You are on page 1of 73

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/272238590

Planning, Design and Estimation of a Warehouse

Technical Report · April 2013


DOI: 10.13140/RG.2.1.2703.4407/1

CITATIONS READS
0 7,458

5 authors, including:

Ankit Gupta Archit Jain


National Remote Sensing Centre Symbiosis Institute of Business Management
14 PUBLICATIONS 93 CITATIONS 7 PUBLICATIONS 0 CITATIONS

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Hyperspectral Data Analysis for Base Metal Deposits (Cu, Pb, Zn) around Pur-Banera and Jahazpur area in Central Aravalli Range, Rajasthan View project

National Hydrology Project View project

All content following this page was uploaded by Ankit Gupta on 14 May 2017.

The user has requested enhancement of the downloaded file.


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 1

PLANNING, DESIGN AND ESTIMATION OF A


WAREHOUSE
(A study to propose a Warehouse in Indore, M.P. under
“Warehousing Development and Regulatory Authority”)

By

ANKIT GUPTA | ARCHIT JAIN | ANUP JAIN


CHANDAN PATEL | PRABHAKAR NARWANKAR

BACHELOR OF ENGINEERING
in
CIVIL ENGINEERING

DEPARTMENT OF CIVIL ENGINEERING


SRI AUROBINDO INSTITUTE OF TECHNOLOGY, INDORE
APRIL 2013

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 2

CONTENTS

S. No. Title Page No.


1. Introduction 3
2. Planning with Technical Details 7
3. Design of Truss 12
4. Design of Slab 19
5. Design of Beam 24
6. Design of Column & Footing 38
7. Design of Step Footing of Stack 58
8. Estimation 60
9. Final Cost 69
10. Conclusion 71
11. References 72

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 3

INTRODUCTION

This plan proposes to provide Warehouse facility for


agriculture crop and agriculture products at Village Sanwer, Distt.
Indore, M.P.

The proposed unit envisages providing facility in the


field of safe storage of agriculture crop by making standard
warehouse with all type of required safety measures at Village
Sanwer, Distt. Indore (M.P.). Demand of warehousing facility at such
place is very high due to huge production of agriculture.

The unit will get registered with M.P. Warehousing


Corp. further the Indore district has been declared, as an industrial
backward district by the Central Govt. Therefore the unit will receive
all sorts of facilities as applicable to a district of such a category.

SITE DETAILS

1. Location : Village Sanwer, Distt. Indore, M.P.


2. Power : Available through M.P.E.B.
3. Water : Available from Well / Tube well.
4. Transport Facility : By Road- Indore-Ujjain Highway.
5. Medical Facility : Available.
6. Post Office : Available.
7. Bank Facility : Available.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 4

STANDARD’S OF WAREHOUSE
The size of warehouse required for an operation is
determined by the maximum quantity, in tonnage and volume, of
supplies to be stored there at any one time. This quantity is
determined by the number of beneficiaries, the lead-time needed to
replenish the warehouse, the type of distribution system and the
frequency of the distributions.

When calculating storage requirements, only 70 per


cent of the total warehouse’s surface capacity should be considered
as available for actual storage space. The remaining 30 per cent is
used to ensure proper ventilation, passageways, handling space and
repackaging areas.

Moreover, it should be noted that it is either


impossible or impractical to fill a warehouse to the roof, nor is it
recommended. Therefore, storage capacity should be calculated at
least a meter below the actual height of the warehouse ceiling.

FOR 150 TONNES OF GRAIN WITH HEIGHT OF 15 BAGS


REQUIRED SURFACE AREA = 55.66 M2
0.5 TONNE OF GRAINS= 1 M3

LENGTH × BREADTH × (HEIGHT - 1M) × 70% = APPROX CAPACITY OF


WAREHOUSE
NOTE: STACK SHOULD BE ATLEAST 1 M FROM THE CEILING

(1)ONLY 70% OF SPACE IS USED FOR STORAGE OF GRAINS


(2)THERE ARE HEIGHT, LOAD AND FLOOR LIMITATION TO HOW GRAIN CAN BE
STACKED.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 5

REQUIREMENT OF WARE HOUSE

In view of the shortage of storage capacity


experienced by FCI and State Agencies in the last 3 years,
Government of India introduced a Scheme on 28.7.2008 for hiring of
Godowns for a period of 5/7/10 years. These instructions were
conveyed vide letter no. E.3 (28)/Construction of
Godown/07/Stg.VI/Vol. II dated 13.08.2008 and subsequent letters.

