Professional Documents
Culture Documents
CivilMajorProject New
CivilMajorProject New
net/publication/272238590
CITATIONS READS
0 7,458
5 authors, including:
Some of the authors of this publication are also working on these related projects:
Hyperspectral Data Analysis for Base Metal Deposits (Cu, Pb, Zn) around Pur-Banera and Jahazpur area in Central Aravalli Range, Rajasthan View project
All content following this page was uploaded by Ankit Gupta on 14 May 2017.
By
BACHELOR OF ENGINEERING
in
CIVIL ENGINEERING
CONTENTS
INTRODUCTION
SITE DETAILS
STANDARD’S OF WAREHOUSE
The size of warehouse required for an operation is
determined by the maximum quantity, in tonnage and volume, of
supplies to be stored there at any one time. This quantity is
determined by the number of beneficiaries, the lead-time needed to
replenish the warehouse, the type of distribution system and the
frequency of the distributions.
PURPOSE
Our primary aim of Warehouse is to facilitate the
movement of goods from our suppliers to our customers and by
doing so, meet our customer’s demand in a timely and cost-effective
manner. In order to achieve this efficiently we may have to hold
stock, but this is not the main role of our warehouses.
Our basic aim must be to minimize the total cost of the operation
while providing the desired level of service.
TECHNICAL DETAIL
Land area in which warehouse is constructed is
3678.42 m2; in spite built up area of warehouse is 1646.34 m2. Entire
structure predominantly consists of 20 numbers of Stacks each of
Dimension 6.09×9.14 m, One Office with Tool Room and Guard
Room of same dimension as of stack. Capacity of Warehouse is
3000 MT with 150 MT of each stack. Front facing shutter with
dimension of 2.44×3.05m is provided in corner stack. The cantilever
slab of 1.52m is provided through out shutter.
MARKET POTENTIALITY
ASSUMPTIONS
DESIGN OF TRUSS
Spacing of trusses =6 m
Slope of truss =1 in 3
LOADING CALCULATION:
Mass of Trafford asbestos sheet =16.2 kg/m2
Live load for design of Roof truss = (2/3) ×581 = 387.33 N/m2
K1 = 1, K3 = 1
DESIGN OF PURLIN:
Total wind load on purlins WW = 867 A
3808×103 1269×103
𝑓𝑏𝑡 = + = 102.06 N/mm2 < 165 N/mm2
103.9×103 19.4 ×103
DEFLECTION CHECK:
5 6347 × 60003
∂x = × = 11.4 mm
384 2×105 ×779.1×104
5 2115 × 60003
∂y = × = 29.07 mm
384 2×105 ×102.3×104
∂ = √ (11.4)2 + (29.07)2 = 31.22 mm
HENCE OK.
−3346×103 372×103
𝑓𝑏𝑡 = + = 51.59 N/mm2 < 165 N/mm2
103.9×103 19.4 ×103
DEFLECTION CHECK:
5 5576 × 60003
∂x = × = 10.06 mm
384 2×105 ×779.1×104
5 620 × 60003
∂y = × = 8.52 mm
384 2×105 ×102.3×104
∂ = √ (10.06)2 + (8.52)2 = 13.18 mm
HENCE OK.
LOADS ON SLABS
(As per limit state method a factored load is considered after
calculating total load)
Live Loads
Calculate ly/lx
DESIGN OF REINFORCMENT-
To calculate the area the area of steel by following formula:
𝐴𝑠𝑡 𝑓𝑦
𝑀𝑢 = 0.87 𝑓𝑦 𝐴𝑠𝑡 𝑑 [1 − ]
𝑏𝑑 𝑓𝑐𝑘
SPACING OF BARS = area of one bar x 1000/Ast
Maximum spacing for main reinforcement
DESIGN CALCULATION:-
Location Mu d Ast req Dia Spacing Ast provided
KN-m mm mm2 Mm Mm mm2
Short Span
Support 118.2 175 2785 12 40 2826
Mid Span 88.38 175 1766 12 60 1884
Long Span
Support 72.37 175 1364 12 80 1413
Mid Span 53.89 175 960.9 12 110 1027
τc = 0.73
If τv < τc than no shear reinforcement is required.
DESIGN CALCULATION:-
Location Mu d Ast req Dia Spacing Ast provided
KN-m mm mm2 Mm Mm mm2
Short Span
Support 21.63 80 997 10 70 1121
Mid Span 16.17 80 673 10 110 713
Long Span
Support 13.24 80 528 8 90 558
Mid Span 9.86 80 376.86 8 130 386.46
τc = 0.524
If τv < τc than no shear reinforcement is required.
