You are on page 1of 1

Location :

H
H
N

T
LA
QIB
31/1/2024 1 change in aeration system Ir Za'aba
DATE REV. DESCRIPTION APP.
Project :

PROPOSED DESIGN, SUPPLY, DELIVERY,


INSTALLATION, TESTING AND
COMMISIONING OF REFURBISHMENT WORKS
AT INDUSTRIAL WASTE WATER TREATMENT
SPC-6 PLANT (IWWTP), COMPLEX A, SULTAN ABDUL
AZIZ SHAH AIRPORT AT PT 51814 (LOT 94332),
SEKSYEN U3, 40150 SHAH ALAM, MUKIM
SUNGAI BULOH, DISTRICT OF PETALING,
SELANGOR DARUL EHSAN.
(“DESIGN & BUILD”)

Project Owner :

ADR 10
IMPECCABLE VINTAGE PROPERTIES SDN BHD
Ground Floor,
Administration Building 2,
Complex A, Sultan Abdul Aziz Shah International Airport
Shah Alam, Selangor Darul Ehsan

Lead Consultant :

BCQS CONSULT SDN. BHD.


No. 9-1, Jalan Dinar D, U3/D,
Taman Subang Perdana,
40150 Shah Alam, Selangor
Darul Ehsan

Quantity Surveyor :

BCQS CONSULT SDN. BHD.


No. 9-1, Jalan Dinar D, U3/D,
Taman Subang Perdana,
40150 Shah Alam, Selangor
Darul Ehsan

Mechanical and Electrical Engineers :

CONSULTING ENGINEERS
Wisma HSS Integrated B1 (1-4) Block B,
Plaza Dwitasik, No. 21 Jalan 5/106,
SAND FILTER ACTIVATED CARBON Bandar Sri Permaisuri,
56000 Kuala Lumpur.
TEL : 03-91730355 FAX : 03-91730939

C & S Consultant :

WAN HUSIN & ASSOCIATES SDN. BHD.


No. 2-6-1, 6th Floor,
Diamond Square, Jalan 3/50,
Off Jalan Gombak,
53000 Kuala Lumpur,
W.P. Kuala Lumpur.

Architect :

36-3, Medan Setia Dua, Plaza Damansara, Bukit Damansara, 50490 Kuala Lumpur
Tel : 603 - 20943177 Fax : 603 - 20937306
Email : linea@linea.com.my

Contractor :

ALIRAN UTILITIES SDN. BHD.


Level 1, Tower Block,
Syed Kechk Foundation Building,
Jalan Kapas, Bangsar,
59100 Kuala Lumpur

Drawing Title :

Designed by: Fiona Drawn By: Ashraf


Checked by: zahin Scale: as shown
Approved by: IR Za'aba Date: 31/12/2023
Drawing No:
CONSTRUCTION DRAWING Rev:
1

You might also like