On 1.3.2012, the Central Pool stock reached all time


high of 199.52 lakh tonnes of wheat and 333.50 lakh tonnes of rice
(including unmilled paddy). This is the highest ever level of stock.
On 1.3.2012, wheat stock lying with FCI & State Agencies in CAP was
98.88 lakh tonnes, out of which 52.72 lakh tonnes was in Punjab,
36.75 lakh tonnes in Haryana and 0.21 lakh tonnes in M.P.

In 2012-13, Food Secretaries have given an estimate


of 318 lakh tonnes of wheat procurement. The present projections
show that the Central Pool stock may reach all time high level of
750.17 lakh tonnes on 1.6.2012. FCI and State Agencies were having
438 lakh tonnes covered capacity as on 31.03.2011. Moreover, the
allocation made by the Govt of India is 526.455 lakh tonnes in 2012-
13 (as on 10.4.2012) as against 707.88 lakh tonnes in 2011-12.

If CWC & SWCs are not able to give the capacity


required by FCI, GMs(R) of FCI may invite bids from private parties
for hiring of godowns with preservation, maintenance and security
for a period of one year extendable by another one year at the same
rates, terms and conditions at the sole discretion of FCI. The
godown can be vacated by FCI at any time by giving three months’
notice during the extended period only.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 6

PURPOSE
Our primary aim of Warehouse is to facilitate the
movement of goods from our suppliers to our customers and by
doing so, meet our customer’s demand in a timely and cost-effective
manner. In order to achieve this efficiently we may have to hold
stock, but this is not the main role of our warehouses.

Our basic aim must be to minimize the total cost of the operation
while providing the desired level of service.

Some valid reasons for holding stock include the following:

To cover demand during supplier’s lead-time.

To enable savings to be made through bulk purchases or discounts.

To cope with seasonal fluctuations.

To provide a variety of product in a centralized location.

The build up/holding of anticipation stocks.

The build-up and holding of investment stocks.

In addition we may also use warehouses to


break bulk stocks down into smaller orders, to transfer goods, to
consolidate and complete order activities for our various dependent
locations. We should view a warehouse as a place to transfer goods
to customers. This may involve some temporary storage but,
essentially, it is a place where we undertake customer order
completion, combining individual items from various locations and
possibly splitting bulk products.

Large amount of grains every year spoils due


to bad storage condition in order to overcome from the scarcity of
storage we planned, design and estimated warehouse along with full
description. Warehouse is planned to store of grains safely.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 7

TECHNICAL DETAIL
Land area in which warehouse is constructed is
3678.42 m2; in spite built up area of warehouse is 1646.34 m2. Entire
structure predominantly consists of 20 numbers of Stacks each of
Dimension 6.09×9.14 m, One Office with Tool Room and Guard
Room of same dimension as of stack. Capacity of Warehouse is
3000 MT with 150 MT of each stack. Front facing shutter with
dimension of 2.44×3.05m is provided in corner stack. The cantilever
slab of 1.52m is provided through out shutter.

Isolated foundation is provided below each column


and step footing is provided below each stack. Depth of footing is
1.5 m below the G.L. and base slab is provided 1m above G.L. The
height of column is 5.48 m above G.L., each of dimensions 0.3×0.3
m. The spacing of column is 6 m c/c from longer side and 5.94 m
c/c from shorter side.

Plinth beam is provided parallel to the base slab, 1m


above the G.L. The other 2 beams are provided at the ht. of 2.74 m
and 5.48 m above G.L. respectively. Dimension of beam is 0.3×0.3 m.
The thickness of wall is 0.3 m. Space is provided in front of stacks
of 9.14 m, with front space of 6.09 m. The thickness of base slab is
0.3 m.

Span of truss is 30 m with 5 m ht. Minimum 1 m of


space is provided from the bottom of truss.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 8

MARKET POTENTIALITY

Indian economy is solely based on agriculture; in India


agriculture is main source of livelihood for around 61% of the
population in India. So agriculture and agricultural growth occupies
a high degree of importance in the development of country.

Our storage techniques have been turning from


conventional subsistence storage to safe warehousing, so this leads
to the increase of demand for standard storeroom.

Village Sanwer and its adjoining areas are well known


for its agriculture products viz. Soya been, Gram, Alsi and other
crop. The economy of this area is directly depending upon
agriculture products. Thus the area itself has lot of potential for
warehousing. Looking at the present trend of agriculture growth in
country there is huge existing demand of warehousing.

The warehousing facilities have continued demand all


over the year because there is wide variety of agriculture crop and
agriculture products. Thus the unit must have demand for the
whole period of year.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 9

ASSUMPTIONS

The cost of storing and profitability of the project for


its first five operating years is calculated which is presented later
on.

