PRODUCTIVITY SHEET

CIVIL WORKS
Production Mason Hrs Carp.Hrs Helper Hrs. S/Fixer Hrs Opr. Total hrs
No Activities Crew Size
per 9 hrs Unit (per unit) (per unit) (per unit) (per unit) (per unit) (per unit)
A Form Works
Form work to footing (isolated 1 m x 1m) 2 C + 1H 12 m2 1.50 0.75 2.25
Form work to isolated footing / strip >1M 2 C + 1H 16 m2 1.13 0.56 1.69
Form work to raft < .5m depth 2 C + 1H 14 m2 1.29 0.64 1.93
Form work to raft D < .5m depth 2 C + 1H 18 m2 1.00 0.50 1.50
Form work to the beam on PCC 2 C + 1H 12 m2 1.50 0.75 2.25
Form work to high level tie beams D >.45m 2 C + 1H 10 m2 1.80 0.90 2.70
Form work to column necks 2 C + 1H 4 m2 4.50 2.25 6.75
Form work to U/G water tank 2 C + 1H 6 m2 3.00 1.50 4.50
Form work to basement retaining walls 2 C + 1H 9 m2 2.00 1.00 3.00
Form work to column (small size) 20 x 40cm 2 C + 1H 7 m2 2.57 1.29 3.86
Form work to column (Large size) 2 C + 1H 9 m2 2.00 1.00 3.00
Form work to D/s beam internal (Shallow) 30cm 2 C + 1H 6 m2 3.00 1.50 4.50
Form work to D/s beam internal (Deep) >30cm 2 C + 1H 7 m2 2.57 1.29 3.86
Form work to D/s beam external (Shallow) 30cm 2 C + 1H 4 m2 4.50 2.25 6.75
Form work to D/s beam external (Deep) 30 cm 2 C + 1H 6 m2 3.00 1.50 4.50
Form work to lift walls Single core 2 C + 1H 8 m2 2.25 1.13 3.38
Form work to lift walls multicore 2 C + 1H 6 m2 3.00 1.50 4.50
Form work to slab decking (10ft) hourdi 2 C + 1H 16 m2 1.13 0.56 1.69
Form work to slab decking (10ft) D/S beams 2 C + 1H 12 m2 1.50 0.75 2.25
Form work to slab decking (>10ft) hourdi 2 C + 1H 12 m2 1.50 0.75 2.25
Form work to slab decking (>10ft) D/S beams 2 C + 1H 10 m2 1.80 0.90 2.70
Form work to staircase (Non-Spiral) 2 C + 1H 4 m2 4.50 2.25 6.75
Form work to balcony parapets 2 C + 1H 6 m2 3.00 1.50 1.50 6.00
Form work to roof parapets 2 C + 1H 8 m2 2.25 1.13 1.13 4.50

Sheet: 1 of 5
PRODUCTIVITY SHEET
CIVIL WORKS
Production Mason Hrs Carp.Hrs Helper Hrs. S/Fixer Hrs Opr. Total hrs
No Activities Crew Size
per 9 hrs Unit (per unit) (per unit) (per unit) (per unit) (per unit) (per unit)
new Pre - prepared Column/Wall 2 C + 1H 15 m2 1.20 0.60
new Pre - prepared beams 2 C + 1H 20 m2 0.90 0.45
new Pre - prepared staircase 2 C + 1H 20 m2 0.90 0.45
new Pre - prepared slab 2 C + 1H 30 m2 0.60 0.30
B Reinforcement
Fix rebar to footing & tie beams 1 SF 250 kg 0.04 0.04
Fix rebar to wall, columns, beams, solid slabs 1 SF 200 kg 0.05 0.05
Fix rebar to ribs of hourdi slabs 1 SF 180 kg 0.05 0.05
Fix rebar to mesh reinforcement 1 SF 50 kg 0.18 0.18
Fix rebar to hidden beams 1 SF 225 kg 0.04 0.04
C CONCRETE PLACEMENT WORKS
Concrete to pile caps, by pump 6M+18H+1C+1SF 180 CM 0.3 0.05 0.90 0.05 1.30
Concrete to PCC blinding (100mm thick) 1M+10H 27 CM 0.33 3.33 3.67
Concrete to slabs/beams, by pump 6M+18H+1C+1SF 180 CM 0.3 0.05 0.90 0.05 1.30
Concrete to slabs/beams, by crane 1M+6H+0.5O+.5SF 27 CM 0.33 2.00 0.17 0.17 2.67
Concrete to walls/columns, by pump 4M+16H+2C 81 CM 0.44 0.22 1.78 2.44
Concrete by site mix 1M+12H+0.5C 9 CM 1 0.50 12.00 13.50
D Masonry Work
Hollow Blockwork (100,150 & 200mm) ht - 3m 1M +1 H 120 No 0.075 0.075 0.15
Hollow Blockwork (large panels) > 4m length 1M +1 H 140 No 0.064 0.064 0.13
Solid Block 1M +1 H 95 No 0.095 0.095 0.19
Solid blockwork as raft forms 1M +1 H 110 No 0.082 0.082 0.16
E Plaster Work
Plaster (int.) wall final coat 1M + 1 H 16 m2 0.56 0.56 1.13
Plaster (int.) wall rush coat 1H 75 m2 0.24 0.24

Sheet: 2 of 5
PRODUCTIVITY SHEET
CIVIL WORKS
Production Mason Hrs Carp.Hrs Helper Hrs. S/Fixer Hrs Opr. Total hrs
No Activities Crew Size
per 9 hrs Unit (per unit) (per unit) (per unit) (per unit) (per unit) (per unit)
Plaster (int.) wall mesh coat 1H 100 m2 0.09 0.09
Plaster (int.) wall hacking/chipping 1H 100 m2 0.09 0.09
Plaster (int.) wall guide points 1M + 1 H 100 m2 0.09 0.09 0.18
Plaster (int.) wall corner beads 1M + 1 H 100 m2 0.09 0.09 0.18
Total 0.74 1.16 1.91
new Plaster -internal (total) 1m+1h 16 m2 1.05 0.65 1.70
new Plaster -external (total) 1m+1h 16 m2 1.24 0.84 2.08
0.00
Plaster (ext.) walls with grooves 1M + 1 H 10 m2 0.90 0.90 1.80
Plaster (ext.) walls without grooves 1M + 1 H 12 m2 0.75 0.75 1.50
Plaster (ext.) walls rush coat 2H 150 m2 0.12 0.12
Plaster (ext.) walls mesh coat 1H 100 m2 0.09 0.09
Plaster (ext.) walls hacking 1H 100 m2 0.09 0.09
Plaster (ext.) walls guide points 1M + 1 H 100 m2 0.09 0.09 0.18
Plaster (ext.) walls corner beads 1M + 1 H 100 m2 0.09 0.09 0.18
Total 1.83 2.13
F Ceramic Work 0.00
Ceramic tiles to wall by motar 1M + 1 H 8 m2 1.13 1.13 2.25
Ceramic tiles to wall motar to corridors 1M + 1 H 9 m2 1.00 1.00 2.00
Ceramic tiles to walls cut pieces 1M 20 m2 0.45 0.45
Ceramic tiles to walls grouting 1H 50 m2 0.18 0.18
Ceramic tiles to walls by glue 1M + 1 H 12 m2 0.75 0.75 1.50
Ceramic tiles to walls corridors, by glue 1M + 1 H 13 m2 0.69 0.69 1.38
Ceramic tiles to walls by glue cut pieces 1M 20 m2 0.45 0.45
Ceramic tiles to walls by glue gouting 1H 50 m2 0.18 0.18

Sheet: 3 of 5
PRODUCTIVITY SHEET
CIVIL WORKS
Production Mason Hrs Carp.Hrs Helper Hrs. S/Fixer Hrs Opr. Total hrs
No Activities Crew Size
per 9 hrs Unit (per unit) (per unit) (per unit) (per unit) (per unit) (per unit)
Ceramic tiles to floor 1M + 1 H 10 m2 0.90 0.90 1.80
Ceramic tiles to floor in halls 1M + 1 H 12 m2 0.75 0.75 1.50
Ceramic tiles to floor cut pieces 1M 20 m2 0.45 0.45
Ceramic tiles to floor grouting 1H 50 m2 0.18 0.18
Ceramic skirting by glue 2M +1 H 50 mtr 0.36 0.18 0.54
Ceramic skirting by glue to halls, corridors 2M +1 H 60 mtr 0.30 0.15 0.45
G Tiling Works

Mosaic/Terrazo tiles to roofs 1M + 1 H 16 m2 0.56 0.56 1.13

Mosaic/Terrazo tiles to floors 1M + 1 H 14 m2 0.64 0.64 1.29

Mosaic skirting to halls 2M +1 H 50 mtr 0.36 0.18 0.54

Mosaic skirting/flush/recessed 2M +1 H 28 mtr 0.64 0.32 0.96

Grouting/sealing to roof/floor tiles 1H 25 mtr 0.36 0.36

H KERBING/BLOCK/PAVING WORKS

PCC to kerb/base 1M + 1 H 0.00

Haunching to kerb base 1M + 1 H 0.00

Kerbstone (without PCC) 1M + 1 H 15 mtr 0.60 0.60 1.20

Interlock paving on pre-prepared sub-base 1M + 2 H 40 m2 0.23 0.45 0.68

Screed works including preparation, 50mm thick 1M + 1 H 15 m2 0.60 0.60 1.20

I MANHOLE/DRAINAGE CONSTRUCTION

Excavation for drains/manholes (sand) 1H 5 cm 1.80 1.80

Backfilling for drains/manholes 1H 10 cm 0.90 0.90

Blockwork for manholes 2M + 1 H 4 Nos 4.50 2.25 6.75

Sheet: 4 of 5
PRODUCTIVITY SHEET
CIVIL WORKS
Production Mason Hrs Carp.Hrs Helper Hrs. S/Fixer Hrs Opr. Total hrs
No Activities Crew Size
per 9 hrs Unit (per unit) (per unit) (per unit) (per unit) (per unit) (per unit)
Plaster to manholes 2M + 1 H 4 Nos 4.50 2.25 6.75

Benching to manholes 2M + 1 H 8 Nos 2.25 1.13 3.38

Fix covers to manholes 1M + 1 H 2 Nos 4.50 4.50 9.00

Fix gulley traps 1M + 1 H 1 No 9.00 9.00 18.00


J MISCELLANEOUS LABOUR WORKS
Bitumen paint to concrete/blockwork surfaces 1H 40 m2 (1coat) 0.23 0.23
Hacking of concrete surfaces 1H 50 m2 0.18 0.18
Fixing of flexcell sheets 1H 8 m2 1.13 1.13
Pile cutting/dressing dia. >450mm 1H 1 Nos 9.00 9.00
Pile cutting/dressing smaller dia. <450mm 1H 2 Nos 4.50 4.50
Vertical sealant (12 mm) 1H 25 mtr 0.36 0.36
Horizontal sealant (12mm) 1H 50 mtr 0.18 0.18
Roof preparation for LW concrete, guide points 1M+1H 50 m2 0.18 0.18 0.36
Angle fillet fixing 1M+1H 40 mtr 0.23 0.23 0.45
Hourdi block shifting & fixing to slab 2H 200 Nos 0.09 0.09
MISCELLANEOUS CARPENRY WORKS
A/c subframe manufacturing/fixing 1C 5 Nos 1.80 1.80
Door subfram manufacturing 1C 4 Nos 2.25 2.25
Water bar fixing 1C 20 mtr 0.45 0.45
L Backfill & compaction 3O+ 2H 75 m3 0.24 0.36 0.60