You are on page 1of 1

MATERIALS OF THE FIBRE ROLL AT ITS LOWEST 3.

THE BIODEGRADABLE CONTENT OF


POINT IS LOWER THAN THE GROUND THE STRAW ROLLS MAY NOT
FIBRE ROLLS: TYPICALLY 200 TO 250mm LEVEL AT EITHER END OF THE ROLL. NECESSARILY NEED TO BE REMOVED
JUTE, COIR OR STRAW ROLL TIED WITH FROM THE SITE.
SYNTHETIC OR BIODEGRADABLE MESH. 6. ENSURE THE ANCHORING STAKES ARE
DRIVEN INTO THE END OF EACH ROLL 4. ALL SYNTHETIC (PLASTIC) MESH OR
STAKES: MINIMUM 25 x 25mm TIMBER AND ALONG THE LENGTH OF EACH ROLL OTHER NON READILY BIODEGRADABLE
STAKES. AT A SPACING NOT EXCEEDING 1.2m OR MATERIAL MUST BE REMOVED FROM THE
SIX TIMES THE ROLL DIAMETER, SITE ONCE THE SLOPE OR DRAIN IS
INSTALLATION WHICHEVER IS THE LESSER. A MAXIMUM STABILISED, OR THE ROLLS HAVE
STAKE SPACING OF 0.3m APPLIES WHEN DETERIORATED TO A POINT WHERE THEY
1. REFER TO APPROVED PLANS FOR USED TO FORM CHECK DAMS. ARE NO LONGER PROVIDING THEIR
LOCATION AND INSTALLATION DETAILS. INTENDED DRAINAGE OR SEDIMENT
IF THERE ARE QUESTIONS OR PROBLEMS 7. ADJOINING ROLL MUST BE OVERLAP AT CONTROL FUNCTION.
WITH THE LOCATION, DIMENSIONS OR LEAST 450mm, NOT ABUTTED.
METHOD OF INSTALLATION CONTACT THE
ENGINEER OR RESPONSIBLE ON-SITE MAINTENANCE
OFFICER FOR ASSISTANCE.
1. INSPECT ALL FIBRE ROLLS PRIOR TO
2. WHEN PLACED ACROSS FORECAST RAIN, DAILY DURING
NON-VEGETATED OR NEWLY SEEDED EXTENDED PERIODS OF RAINFALL,
SLOPES, THE ROLLS MUST BE PLACED AFTER SIGNIFICANT RUNOFF
ALONG THE CONTOUR. PRODUCING STORMS OR OTHERWISE AT
WEEKLY INTERVALS.
3. IF PLACED ON OPEN OR LOOSE SOIL,
ENSURE THE FIBRE ROLLS ARE 2. REPAIR OR REPLACE DAMAGED FIBRE
TRENCHED 75 TO 125mm IN SANDY SOILS ROLLS.
AND 50 TO 75mm IN CLAYEY SOILS. Collected sediment
3. REMOVE COLLECTED SEDIMENT AND
4. ENSURE THE OUTER MOST ENDS OF DISPOSE OF IN A SUITABLE MANNER Fibre rolls recessed
THE FIBRE ROLL ARE TURNED UP THE THAT WILL NOT CAUSE AN EROSION OR 50 to 75 mm in clayey soils,
SLOPE TO ALLOW WATER TO POLLUTION HAZARD. or 75 to 125 mm in sandy soils
ADEQUATELY POND UP-SLOPE OF THE
ROLL, AND TO MINIMISE FLOW REMOVAL
BYPASSING.
1. ALL EXCESSIVE SEDIMENT TRAPPED
5. WHEN PLACED ACROSS THE INVERT BY THE ROLLS MUST BE REMOVED FROM
OF MINOR DRAINS, ENSURE THE SOCKS THE DRAIN OR SLOPE IF SUCH SEDIMENT
ARE PLACED SUCH THAT: IS LIKELY TO BE WASHED AWAY BY
EXPECTED FLOWS.
(i) THE CREST OF THE DOWNSTREAM
Catchments & Creeks Pty Ltd

ROLL IS LEVEL WITH THE CHANNEL


2. DISPOSE OF COLLECTED SEDIMENT IN
INVERT AT THE IMMEDIATE UPSTREAM
SOCK (IF ANY);
A SUITABLE MANNER THAT WILL NOT Figure 1 - Typical installation of fibre rolls
CAUSE AN EROSION OR POLLUTION
(ii) EACH ROLL EXTENDS UP THE HAZARD. Drawn: Date:
CHANNEL BANKS SUCH THAT THE CREST
GMW Apr-10 Fibre Rolls FR-01

You might also like