor, materials, and
JIT highlights the importance of workflow sequencing and lo- equipment, and predicts future demands. The report is checked for
gistics, which optimizes the arrangement of resources to eliminate accuracy by the site supervisor and for accuracy and rationality by
waste. With the assistance of LPS, the construction schedule is the manager.
clearly defined, whilst JIT logistics provide for resources to be Prefabrication is a production method that creates inventory off
available at the right time, in the optimum quantity, with the site, which allows for continuous on-site workflow, and waste
necessary materials, labor and equipment, and only when the minimization (Tam and Hao, 2014). The prefabrication rate of this

Table 1
Main benefits of the prefabricated elements used in the case study project.

Item On-site application Main benefits

Precast steelwork Minimizing on-site noise and dust;


Reducing on-site inventory, defects and waiting times;
Lowering the cost of on-site labor, material and equipment;
Decreasing energy consumption;
Maintaining standardization of the design;
Reducing on-site health and safety hazards;
Avoiding overproduction.

Deck panel

Assembled scaffolding

5
W. Xing, J.L. Hao, L. Qian et al. Journal of Cleaner Production 286 (2021) 124944

Fig. 5. Applications of digital technologies and IoTs in the case study project.

project exceeded 50%, which is made up of prefabricated steelwork project, Aconex was the primary tool for the LCM group members
for the main structure, deck paneling, and preassembled scaf- to inspect the project status and track the workflow. It was espe-
folding. Off-site production brings remarkable environmental, cially significant for the storage of important files and for document
economic, technical and managerial benefits to the project, as approval, as members were able to visit it anytime and anywhere,
shown in Table 1. Furthermore, the deck panels act as a permanent thereby reducing paper documentation on site to a minimum. The
mould for the cast-in-situ concrete floor, which follows the concept site inspection and issues track functions of Aconex Field provided a
of modern timber-concrete composites (Richard et al., 2019). By not significant boost to the quality and efficiency of inspections and
requiring concrete to be placed in the bottom part of the floor slab acceptance of construction tasks by using a holistic approach. Once
where the concrete is in tension and therefore ineffective, increased a site supervisor detects an undesirable on-site issue, they record it
bending strength and savings in the quantities of concrete used are on the platform to inform the contractors and track the solutions.
achieved. It also increases durability by limiting crack propagation Contractors can follow the recorded details, such as the issue type,
and reducing water ingress that can freeze or/and carry damaging the location, the issue description and due date, and respond to the
salt ions (Sikora and Klemm, 2014). The utilization of these pre- supervisors through the mobile service anytime when they rectify
fabricated elements, require the application of JIT to save materials the problems on site, instead of submitting a paper report.
and guarantee a smooth workflow. The client for this project established an I-site content man-
agement platform, which was connected to intelligent safety hel-
mets worn by site personnel. The platform receives a signal emitted
4.4. Digital technologies and Internet of Things
from the helmet and transfers the signal into digital information
that is presented as a flow heat map. The system also classifies the
Digital technologies and the IoT are effective tools that aided the
construction personnel in terms of different work areas, job duties
project and supported the LCM group with decisions over critical
and disciplines, providing a convenient manpower management
work processes and elimination of possible risks. The applications
tool. An automatic count of attendance and work hours, as well as
used in this project included BIM, Aconex and Aconex Field, I-site
risk pre-warming can also be integrated into intelligent safety
and QR code, where they integrated with LCM to promote pro-
helmets.
ductivity from design to maintenance phases.
QR codes make full use of IoT by reducing direct human-to-
Fig. 5 illustrate the functions of each application in different
human or human-to-computer interactions. The case study proj-
project phases. BIM was used to present a clear visual presentation
ect employed QR codes to record production and inspection pro-
of the design scheme to the LCM group before commencement of
cedures for all prefabricated components. There are several
construction work to help them understand the details of the
advantages of QR codes, such as low probability of code error, large
structural design and appearance of the project, to show them how
information capacity, and strong fault tolerance, which allows
client design changes were incorporated, and to demonstrate how
project information to be stored and accessed in a convenient and
clash detection was easier with the help of 3D visualization. During
accurate manner. Furthermore, QR codes enrich the quality control
the construction stage, construction simulation (4D feature) coor-
of projects in terms of supply chain management and inspection
dinated with the schedule was used to present the dynamic char-
tracking.
acteristics of the construction progress, and arrange the material,
labor and equipment resources accordingly. Contrary to traditional
manual calculation of the schedule and resources distribution, BIM 4.5. Quality and safety management
relies on the input of accurate information and scenario simulation.
Consequently, manual calculation mistakes with consequential Clients have their own standard for quality and safety of their
risks, waste, and uneven distribution of resources decline sharply construction project, where the integration of digital technologies
with the use of BIM. and IoTs are adopted as shown by Fig. 6. Both the management
Aconex is an information collaboration platform providing company and the site supervision company took a major role in
project information and process management services, while quality and safety monitoring in the case study project. They did so
Aconex Field, a Plan-Do-Check-Act (PDCA) inspection tool, is through inspecting on-site construction work, organizing weekly
responsible for site inspections. Both rely on a cloud-based plat- quality and safety meetings, holding meetings for specific issues,
form accessed by mobile and web terminals. In this case study and using Aconex Field software to track issues. For quality and
6
W. Xing, J.L. Hao, L. Qian et al. Journal of Cleaner Production 286 (2021) 124944

