1. GENERAL
1.1 Demolition shall be carried out by hand operated pneumatic breaker at beam/ slab joint next to
neighboring unit. Oxy-acetylene torch may be used to cut the reinforcement. Mobile air compressor shall be
placed on 1st floor.
1.2 Demolition shall begin on the roof and proceed down floor by floor to the 1st floor. The concrete of each
structural element shall be broken down gradually. The reinforcement shall be left in placed until the concrete
is broken away and when its support is no longer need,
2. DEMOLITION SEQUENCE: