Professional Documents
Culture Documents
220802DJPCME715 Demolition Work Procedure Rev - 00
220802DJPCME715 Demolition Work Procedure Rev - 00
EPCI-2
Contract N.
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
DEMOLITION WORK PROCEDURE AT PK 52 Page 2 of 21
EniMuara Bakau B.V. 02 EX-CO
NILAM
The purpose of this document is to provide demolition work procedure at PK52 Nilam in Jangkrik new
Abstract
field development. This procedure define the requirements for preparation and execution of
fabrication and installation activities during construction work of Jangkrik new field developments.
Document Verification
Signature
Prepared by Date
Enggartyasto Haryoyudhanto 07-Jan-2019
Vendor Prepared
Signature
Checked by Date
Basir Sinaga 07-Jan-2019
Signature
Approval by Date
Jakarias Haloho 07-Jan-2019
Proj. Dev.
Proj. Dev.
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
DEMOLITION WORK PROCEDURE AT PK 52 Page 3 of 21
EniMuara Bakau B.V. 02 EX-CO
NILAM
REVISION LIST
RECORD OF AMENDMENT
No Section Para No Description of Changes
HOLD LIST
Section Description of Hold
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
DEMOLITION WORK PROCEDURE AT PK 52 Page 4 of 21
EniMuara Bakau B.V. 02 EX-CO
NILAM
TABLE OF CONTENTS
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
DEMOLITION WORK PROCEDURE AT PK 52 Page 5 of 21
EniMuara Bakau B.V. 02 EX-CO
NILAM
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
DEMOLITION WORK PROCEDURE AT PK 52 Page 6 of 21
EniMuara Bakau B.V. 02 EX-CO
NILAM
1.0 INTRODUCTION
1.1 Project Overview
Jangkrik field is located about 70 km from the coast, in the Muara Bakau permit area,
Makassar Strait, offshore Kalimantan, at water depth ranging from 250 to 500 m. ENI
through its Indonesian subsidiary, operates the Muara Bakau PSC.
The treated gas and condensate from FPU are exported via 24 inch treated gas export
pipeline and 4 inch condensate export pipeline to shore at Sapi landfall. An onshore
receiving facility (ORF) fiscal metering system for gas and condensate is located
approximately 4 km downstream of Sapi Landfall. Gas and condensate pipelines are the
tie-in to existing East Kalimantan pipeline network. Another tie-in at KM 21.65 is required
for the gas line to allow the full capacity of jangkrik gas. For this purpose, a 15 km of new
pipelines is to be installed parallel to existing line with PHM ROW from ORF to KM 21.65,
and will be tie-in to existing 20 inch Handil-Nilam pipeline and modification to be done at
Nilam, BEM, and KM 53 inside POMA area. Final destination of Jangkrik treated gas is to
the Bontang LNG Plant and domestic Bontang market; and the final destination of Jangkrik
condensate is to Senipah Plant.
The purpose of this document is to provide the detail method and sequence for demolition
work PK52 Nilam at EKS Modification at BEM and KM 53 Area Project. This procedure define
the demolition such as ground back filing, compacting, scaffolding, bolting unbolting, and
lifting activities.
2.0 REFERENCES
The following documents are referred to in this document.
2.1 Company Reference
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
DEMOLITION WORK PROCEDURE AT PK 52 Page 7 of 21
EniMuara Bakau B.V. 02 EX-CO
NILAM
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
DEMOLITION WORK PROCEDURE AT PK 52 Page 8 of 21
EniMuara Bakau B.V. 02 EX-CO
NILAM
KM 53 Kilometer 53 Location
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
DEMOLITION WORK PROCEDURE AT PK 52 Page 9 of 21
EniMuara Bakau B.V. 02 EX-CO
NILAM
4.2 Superintendent
He is responsible for all activities at yard, preparation tools and equipment, prepare tie-in materials
including installation works as per approved procedure, COMPANY specification, HSE requirement
and ensure all works are in line with work plan.
4.8 Slinger
Participate in the planning and TRA of lifting operation and pre-lift safety meeting. Prepare the
load for lifting according to LOP and complete pre-use inspection of liftng accessories before use.
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
DEMOLITION WORK PROCEDURE AT PK 52 Page 10 of 21
EniMuara Bakau B.V. 02 EX-CO
NILAM
4.10 Rigger
Riggers are responsible for:
o Attaching, detaching slings to and from the load.
o Riggers are appointed where it is necessary to ensure that loads are correctly attached to
the lifting equipment.
o Rigger also monitoring/ control the risk due to equipment movement and guide/ inform to
lifting superintendent/ safety man.
4.12 Foreman
Shall be responsible for overall demolition activity site. He shall be responsible for the works and
will oversee all demolition work as per approved method statement, COMPANY specification and
HSE requirement.
4.13 AGT
The AGT’s are approved persons who have been formally trained (Certified) and
authorized in gas testing techniques and methods.
Authorized to test for the presence of flammable vapors, toxic gas and oxygen as
requested by the Performing Authority (PA).
Competent to carry out gas testing on all activities including testing for explosive
atmospheres and oxygen deficiency.
Ensure the work site in a safe condition report the result of his tasks direct to the
Performing Authority.
Continue monitor the atmosphere whilst personnel are within the confined space
entry.
Keep entry log up to date at all time with CSE permit its must be keeped with and
returned with the PTW
Level 3 (CTR) Competent to monitor continuously using a personal gas detector
4.15 Helper
To assist fitter and support demolition activity.
4.16 Scaffolder
Assure that all scaffolding they will be working on has been installed and inspected
and is safe for the employee to work on, before beginning work.
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
DEMOLITION WORK PROCEDURE AT PK 52 Page 11 of 21
EniMuara Bakau B.V. 02 EX-CO
NILAM
Wear all appropriate PPE and an approved harness with shock absorbing lanyards
with double locking snap hooks will be worn at all times while working off of a scaffold.
He is responsible for safety of the scaffolding teams during erection, dismantling
operations including selection of PPE and protection of working area.
Finding out details of work to be carried out for the scaffold and to ensure that it is
properly constructed and of the correct type for the requested duty.
Shall have scaffolding training and certified by third party.
Shall have working at height training and certified.
Scaffolder shall be pass assessment by COMPANY.
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
DEMOLITION WORK PROCEDURE AT PK 52 Page 12 of 21
EniMuara Bakau B.V. 02 EX-CO
NILAM
Driver shall ensure that he and his passenger are fastened their seat belt prior driving
vehicle.
Driver must turn off the engine while refueling.
Driver shall perform a daily inspection checklist of their vehicle as per attached formats and
reports submitted to transport coordinator on daily basis.
All vehicles incidents involving COMPANY owned / leased vehicle on company business
shall be reported to transport coordinator immediately.
Driver shall assure that STNK & SIM vehicle license is valid.
Driver shall have a valid MCU.
Driver shall assure that his vehicle is maintained and ready.
Driver shall not use mobile phone, under alcoholic or additive substances while driving.
Driver shall have awareness to stop unsafe action or condition.
5.0 SAFETY
5.1 Coordination Meeting and Tool Box Talk (TBT)
To ensure the safe execution, CONTRACTOR shall perform daily Tool Box Talk (TBT) in every
beginning working shift before the work started. In this TBT the Construction Lead/ Supervisor will
explain the work which will be done during the working shift, explain the HSSE risk on every
working step, and the mitigation to eliminate/minimize the risk to all of the working team.
Daily coordination meeting between COMPANY and CONTRACTOR will be done to discuss on the
elapsed day daily progress report focusing on the construction concern and the solution plan.
Weekly progress meeting will be done in weekly basis, discussing on the elapsed week progress
report, focusing on the HSSE & construction concern and the solution plan, next 2 weeks look
ahead schedule, and recovery plan (if any).
5.2 General
To minimize the risk of accidents during the work, safety precautions and risk assessment has
been prepared as guidelines for the all personnel involved. Safety induction shall be organized
upon mobilization of all personnel on the site, including COMPANY personnel.
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
DEMOLITION WORK PROCEDURE AT PK 52 Page 13 of 21
EniMuara Bakau B.V. 02 EX-CO
NILAM
5.7 Environment
The installation activities should minimized impact to the environment. Any waste material and or
unused material shall be discharged to designated area that approved by Government bodies
6.0 RESOURCES
6.1 Equipment and Tool
1. Site Manager 1 Person
2. Superintendent 1 Person
3. Piping Supervisor 1 Person
4. Lifting Supervisor 1 Person
5. Quality Control Inspector 1 Person
6. Safety Officer 1 Person
7. Excavator Operator 1 Person
8. Rigger 4 Persons
9. Banksman / Signaller 1 Person
10. Foreman 1 Person
11. AGT 1 Person
12. Pipe Fitter 4 Persons
13. Helper 4 Persons
14. Scaffolder 6 Persons
15. Scaffolder Inspector 1 Person
16. Boom Truck Operator 1 Person
17. Crane Operator 1 Person
18. Transport Coordinator 1 Person
19. Vehicle Driver 1 Person
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
DEMOLITION WORK PROCEDURE AT PK 52 Page 14 of 21
EniMuara Bakau B.V. 02 EX-CO
NILAM
Demolition work shall be conducted in struct accordance with approved procedure and LOP. Any
variation from the agreed procedure and LOP shall result in the job being stopped and reassessed to
ensure continued safe operation.
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
DEMOLITION WORK PROCEDURE AT PK 52 Page 15 of 21
EniMuara Bakau B.V. 02 EX-CO
NILAM
7.3 Ball Valve 20” 600#, 2EA and 4” Piping Line Removal Sequence
4” Piping Line Removal
1. Remove all valves and equipment that connected to demolished line.
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
DEMOLITION WORK PROCEDURE AT PK 52 Page 16 of 21
EniMuara Bakau B.V. 02 EX-CO
NILAM
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
DEMOLITION WORK PROCEDURE AT PK 52 Page 17 of 21
EniMuara Bakau B.V. 02 EX-CO
NILAM
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
DEMOLITION WORK PROCEDURE AT PK 52 Page 18 of 21
EniMuara Bakau B.V. 02 EX-CO
NILAM
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
DEMOLITION WORK PROCEDURE AT PK 52 Page 19 of 21
EniMuara Bakau B.V. 02 EX-CO
NILAM
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
DEMOLITION WORK PROCEDURE AT PK 52 Page 20 of 21
EniMuara Bakau B.V. 02 EX-CO
NILAM
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
DEMOLITION WORK PROCEDURE AT PK 52 Page 21 of 21
EniMuara Bakau B.V. 02 EX-CO
NILAM