Fig. 6. Quality and safety management in the case study project.

safety monitoring, the management company focused more on control by QR codes, suppliers were required to record the
establishing a framework of related issues, while the site supervi- manufacturing process and properties of the prefabricated ele-
sion company was in charge of executing the quality and safety ments, then input into a QR code label attached to the element. All
plans. the prefabricated parts got a unique birth certificate QR code when
Before the construction work started, the project personnel they were delivered to the construction site, showing how they
were required to complete a site environment, health and safety were produced and thereby improving the transparency of the
(EHS) orientation. Apart from the initial training, weekly safety supplier’s production system. The QR code requirement also
education and tool-box meetings were held to strengthen the applied to concealed works that contained vital parts or parts prone
safety consciousness of construction personnel. to damage. Every work stage was documented to assist QR code
On-site inspections included daily, weekly, and specific in- users to follow the construction progress and ascertain re-
spections, as well as a safety audit. The purpose of the weekly sponsibility in case of quality issues.
quality and safety meetings was to review the construction status
of the previous week and identify the quality and safety plans for 4.6. Continuous improvement and scrum
the upcoming week, whereas specific meetings were to address
specific quality and safety matters as necessary. In addition, risk The core principle of the continuous improvement is the self-
management was applied to identify, evaluate, and control risks reflection of the existing processes along with PDCA model
based on the likelihood and potential consequences of any given (Heigermoser et al., 2019). To add value to project activities and
hazard. make profitable progress during the construction period, the case
For more quality and safety management measures, digital study project integrated continuous improvement based on lean
technologies and IoTs played important roles. BIM was employed to thinking, the Scrum iteration software program, and Agile project
conduct clash detection and construction process simulation, management methodology. Generally, several elements were
demonstrating interference or design flaws prior to construction reviewed during the stand-up meetings, including the work done
activities, while Aconex Field was used to report issues in real time, today, the work needed to be finished tomorrow, and obstacles that
which avoided checking omissions and shortened the response needed to be addressed. Through a continuous round of daily re-
time. In addition, the LCM group implemented an intelligent hel- views, better informed decisions were iterated on the basis of the
met integrated with I-site for real-time communication and current construction progress in line with the Scrum iteration
personnel positioning. The intelligent helmet was equipped with a process. A similar approach was taken at the weekly meetings of
motion sensor that sent out a signal to support the real-time the LCM group where tasks were prioritized from immediate action
positioning function visualized on I-site. Its two-way communica- to inclusion in the upcoming weekly plan. Construction personnel
tion promoted the exchange of information and instructions, so as were then notified accordingly of the tasks they had been assigned
to achieve remote commend and reduce the unnecessary move- to.
ment of personnel. It is an effective way to reduce the likelihood of The Kanban used in this project was continuously upgraded
severe injury occurring, especially for projects with a large con- from the lessons learned from previous projects and current
struction area, complicated structure, and/or a large number of on- experience. Initially, the level of detailing of the LCM cards on
site personnel. Regarding supply chain management and quality which the information was recoded was simplified based on
7
W. Xing, J.L. Hao, L. Qian et al. Journal of Cleaner Production 286 (2021) 124944

Fig. 7. Improvement of Kanban system.

feedback from previous users. However, some users were still un- down activities were tightly linked. There was no evidence of
happy with the card’s complex format and complained that hidden overproduction because the construction activities followed the
regions of the card were prone to neglect. As a consequence, post-it design and construction plan strictly, and prefabricated elements
notes on the moveable Kanban replaced the cards to show the were extensively used. However, the interviewees noted that pre-
construction issues, as shown in Fig. 7. fabrication requires a higher degree of completeness and precision
in design. In terms of energy efficiency, the client considered that
energy waste was mainly connected to over-design, which can be
5. Results and discussion diminished through greater BIM collaboration.
However, interviewees felt that there were several obstacles
5.1. Local perspective on lean practice from interviews that LPS could not fully address on the construction site, which can
be attributed to inharmonic relationships among different stake-
5.1.1. Factors influencing lean practice implementation holders (Miller et al., 2002). From the perspective of construction-
According to Li et al. (2020), although LC is in a stage of rapid related personnel, since managers from the contractor’s side are
development in China, it is extremely unbalanced in terms of less academically qualified, their awareness of the significance of
geographical location, enterprise size and project type. Conse- work division and the ability to scientifically break down the work
quently, exploring the benefits and challenges of implementing tasks are deficient. Even if the managers may fully understand the
lean practice becomes one of the incentives for promoting LC in construction management methods, it is ultimately the construc-
China. tion personnel who execute the work and their activities may
While there are eight types of on-site waste in LC philosophy deviate from the essence of the LPS. This confirmed the study of Li
(Gao and Low, 2014), seven types of waste reductions were et al. (2017). From the perspective of project stakeholders, there is a
observed as a result of implementing lean practices in the case contradiction between the client and contractors that hinders work
study project. The effectiveness of LCM to inventory associated with division. Since contractors are profit driven, it is advantageous for
waiting time are fully addressed by the case study project. The them if less labor is allocated to a task with a longer construction
limited construction space influenced the quantity of inventory and period permitted. On the other hand, the client would prefer to use
its storing period, therefore a complete and detailed schedule, and more labor and resources to minimize the duration of the task.
smooth workflow were vital for preparing the resources on time These two different requirements are difficult to reconcile and so
and accordingly shortening the waiting time. One of the goals of the division of work has to be balanced to mitigate the differences
LCM is to arrange and maintain the workflow properly through to ensure further cooperation. The client gets involved in setting
well-established schedules, so the waste reductions from inventory the work schedule and participates in on-site monitoring, while the
and waiting time are obvious. More than 90% of the defects were managers from the contractor assign the tasks to the construction
effectively solved or observed in advance, owing to the employ- personnel and guarantee the construction schedule. In view of the
ment of LCM and elaborate preliminary work, which ultimately aforementioned difficulties, it would seem that the successful
reduced waste and saved resources. The smooth workflow also had implementation of LCM in China remains a challenge.
positive impacts on underutilizing people and transport as the top