DESIGN OF BEAMS
1. Plinth Beam of all Sides (B1):
Given:
= 2.44 m
Wu = 1.5 × 16.52
= 24.78 KN/m
24.78×6.32
= =122.93 KN m
8
xu lim = 0.48d
= 55.97 KN m
Ast 1 = 746.622 mm 2
To find Ast 2
124.8−40
𝐸𝑠𝑐 = ( ) = 2.37 × 10-3 mm2
124.8
Vu = 78.05 KN = 7805.5 N
𝑉𝑢 7805.5
𝜏= = 300×260 = 1.01 N/mm2
𝑏𝑑
Ast 1256
𝑃𝑡 = × 100 = × 100 = 1.61 %
𝑏𝑑 300×260
τ = 0.733
From table 20
τ =2.8 N / mm2
τc < τv < τc max
Shear reinforcement will be provided
Vus = Vu - τc bd
Sv = 415.7 mm
3.375×6.302
𝑀𝑢 = = 16.74 KN m
8
Mu lim > Mu
𝐴𝑠𝑡 𝑓𝑦
𝑀𝑢 = 0.87 × 𝑓𝑦 × 𝐴𝑠𝑡 × 𝑑 (1 − )
𝑏𝑑 𝑓𝑐𝑘
𝐴𝑠𝑡 415
16.74 × 106 = 0.87 × 415 × Ast × 260 × (1 − × )
300×260 20
τc = 0.384 N/mm2
15.09×5.942
Mu = = 66.55 KN m
8
Mu lim = 0.138 fck bd2 = 0.138 × 20 × 300 × 2602 = 55.97 × 106 KN-m
Mu > Mu lim
Calculation of Ast 2
Vu = 44.81 KN = 44810 N
𝑉𝑢 44810
τv = 𝑏𝑑 = 300×260 = 0.57 N/mm2
Ast 1004.8
Pt = × 100= × 100 = 1.28 %
𝑏𝑑 300×260
τc = 0.68 N / mm2
τc max =2.8 N / mm2
τc > τv
No shear reinforcement required.
= 16.75 m2
29.4×6.32
= =145.86 KN m
8
xu lim = 0.48d
Ast 1 = 746.622 mm 2
To find Ast 2
124.8−40
𝐸𝑠𝑐 = ( ) = 2.37 × 10-3 mm2
124.8
Vu = 92.61 KN = 92610 N
𝑉𝑢 92610
𝜏= = 300×260 = 1.18 N/mm2
𝑏𝑑
Ast 1885
𝑃𝑡 = × 100 = × 100 = 2.41 %
𝑏𝑑 300×260
τc = 0.82
From table 20
Vus = Vu - τc bd
Sv = 329 mm
44.75×5.942
𝑀𝑢 = = 197.36 KN m
8
Vu = 132.9 KN = 132900 N
𝑉𝑢
τv = =
132900
= 1.70 N/mm2
𝑏𝑑 300×260
Ast 2943.75
Pt = × 100 = × 100 = 3.77 %
𝑏𝑑 300×260
15.81×3.32
𝑀𝑢 = = 21.52 KN m
8
Mu lim > Mu
𝐴𝑠𝑡 𝑓𝑦
𝑀𝑢 = 0.87 × 𝑓𝑦 × 𝐴𝑠𝑡 × 𝑑 (1 − )
𝑏𝑑 𝑓𝑐𝑘
𝐴𝑠𝑡 415
21.52 × 106 = 0.87 × 415 × Ast × 260 × (1 − × )
300×260 20
Spacing of Column = 6m
P = 322.798 KN
𝑃 𝑃
484197 = 0.4 × 20 × 𝐴𝑔 (1 − ) + 0.67 × 415 × × 𝐴𝑔
100 100
243045 P = 235803
P = 0.97%
Pu = 484.197 KN
1.5 × 484.197
𝑞𝑢 = = 181.57 𝐾𝑁/𝑚2
2×2
= qu × B [{(B-b)/2} - d]
Vu = 362 × (850 - d)
τc = 0.32 N/mm2
Minimum depth required:
d = 307 mm ~ 310 mm
Mu = qu (B – b)2/8 × B
= 0.181(2000-300)2/8 × 2000
= 4 × (300+310) = 2440 mm
= 2440 × 310
= 0.556 N/mm2
Max. Shear stress permitted = 0.25√fck = 0.25√20 = 1.118 N /mm2
Ast fy
Mu = 0.87 × fy × Ast × d [1 − ]
bd fck
A 415
130.722 × 106 = 0.87 × 415 × Ast × 310 [1 − (2000×310
st
)
]
20
Using 12 mm bars.
