3 m (min)

Work site
50 − 75 mm, or Minimu Flow control berm incorporated
m leng into the rock pad if the pad
100 − 150 mm th 15 m
(min) receives runoff from the soil
crushed rock 300 mm (min)

15 m (min)
disturbance (location may vary) Land slope
200 mm (min)

Width 3.0 m (min) da


ry Kerb
n
ou
yb
p er t Footpath Make safe for
Up-slope runoff directed Pro Footpath pedestrian traffic
to an appropriate Roadway
sediment trap
Make safe for ROADWAY
Geotextile filter cloth (mandatory
when working on clayey soils) pedestrian traffic

(a) Rock entry/exit pad for construction sites (b) Rock pad sloping away from road
(refer to Standard Drawing Exit-03 for building sites)
3 m (min)
4 m (min) Work site

Typically 190 mm spacing


75 mm (min) rock
between 100 x 100 mm angle Land slope
placed over the

15 m (min)
Note; alternative locating systems vibration grid

Sediment fence

Sediment Sediment Make safe for


storage chamber storage chamber Footpath
pedestrian traffic

ROADWAY
Typically 750 x 450 RCBC
Catchments & Creeks Pty Ltd

Earth or rock ramp


(d) Rock pad sloping towards the road
(c) Alternative low maintenance arrangement Drawn: Date:

(still under development) Construction Exit - Rock Pad


GMW Apr-10 (construction sites only) Exit-01