Table 2
Lessons learned from previous project experiences for continuous improvement.

Stakeholders Lessons learned & Continuous improvement

Contractors LCM process generally helps to maintain the workflow;


Mapping out 4-week look-ahead takes lots of effort;
LCM only works if everybody follows commitment;
LCM Kanban board is inconvenient to see the details.
Site managers Lots of unforeseen construction stops means that the LCM Kanban board has to be continuously updated;
Reward and punishment system should be implemented to ensure contractors fulfill their targets.
Client LCM Kanban card should be simplified;
For complex areas an additional more detailed schedule will be used on a separate board;
LCM manager as a single role is necessary for each contractor and for the site managers;
Daily LCM meeting is in the afternoon, verification of works can be done properly in advance so meeting duration can be reduced.

8
W. Xing, J.L. Hao, L. Qian et al. Journal of Cleaner Production 286 (2021) 124944

5.1.2. Suggestions to promote implementation of lean practice offer netlike and on-time communications among stakeholders.
Different from the manufacturing industry, the construction However, the contract manager mentioned that the efficiency of
industry is more complex and sensitive to unpredictable issues and applying QR codes to structural elements was not as good as
external factors (Paez et al., 2005), such as the weather, govern- anticipated, since all the information had to be uploaded and
ment policies, and supply chain problems as encountered in the classified to the system manually.
case study project. According to the construction manager, con- The interviewees provided comprehensive feedback from their
struction plans never keep up with on-site changes so that it is experiences of implementing LC techniques and LCM in the case
ineluctable to have to adjust the schedule throughout the con- study project, highlighting both the potential benefits and possible
struction period even if a comprehensive plan is set. In short, challenges. Table 3 provides a summary of these benefits and
managers need to provide enough buffer in construction assign- challenges.
ments and set a more flexible schedule to allow for occasional
setbacks. 5.2. Global perspectives on lean practice from survey
In terms of daily stand-up meetings, its efficiency improved as
the construction process advanced. Lessons learned from previous 5.2.1. General information about respondents
project experiences, summarized in Table 2, show it is better to A total of 22 LC practitioners and scholars provided valid re-
limit the duration of meetings so that participants can concentrate sponses to the questionnaire survey. Several respondents had
on the most urgent issues and avoid unnecessary discussions. The multiple roles in the AEC industry. Consultants accounted for 31.8%,
Kanban system used in the case study project was essentially an followed by researchers (27.3%), contractors (27.3%), architects
improved version that includes Scrum iteration, where the tasks in (13.6%), civil engineers (9.1%), and construction managers (9.1%).
terms of deadlines and responsibilities are more visible to man- Fig. 8 displays the proportions of respondents regarding business
agers. Accordingly, the fineness of LPS decreases since the target type, working experience, and number of LC projects they had
receivers are LCM group members rather than on-site construction previously worked on. A majority of respondents (59.1%) worked
personnel. Nevertheless, the client recognized that the theory- for a private company, and more than half (54.5%) had worked for
based actions of the LPS should be combined with practice and more than 10 years in the AEC industry. Although all respondents
that corresponding adjustments sometimes need to be made. The were either LC practitioners or scholars, only 45.5% of them had
idea is similar to the view of Meng (2019), who emphasized the participated in more than 10 LC projects and could therefore be
coexistence of learning from other industries and pursuing an in- considered experts in this field. According to data from the
dividual path when promoting LCM. returned questionnaires, commercial construction was the pre-
The interviewees also stated that the future of construction will dominant (72.7%) business type using LC that respondents had
be more integrated with IoT technology. BIM virtually verifies the worked on; 10 respondents had worked on LC residential projects;
quality and build ability of a construction design, so that the work 7 respondents had been involved in industrial LC projects; and 5
will not be interrupted by design failures and can be fully realized respondents had worked on infrastructure projects.
on the construction site. The next level of BIM application is design
and build so that construction can be made in advance with higher 5.2.2. Waste reduction through lean practice
precision among different disciplines. The online virtual model Table 4 shows the main LC techniques that respondents had
coheres all the stakeholders, such as clients, designers and builders, prior experience of. LPS and JIT had been used by the greatest
remotely to provide for more efficient collaboration. This opinion is number of respondents, while quality and safety management, and
exactly aligned with scholars who suggest that LC should be sup- constraint analysis had been used by about half of the respondents
ported by visualization tool for improving process transparency in their previous projects. The survey result strengthens the
(Sacks et al., 2009), and LCM level (Heigermoser et al., 2019). The contention by some researchers that LPS and JIT are the most
utilization of Aconex and Aconex Field provides for the distribution widely used lean practices in construction (Babalola et al., 2019; Li
of paperless documents and mobile-accessible workflow. They also et al., 2020). Seeking the reason why such lean practices have high

Table 3
Benefits and challenges learned from implementing LC and LCM in the case study project.