𝜋⁄ ×122 ×2000
4
𝑆𝑝𝑎𝑐𝑖𝑛𝑔 = = 185.7 mm
1217
Spacing of Column = 6m
P = 424.528 KN
243045 P = 83210
P = 1.2%
Pu = 636.79 KN
1.5 × 636.79
𝑞𝑢 = = 197.35 𝐾𝑁/𝑚2
2.20 × 2.20
= qu × B [{(B-b)/2} - d]
VU = 433.4 × (950 - d)
d = 362 mm ~ 370 mm
Mu = qu (B – b)2 /8 × B
= 0.197×(2000-300)2/8 × 2200
= 4 × (300+370) = 2680 mm
= 2680 × 370
= 0.93 N/mm2
Max. Shear stress permitted = 0.25√fck = 0.25√20 = 1.118 N /mm2
Ast fy
Mu = 0.87 × fy × Ast × d [1 − ]
bd fck
A 415
195.57 × 106 = 0.87 × 415 × Ast × 370 [1 − (2200×370
st
)
]
20
Using 12 mm bars.
𝜋⁄ ×122 ×2200
4
𝑆𝑝𝑎𝑐𝑖𝑛𝑔 = = 163 mm
1521
Spacing of Column = 6m
= 34.40 KN
P = 285.198 KN
243045 P = 292210
P = 0.90%
Pu = 427.79 KN
1.5 × 427.79
𝑞𝑢 = = 198.05 𝐾𝑁/𝑚2
1.8 × 1.8
= qu × B [{(B-b)/2} - d]
Vu = 356.4 × (750 - d)
d = 287 mm ~ 300 mm
Mu = qu (B – b)2 /8 × B
= 0.198(1800-300)2/8 × 1800
= 4 × (300+300) = 2400 mm
= 2400 × 300
= 0.86 N/mm2
Max. Shear stress permitted = 0.25√fck = 0.25√20 = 1.118 N /mm2
Ast fy
Mu = 0.87 × fy × Ast × d [1 − ]
bd fck
A 415
100.23 × 106 = 0.87 × 415 × Ast × 310 [1 − (2000×310
st
)
]
20
Using 12 mm bars.
𝜋⁄ ×122 ×1800
4
𝑆𝑝𝑎𝑐𝑖𝑛𝑔 = = 211.95 mm
960
= 23.80 KN
= 5.625 KN
= 4.03 KN
Pu = 50.18 KN
Ag = 75000 mm4
P = 0.37 %
Ag = 49431mm2
P = 50.18 KN
L=B=0.74m
1.5 × 55.98
𝑞𝑢 = = 129.37 𝐾𝑁/𝑚2
0.8 × 0.8
Let Critical Section is at distance ‘d’ from face of Column
VU = 103.49 × (250 - d)
d = 72 mm ~ 80 mm
Mu = qu (B – b)2 /8 × B
Ast fy
Mu = 0.87 × fy × Ast × d [1 − ]
bd fck
A 415
6.687 × 106 = 0.87 × 415 × Ast × 80 [1 − (800×80
st
)
]
20
𝜋⁄ ×102 ×800
4
𝑆𝑝𝑎𝑐𝑖𝑛𝑔 = = 249 mm ~ 220 mm
251.7
=19.5 × 1 × 0.30
=5.85 KN/m
=1.5 KN/m
= 15.42 KN/m
= (15.42 × 10)/100
= 1.542 KN/m
= 16.96/100
= 0.1696 m
𝑤 1−sin ∅
Depth of foundation = ×(1+sin ∅) 2
𝑎×𝜌
16.96 1−sin 30
= .1696×16 × (1+sin 30)2
= 6.25 × 0.1111
= 0.695 m
So we assume,
3𝑞
D = 𝛼 × √𝑀
15 3×16.96
= 100 × √160×0.75×0.80
ESTIMATION
Quantity
S. Particular of items Length Breadth Height (in cu.
no. & details of works No. (in m) (in m) (in m) m) Explanatory notes
Earthwork in
excavation in
1 foundation:
L = 31.66 m because
30 cm walls of stack 20 31.66 0.8 0.75 379.92 No. of junction = 0
For longer span
column footing (C1) 16 2 2 2.5 160
For shorter span
column footing (C2) 8 2.2 2.2 2.5 96.8
For end column
footing (C3) 4 1.8 1.8 2.5 32.4
30 cm wall of office 1 31.66 0.8 0.75 18.996
30 cm walls of outer L = 182.12 m because
slab 1 182.12 0.8 0.75 109.272 No. of junction = 0
For columns of
boundary walls 40 0.8 0.8 0.8 20.48
Total 817.86
Brick work in
Warehouse wall:
L = 54.86 - 3.04 (10-
Longer span 2 51.82 0.3 4.88 154.26 column of size 0.3×0.3)
Ht = 5.49 - 0.61 (2-
Beams)
Deduction:
Shutter in one span
both sides 14 2.44 0.3 2.44 25.405
Ventilation in both
sides 12 0.61 0.3 0.61 1.36
Windows in both span 12 0.61 0.3 0.61 1.36
Deduction:
Doors 4 0.96 0.3 2.13 2.49
Shutter 1 2.44 0.3 2.44 1.82
Window 1 0.914 0.3 0.914 0.26
Total P.C.C. in
warehouse 124.08
Calculation of cement
concrete in wall
4 footing
Calculation of R.C.C.