Benefits

Plan More forecasts and optimizations before construction begins means that less risk and better control of costs.
Schedule Well-established schedules generate higher productivity and improve the quality of the project.
Waste Various LC techniques, LCM and other technologies combine to reduce on-site waste and lower costs.
Communication Implementations of LC techniques and LCM promote stakeholder collaboration and communication resulting in smoother workflow and less
rework.
Defect Completion of defects detected on-site reached 90%, which is much higher than traditional construction projects.
Health and safety Quality and safety management in LCM resulted in zero accidents occurring on site.
Continuous improvement Lessons learned and Scrum help to continuously improve project quality and productivity.
Involved stakeholders The use of LC techniques and LCM promotes their acceptance by traditional construction companies and helps to extend the further
applications in China.
Challenges
User requirement Difficulty of convincing the user to align their requirements with lean thinking.
Stakeholders’ willingness Stakeholders lack time and willingness to learn lean thinking, LC techniques and LCM.
Educational level and Difficult to change conventional customs and knowledge of traditional construction methods to LC techniques and LCM.
customs
Manpower management Dealing with the workload and worktime of construction personnel is a challenge since respect for humanity is the principle of lean.
Profit distribution Implementing LC techniques and LCM may cut down the profits of contractors when they first use them.
Project quality Insufficient design and construction time given but high demand due to the rapid expansion of the AEC industry.
Policy Adjustment of government policies may delay the schedule and increase the cost of the project, which may even result in abandoning the
project.
Material market Controlling the construction investment as the price of construction material is always fluctuant.

9
W. Xing, J.L. Hao, L. Qian et al. Journal of Cleaner Production 286 (2021) 124944

Fig. 8. Business type, working experience, and number of LC projects worked on.

Table 4 thinking, big room methodology, lean integrated project delivery,


LC techniques with which respondents had prior experience. retrospectives, team health assessments, and cost benefit analysis.
Ranking LC techniques No. of respondents Percentage As would be expected, respondents who had worked in the AEC
industry for more than 20 years had the most experience of
1 LPS 17 77.3%
1 JIT 17 77.3% implementing LC techniques and management methods in
3 Quality and safety management 13 59.1% projects.
4 Constraint analysis 11 50% On the question of waste reduction, Table 5 clearly shows that
5 Concurrent engineering 8 36.4% the majority of respondents experienced practical benefits from the
6 Kanban system 7 31.8%
7 LPDS 4 18.2%
implementation of LC techniques and LCM, with reduction of
8 Target value delivery 3 13.6% waiting times, defects, and underutilization of personnel being the
9 5S method 2 9.1% three most obvious. The results are generally in agreement with the
findings of Sarhan et al. (2017), although they also claimed that
divergence on types of waste reduction might occur due to the lean
Table 5 practices used, the project type, and the enterprise size. As a result,
Respondents’ opinions on the three most significant types of waste reduced through the opinions from respondents on waste reductions are well con-
lean practice implementation. nected to their experiences of lean practice implementation. In
Ranking Waste reduction No. of respondents Percentage general, LPS encourages the pull-driven method to match all the
resources and requirements on-site including labor, materials and
1 Waiting time 16 72.7%
2 Defects 14 63.6%
equipment arrangement (Song and Liang, 2011), and JIT is best for
3 Underutilizing people 13 59.1% shortening the waiting time for material delivery and corre-
4 Inventory 8 36.4% sponding transport issues (Solaimani and Sedighi, 2020). Also, the
5 Overproduction 6 27.3% increasing trending of digital technologies and prefabrication ap-
6 Motion 4 18.2%
plications have been identified in LC projects recently (Li et al.,
7 Transport 3 13.6%
8 Energy 1 4.5% 2019), which significantly improves standardization and brings
benefits to the project by reducing defects, inventory, and over-
production. Since most of respondents had experiences of LPS and
JIT, the reduction of waiting times, defects and underutilizing
implementation ratio, it can be explained that compatibility and
people may be due to those lean practice techniques.
profitability are the topmost criteria when considering whether or
not to implement lean practice (Aslam et al., 2020). Apart from
those listed, other lean techniques experienced by respondents 5.2.3. Benefits and challenges of lean practice implementation
were shadow boards, PPC boards, value stream mapping (VSM), A3 The values from Cronbach’s alpha indicate that the result ob-
tained in Table 6 are reliable. Of the nine benefits of using lean

Table 6
Level of importance scores for benefits of using LC techniques and LCM (1 ¼ Not at all important; 2 ¼ Slightly important; 3 ¼ Important; 4 ¼ Fairly important; 5 ¼ Very
important).

Ranking Benefit identified Level of importance score Mean score SD

1 2 3 4 5

1 Improvement of project productivity and quality 0 0 3 7 12 4.409 0.734


2 Improvement of construction workflow 0 1 4 5 12 4.273 0.935
3 Improvement of health and safety at work 0 1 6 4 11 4.136 0.990
4 Elimination of waste 1 1 3 8 9 4.045 1.090
5 Reduction of construction time and cost 1 0 8 4 9 3.909 1.109
6 Improvement of interpersonal relations and communications 0 2 7 7 6 3.773 0.973
7 Reduction of variability 0 5 3 7 7 3.727 1.162
8 Improvement of standardization 1 4 8 4 5 3.364 1.177
9 Reduction of material, water and energy consumption 0 6 10 3 3 3.136 0.990
Cronbach’s alpha ¼ 0.809: Good

10
W. Xing, J.L. Hao, L. Qian et al. Journal of Cleaner Production 286 (2021) 124944

Table 7
Scores of challenges when using LC techniques and LCM according to its level of difficulty (1 ¼ Not at all difficult; 2 ¼ Slightly difficult; 3 ¼ Difficult; 4 ¼ Fairly difficult; 5 ¼ Very
difficult).

Ranking Challenge identified Level of difficulty score Mean score SD

1 2 3 4 5

1 Lack of trust and abilities in the implementation of lean 1 2 5 6 8 3.818 1.181


2 Unwillingness of participant to face the drawbacks 2 3 8 4 5 3.318 1.249
3 Ineffective communication 0 7 5 9 1 3.182 0.958
4 Level of education of labor resources for lean 2 4 7 7 2 3.136 1.125
5 Insufficient knowledge about lean 1 7 5 6 3 3.136 1.167
Cronbach’s alpha ¼ 0.582: Poor

practice, “improvement of project productivity and quality” ob- the challenges. This is strong evidence to support the contention
tained the highest level of importance score from the respondents. that the use of LC techniques and LCM should be promoted for all
“Improvement of construction workflow”, “elimination of waste”, projects.
and “improvement of health and safety at work” were also regarded Overall, there is too much focus on data showing how LC im-
as fairly important benefits. Although “reduction of material, water proves safety, quality and efficiency, and not enough on the bar-
and energy consumption” received the lowest score, the re- riers to implementation of LC to the AEC industry. The respondent
spondents nevertheless rated it as an important benefit. This result in question felt that it is better to deal with the challenges before
is in line with the study of Bajjou and Chafi (2018), where con- implementing a greater degree of lean practice in AEC projects. As
struction time and cost were considered to be less important than a result, suggestions can be made from the perspectives of the
quality and safety, whilst they were still the key benefits of individual, team, government, and the AEC industry. One sug-
employing lean practice on construction projects. gestion from an individual perspective was that individual LC
Table 7 shows respondent scores for the five possible challenges performance should be incentivized in order to encourage LC
of using LC techniques and LCM. It can be seen that the respondents thinking at the individual level of the project. Accordingly,
considered the biggest challenge to be “lack of trust and abilities in training and continuous education either from internal or external
the implementation of LC techniques” with a score bordering on LC experts should be provided for both individual and project
the fairly difficult level of 4. The other four challenges are closer to teams to build and maintain enthusiasm for lean practice.
the difficult level score of 3. Respondents raised additional possible Furthermore, developing an understanding of LC and bringing
challenges, which primarily concerned subjective factors, such as lean concepts to the team should be proportional to their maturity
resistance to change, lack of respect, and fear of negative conse- level in terms of LC experience. It was also suggested that gov-
quences and blame. However, it should be noted that the result is ernment and regulatory authorities should play a greater role
less reliable than benefits obtained based on Cronbach’s alpha regarding the implementation and awareness of LC and LCM by
value. providing both financial and political support. Finally, a national
Since the defined levels of importance and difficulty are classi- LC initiative involving all stakeholders in the AEC industry should
fied using a similar scoring method, it is possible to compare the be implemented. If LC is expected by all stakeholders and people
benefits and challenges of using lean practice in a project by are held accountable from the top down, the full benefits of LC
comparing scores. Accordingly, a comparison of scores reveals that techniques and LCM can be realized.
the benefits of implementing lean practice in a project outweigh

Table 8
Comparative analysis of results from case study interviews and survey questionnaire.

Case study interviews Questionnaire survey

LC techniques and LCM methods LPS; LPS;


Kanban system; JIT;
JIT; Quality and safety management;
Concurrent engineering; Constraint analysis;
Constraint analysis; Concurrent engineering;
Quality and safety management. LPDS;
Target value delivery;
Kanban system;
5S method.
Three most reductions of waste Inventory; Waiting time;
Waiting time; Defects;
Defects Underutilizing people.
Three most important benefits Improvement of construction workflow; Improvement of project productivity and quality;
obtained Improvement of project productivity and quality; Improvement of construction workflow;
Improved collaboration and communication among Elimination of waste.
stakeholders.
Three most difficult challenges Educational level and customs of stakeholders; Lack of trust and abilities in the implementation of LC techniques;
encountered Lack of trust and abilities in the implementation of LC Unwillingness of participants to face the drawbacks of traditional
techniques and LCM; construction;
Fully address user requirement. Inefficient communication among stakeholders.