5 in whole structure
R.C.C. in footing of
boundary columns 40 0.9 0.9 0.2 6.48
R.C.C. in footing of
warehouse columns:
Footing of C1 16 2 2 0.31 19.84
Footing of C2 8 2.2 2.2 0.37 14.32
Footing of C3 4 1.8 1.8 0.3 3.89
R.C.C. in columns of
warehouse:
Column C1 16 0.3 0.3 7.67 11.044
Column C2 8 0.3 0.3 7.61 5.479
Column C3 4 0.3 0.3 7.68 2.764
R.C.C. in beams:
Beam 1 (for longer
span) 18 6 0.3 0.3 9.72 9 - beams in one side
Beam 1 (for shorter
span) 10 5.94 0.3 0.3 5.35 5 - beams in one side
6 REINFORCEMENT
19.041
In beam 1 15.066 1.61% 78.5 Qt. 1.61% of total volume 1
19.041
In beam 2 15.066 1.61% 78.5 Qt. 1.61% of total volume 2
In beam 3 9.72 0.30% 78.5 2.289 Qt. 0.30% of total volume 3
In beam 4 2.031 1.21% 78.5 1.921 Qt. 1.2% of total volume 4
In beam 5 2.031 2.41% 78.5 3.842 Qt. 2.41% of total volume 5
In beam 6 1.069 3.77% 78.5 3.163 Qt. 3.77% of total volume 6
In beam 7 20.422 0.38% 78.5 6.091 Qt. 0.38% of total volume 7
55.388
Total Qt. Or 5538.8≈5539 Kg.
7 PLASTERING
898.73
Boundary wall 485.8 1.85 Sq.m. (74.67×4)+(51.30×2)+(42.26×2)=485.8
Ware house 1860.13
wall 339.44 5.48 Sq.m. (54.86×4)+(30×4)=339.44
Deduction
Total area of 89.23
shutter 15 2.43 2.43 Sq.m.
Total area of 4.46
window w1 12 0.6 0.6 Sq.m.
Total area of 4.46
ventilation 12 0.6 0.6 Sq.m.
Total area of 10.08
door 4 1.2 2.1 Sq.m.
Total area of 0.83
window w2 0.91 0.91 Sq.m.
109.06
Total deduction Sq.m.
Area of gable 300
wall Sq.m. 2×(1/2×15×5)×4
Total area of
plastering in 300
ware house wall Sq.m.
Outer wall of
ware house
112.76
Long wall 2 56.38 m 56.38×2
Short wall of
back side 33.02 33.02 m
Short wall of
front side 3.04 m
Total length of 148.82
wall m 112.76+33.02+3.04
Total area of 148.82
wall 148.82 1 Sq.m.
Plastering in office
337.01
Total plaster Sq.m. 3.66×92.08
Deduction
10.08
Door 4 1.2 2.1 Sq.m. (1.2×2.1)×4
0.82
Window 1 0.91 0.91 Sq.m. (0.91×0.91) × 1
0.405
Ventilator 2 0.45 0.45 Sq.m. (0.45×0.45) × 2
325.69
Net plaster Sq.m. 337-10.08-0.82
8 MURRUM FILLING
In stacks 20 9.2 6.1 1
1116.30
Total volume Cu.m. (9.15×6.1×1) × 20
132.76
in outer slab 2 54.86 1.21 1 Cu.m. (54.86×1×1.21) × 2
39.954
Shorter span 33.02 1.21 1 Cu.m. 33.02×1.21×1
1289.06
Total Murrum Filling Cu.m. 40+132.76+1116.30
9 FINE AGGREGATE
Thickness 0.5
Longer span 2 74.67 9.15 0.05
68.32
Total volume Cu.m. (74.67×9.15×0.05) × 2
27.45
Shorter span 2 30 9.15 0.05 Cu.m. (309×150×0.05) × 2
95.77
Total fine aggregate Cu.m. 68.32+27.45
CALCULATION OF
10 TRUSS
14400 115200
Total Wt. Of Truss 8 Kg. Kg Or 1152 Qt.
CALCULATION OF
11 ROOF SHEETS
FINAL COST
Item
No. Description Or Particulars Quantity Unit Rate Amount
Excavation in all type of soil up to required
depth for column, footing including
1 throwing off the soil 817.86 Cu.m. 181 ₹ 148,031
8 Providing Murrum filling below Stacks Slab 1290 Cu.m. 600 ₹ 774,000
Total :- ₹ 15,374,312
CONCLUSION
All the slabs are designed as two way Slabs, by the method
provided by IS 456: 2000.
REFERENCES