11
W. Xing, J.L. Hao, L. Qian et al. Journal of Cleaner Production 286 (2021) 124944

5.3. Comparative analysis avoidance of hazards, and accelerated construction progress. The
3D visualization, the construction process simulation, the clash
Since the interview and survey questions were similar, it is detection, the in-time inspection, all assisted by digital technology
reasonable to conduct a comparative analysis. Through a compar- and IoT allowed the LCM group to be in better control of the project.
ison of results, closer insights of LC techniques and LCM are pro- With respect to the comparative analysis, both the case study
vided. In order of their levels of significance, Table 8 lists the project stakeholders, and the global LC practitioners and scholars
comparative results from the case study interviews and question- shared the view that the most distinguishable benefits of imple-
naire survey with regards to LC techniques and LCM methods used, menting lean practice in a project are the reduction of waiting time
types of wastes reduction, benefits obtained, and challenges and of defects. The benefits accruing to construction workflow and
encountered. schedule, project quality and productivity, on-site health and
LPS and JIT were widely recognized by interviewees and by the safety, and communication and collaboration among stakeholders
largest number of survey respondents, which means that these two are also obvious and promising for maximizing the value of future
techniques may be the most appropriate to use when construction LC projects in China’s AEC industry.
firms first start to implement LC practices. Although concurrent
engineering, constraint analysis, and quality and safety manage- 6.2. Limitations and recommendations
ment are all part of traditional construction management, their use
as a part of a lean thinking approach will give these strategies a new Firstly, there is the question of whether the LC case study project
meaning and stimulate improvements in project quality and pro- is representative of the normal conditions in China’s AEC industry.
ductivity. Although the Kanban system was a core method that The client and the construction manager were familiar with lean
supported construction progress in the case study project, ac- principles and strongly believed in implementing them in con-
cording to global LC experts it is rarely used. However, since the struction projects. In addition, other stakeholders had been trained
case study project achieved the expected results on the workflow, before the project. By contrast, the majority of local construction
resource distribution, and communication between stakeholders, firms in China are still steeped in traditional construction methods.
there is a strong case for recommending that the Kanban system be Therefore, in order to obtain findings that are more representative
further developed for use in China’s ACE industry. Since survey of the local situation in China’s ACE industry, it is recommended
respondents identified a number of additional LC techniques, there that a purely domestic LC project should be investigated with
is a good possibility of increasing the level of LC implementation particular regard to the project type, the contract form, the con-
once ACE stakeholders become more familiar with applying lean struction method, and the management system.
principles to their projects. Secondly, according to some case study interviewees, lean
Interviewees and survey respondents held a similar view that practice applied to industrial construction projects are slightly
waiting time and defects are reduced through the implantation of different to other types of projects, particularly with respect to the
LC techniques and LCM. Interviewees observed that inventory lean assembly process and lower tolerance of quality flaws. Also,
waste was the most significant type of waste reduced, but this was prefabrication as used in the case study project is not as efficient for
mainly due to the measures taken to deal with the project’s limited industrial construction projects as it is for residential projects,
working space; the strictly controlled material quantity and where modular construction makes it easier to achieve project
entering sequence helped avoid unnecessary material storage. As value and reduce on-site waste. Consequently, since findings from
for underutilizing people, survey respondents felt that the appli- the case study interviews are based on an industrial type project,
cation of LC helped to coordinate labor resources between different they can only be partially applied to residential and other types of
disciplines and thereby reduced labor costs. Other potential bene- project.
fits and possible challenges observed by interviewees and survey Thirdly, even though the questionnaire survey sought the views
respondents were aligned. of LC practitioners and scholars in the global AEC community, since
the interviews focused exclusively on a LC industrial project in
6. Conclusions, limitations and recommendations China’s AEC industry, there is a limitation with regard to universally
applying the study’s findings. This limit is exacerbated by the fact
6.1. Conclusions that only three interviewees volunteered feedback from their in-
dividual experiences, with other stakeholders such as designers,
To better understand how LC techniques and LCM can be contractors, and construction personnel neglecting to do so. There
implemented in ACE projects in China, a case study of a project in is no denying that the aforementioned stakeholders are crucial
Suzhou, China was conducted. The LC techniques and LCM when implementing LC practices, as they greatly influence the
employed were divided into five categories: ‘LPS and Kanban sys- construction workflow and project quality. While it may be un-
tem’, ‘JIT and prefabrication’, ‘digital technologies and IoT’, ‘quality derstandable that they would pay more attention to the execution
and safety’, and ‘continuous improvement and Scrum’. Interviews of their own particular discipline rather than managerial strategies
were conducted with stakeholders of the case study project to elicit and interdisciplinary knowledge, it is nevertheless important that
their views on the benefits and challenges of implementing LCM in future research make a concerted effort to elicit their feedback on
the project. A questionnaire survey in line with the interview the implementation of LC techniques and LCM.
questions was conducted among global LC practitioners and Respondents to the questionnaire were mostly from countries or
scholars to collect their opinions of LC techniques and LCM. regions outside of China, therefore their experiences and attitudes
Through a comparative analysis of the case study interviews and are more reflective of the global trend towards implementation of
results from the questionnaire survey, valuable conclusions can be LC. From the comparative analysis, it is clear there is a gap between
drawn from both the Chinese and global perspectives. the Chinese and global AEC industries with respect to the practice
Implementation of lean practice in the case study project and experience of LC. Nevertheless, the Kanban system in the case
brought significant benefits to the project in terms of schedule, study project played a vital role in improving the workflow and
workflow, quality and safety issues. The adoption of prefabricated visualization of the construction process, whereas prefabrication,
elements led to more precise engineering, reduced on-site waste digital technologies and IoTs, and continuous improvement
generation, better mechanical and durability performance, significantly promoted project performance. Accordingly, it is
12
W. Xing, J.L. Hao, L. Qian et al. Journal of Cleaner Production 286 (2021) 124944

recommended that the fundamental lean practices of LPS and JIT be Koskela, L., 1993. Lean Production in Construction. Automation and Robotics in
Construction X: Proceedings of the 10th International Symposium on Auto-
adopted by construction projects in China, and that future research
mation and Robotics in Construction (ISARC), Houston, Texas, USA, 24-26 May,
should focus on comprehensive lean practice implementation and 1993, pp. 47e54. Elsevier Science Ltd.
application of the Kanban system in China’s AEC industry. Li, L., Li, Z., Li, X., Wu, G., 2019. A Review of Global Lean Construction during the Past
Two Decades: Analysis and Visualization Engineering. Construction and
Architectural Management.
CRediT authorship contribution statement Li, S., Fang, Y., Wu, X., 2020. A systematic review of lean construction in Mainland
China. J. Clean. Prod. 257, 120581. https://doi.org/10.1016/j.jclepro.2020.120581.
Weiqi Xing: Methodology, Investigation, Data curation, Formal Li, S., Wu, X., Zhou, Y., Liu, X., 2017. A study on the evaluation of implementation
level of lean construction in two Chinese firms. Renew. Sustain. Energy Rev. 71,
analysis, Writing - original draft. Jian Li Hao: Conceptualization, 846e851. https://doi.org/10.1016/j.rser.2016.12.112.
Supervision, Writing - review & editing, Project administration, Liao, Y., 2018. Research on Implementation Strategy of Lean Construction Man-
Funding acquisition. Liang Qian: Methodology, Supervision, agement in Chinese Construction Enterprises. 2nd International Conference on
Culture, Education and Economic Development of Modern Society (ICCESE
Writing - review & editing. Vivian W.Y. Tam: Methodology, Data 2018). Atlantis Press.
curation, Supervision. Karol S. Sikora: Supervision, Writing - re- Low, S.P., Min, W., 2005. Just-in-time management in the ready mixed concrete
view & editing. industries of Chongqing, China and Singapore. Constr. Manag. Econ. 23 (8),
815e829. https://doi.org/10.1080/01446190500040638.
Meng, X., 2019. Lean management in the context of construction supply chains. Int.
Declaration of competing interest J. Prod. Res. 57 (11), 3784e3798.
Miller, C.J., Packham, G.A., Thomas, B.C., 2002. Harmonization between main con-
tractors and subcontractors: a prerequisite for lean construction? J. Construct.
The authors declare that they have no known competing
Res. 3 (1), 67e82.
financial interests or personal relationships that could have Min, Y., Su, Z., 2007. Research on lean construction management pattern [in Chi-
appeared to influence the work reported in this paper. nese]. Constr. Econ. 291 (1), 52e55.
MOHURD, 2020. Information On Green Building Implementation in China [Online].
Ministry of Housing and Urban-Rural Development of the People’s Republic of
Acknowledgements China. Available: http://www.mohurd.gov.cn/wjfb/202007/t20200724_246492.
html.
The authors wish to acknowledge the support from the NBS, 2019. Gross Output Value of Construction 2019 [Online]. National Bureau of
Statistics of China. Available: http://data.stats.gov.cn/english/easyquery.htm?
Department of Civil Engineering, Xi’an Jiaotong-Liverpooll Univer- cn¼C01.
sity, China RDF (2016-01-32), Key Special Fund Exploring Program Paez, O., Salem, S., Solomon, J., Genaidy, A., 2005. Moving from lean manufacturing
(2018-E-29) from Suzhou Industrial Park, China. The authors are to lean construction: toward a common sociotechnological framework Human.
Factors Ergon. Manuf. & Service Industr. 15 (2), 233e245.
also grateful for LCM group and its staff to provide the opportunity Richard, P., Liu, Z., Descamps, T., Sikora, K.S., 2019. Effect of Concrete Modification on
to collect the data for the research. Shear of Connections for TimbereConcrete Composites Proceedings Of the
Institution Of Civil Engineers-Structures And Buildings, pp. 1e14. https://
doi.org/10.1680/jstbu.19.00046.
References Sacks, R., Treckmann, M., Rozenfeld, O., 2009. Visualization of work flow to support
lean construction. J. Construct. Eng. Manag. 135 (12), 1307e1315.
Anisimova, T., Thomson, S.B., 2012. Enhancing multi-method research methodolo- Saieg, P., Sotelino, E.D., Nascimento, D., Caiado, R.G.G., 2018. Interactions of building
gies for more informed decision-making. JOAAG 7 (1), 96e104. information modeling, lean and sustainability on the architectural, engineering
Aslam, M., Gao, Z., Smith, G., 2020. Exploring factors for implementing lean con- and construction industry: a systematic review. J. Clean. Prod. 174, 788e806.
struction for rapid initial successes in Construction. J. Cleaner Prod. 123295. https://doi.org/10.1016/j.jclepro.2017.11.030.
Babalola, O., Ibem, E.O., Ezema, I.C., 2019. Implementation of lean practices in the Salem, O., Solomon, J., Genaidy, A., Minkarah, I., 2006. Lean construction: from
construction industry: A systematic review. Build. Environ. 148, 34e43. theory to implementation. J. Manag. Eng. 22 (4), 168e175.
Bajjou, M.S., Chafi, A., 2018. Lean construction implementation in the Moroccan Sarhan, J.G., Xia, B., Fawzia, S., Karim, A., 2017. Lean construction implementation in
construction industry: awareness, benefits and barriers. J. Eng. Des. Technol. 16 the Saudi Arabian construction industry. Constr. Econ. Build. 17 (1), 46e69.
(4), 533e556. Sikora, K.S., Klemm, A.J., 2014. The effect of superabsorbent polymers on perfor-
Ballard, G., 1994. The Last Planner Northern. California Construction Institute, mance of fly ash cementitious mortars exposed to accelerated freezing/thawing
Monterey, California, pp. 1e8. conditions. Int. J. Comput. Methods Exp. Measur. 2 (3), 255e268. https://
Ballard, G., Howell, G., 1995. Toward construction JIT. Lean Constr. 291, 300. doi.org/10.2495/CMEM-V2-N3-255-268.
Ballard, G., Howell, G., 2003. Lean project management. Build. Res. & Infor. 31 (2), Solaimani, S., Sedighi, M., 2020. Toward a holistic view on lean sustainable con-
119e133. struction: a literature review. J. Clean. Prod. 248, 119213.
Carvajal-Arango, D., Bahamo  n-Jaramillo, S., Aristizabal-Monsalve, P., Va squez- Song, L., Liang, D., 2011. Lean construction implementation and its implication on
Hern andez, A., Botero, L.F.B., 2019. Relationships between lean and sustainable sustainability: a contractor’s case study. Can. J. Civ. Eng. 38 (3), 350e359.
construction: positive impacts of lean practices over sustainability during Tam, V.W., Hao, J.L., 2014. Prefabrication as a mean of minimizing construction
construction phase. J. Clean. Prod. 234, 1322e1337. waste on site. Int. J. Constr. Manag. 14 (2), 113e121. https://doi.org/10.1080/
Dave, B., Kubler, S., Fra€mling, K., Koskela, L., 2016. Opportunities for enhanced lean 15623599.2014.899129.
construction management using Internet of Things standards Automation in Tezel, A., Taggart, M., Koskela, L., Tzortzopoulos, P., Hanahoe, J., Kelly, M., 2020. Lean
construction, 61, pp. 86e97. construction and BIM in small and medium-sized enterprises (SMEs) in con-
Feng, S., Liu, Y., 2008. Research on theoretical lean construction system [in Chinese]. struction: a systematic literature review. Can. J. Civ. Eng. 47 (2), 186e201.
Project Manag. Technol. 3, 18e23. Tommelein, I.D., 1998. Pull-driven scheduling for pipe-spool installation: simulation
Gable, G.G., 1994. Integrating case study and survey research methods: an example of lean construction technique. J. Construct. Eng. Manag. 124 (4), 279e288.
in information systems. Eur. J. Inf. Syst. 3 (2), 112e126. Wang, S., 2019. Prospect overview on 2019 Chinese AEC industry development [in
Gao, S., Low, S.P., 2014. Lean Construction Management: the Toyota Way. Springer. Chinese]. Constr. Arch. 873 (1), 15e20.
Hao, J.L., Yuan, H., Liu, J., Chin, C.S., Lu, W., 2019. A model for assessing the economic Wang, Y., 2015. On theoretic research of lean construction and development [in
performance of construction waste reduction. J. Clean. Prod. 232, 427e440. Chinese]. Shanxi Archit. 41 (22), 226e228.
https://doi.org/10.1016/j.jclepro.2019.05.348. Xing, W., Hao, J., Wu, D., Qian, L., Sikora, K.S., 2019. Lean Construction Application: A
Heigermoser, D., de Soto, B.G., Abbott, E.L.S., Chua, D.K.H., 2019. BIM-based Last Case Study in Suzhou, China. Sustainable Buildings and Structures: Building a
Planner System tool for improving construction project management Auto- Sustainable Tomorrow: Proceedings of the 2nd International Conference in
mation in. Construction 104, 246e254. Sustainable Buildings and Structures (ICSBS 2019), October 25-27, 2019, Suzhou,
Heravi, G., Rostami, M., Kebria, M.F., 2020. Energy consumption and carbon emis- China. CRC Press, p. 365.
sions assessment of integrated production and erection of buildings’ pre- Yang, J., 2017. The research on green construction management model based on
fabricated steel frames using lean techniques. J. Clean. Prod. 253, 120045. lean construction [in Chinese]. J. Changchun Inst. Technol. 18 (1), 77e79.
Huang, Y., Gao, S., 2011. Consideration on lean construction applied in China con- Zhao, B., Niu, B., Wang, Y., 2011. The interactive application of lean construction and
struction industry [in Chinese]. Construct. Technol. 22 (40), 93e95. BIM technology in construction [in Chinese]. J. Eng. Manag. 5.
Issa, U.H., 2013. Implementation of lean construction techniques for minimizing the Zhou, J., Tam, V.W., Qin, Y., 2018. Gaps between awareness and activities on green
risks effect on project construction time. Alexandria Eng. J. 52 (4), 697e704. construction in China: a perspective of on-site personnel. Sustainability 10 (7),
Jiang, S., Su, Z., 2004. Lean Construction: a kind of advanced system of construction 2266. https://doi.org/10.3390/su10072266.
[in Chinese]. Optim. Capital Constr. 3.

13

You might also like