The various assumptions made for the calculation of


cost of production and profitability is listed below:

1. The unit will work for all 365 days.


2. The capacity utilization has been assumed at 80% in the first
year, 85% in the Second year, 90% in the third year and 95% in
the fourth year onwards.
3. The rent rate is considered without labor charges basis, based
on prevailing market rate.
4. The details of manpower and wages are on the basis of
industry practice.
5. Employee’s benefits have been taken at 10% of wages and
salaries, which include benefits, house rent, gratuity, paid leave
etc.
6. In case of Receipts in every third year an increase of 10% has
been assumed.
7. The interest on term loan & working capital has been taken @
11.00% per year.
8. Operational year means year of operation.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 10

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 11

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 12

DESIGN OF TRUSS

Roof of truss span =30 m

Height of column =5.48 m

Spacing of trusses =6 m

Type of truss =A-Type

Rise =5m; Pitch of truss =1/6

Basic wind pressure =86.7 kg/m2

Slope of truss =1 in 3

Length of top chord =√ (5)2+ (15)2 =15.81 m

Divide the length of span in 11 equal panels

Length of each panel =15.81/11 =1.43 m

Let us provide 12 purlins at spacing of 1431 mm, 1431×11=15730


and a gap of 60 mm at apex.

LOADING CALCULATION:
Mass of Trafford asbestos sheet =16.2 kg/m2

Weight of A.C sheet =16.2×9.81 =159 N/m2

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 13

Weight of sheet/meter length of purlin = 159×1.431 =227 N/m

Assume weight of purlin/meter length =100 N/m

Hence, dead load per meter length =227+100 = 327N/m

Total Dead load on purlin =327×6 =1962 N

Live load on purlin = [750-(18.43-10)20]

=581 N/m2 of plane area

Live load for design of Roof truss = (2/3) ×581 = 387.33 N/m2

Total live load on purlin WL =581×1.43 cos18.43°×6 =4729 N

COMPUTATION OF WIND LOAD:


Basic wind speed = 39 m/s

K1 = 1, K3 = 1

K2 = 0.93 [Category 2 and Building of Class C]

VZ = 39×1×1×0.93 = 36.27 m/s

PZ = (36.27)2 × 0.6 = 0.789 KN/m2

Slope 18.43°, h/w = 0.16, Cpe = -0.6, CPI = ±0.5

= (0.6+0.5) × 0.789 = 0.867 KN/m2 = -867 N/m2

DESIGN OF PURLIN:
Total wind load on purlins WW = 867 A

A = Spacing of purlins × Length of purlins = 1.43 × 6 = 8.58 m2

WW = -867 × 8.58 = -7438 N

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 14

The Load Combination is:-


1. D.L. + L.L. = Wd + Wl = 1962 + 4729 = 6691 N

DESIGN OF CHANNEL PURLINS (WITHOUT SAG RODS):

Wdlx = Load perpendicular to slope = 6691 cos18.43° = 6347 N

Wdly = Load parallel to slope = 6691 sin18.43° = 2115 N

Mdlx = (6347 × 6)/10 = 3808 N-m ≈ 3808 × 103 N-mm

Mdly = (2115 × 6)/10 = 1269 N-m ≈ 1269 × 103 N-mm

Assume, Zx/Zy = 6, Zx = ((3808 + (6×1269)) × 103)/165=69.22×103mm3

Let us try ISMC-150 @ 16.09 Kg/m having

Zxx = 103.9 × 103 mm3 Zyy = 19.4 × 103 mm3

Ix = 779.1 × 103 mm4 Iy = 102.3 × 103 mm4

3808×103 1269×103
𝑓𝑏𝑡 = + = 102.06 N/mm2 < 165 N/mm2
103.9×103 19.4 ×103

DEFLECTION CHECK:
5 6347 × 60003
∂x = × = 11.4 mm
384 2×105 ×779.1×104

5 2115 × 60003
∂y = × = 29.07 mm
384 2×105 ×102.3×104
∂ = √ (11.4)2 + (29.07)2 = 31.22 mm

HENCE OK.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 15

2. D.L. + W.L. (Wd = 1962 N, Ww = -7438 N) :


DESIGN OF CHANNEL PURLINS (WITHOUT SAG RODS):

Wdwx = Load normal to slope = -7438 + 1962cos18.43° = - 5576 N

Wdwy = Load parallel to slope = 1962sin18.43° = 620 N

Mdlx = (-5576 × 6)/10 = -3346 N-m ≈ 3346 × 103 N-mm

Mdly = (620 × 6)/10 = 372 N-m ≈ 372 × 103 N-mm

Let us try ISMC-150 @ 16.09 Kg/m having

Zxx = 103.9 × 103 mm3 Zyy = 19.4 × 103 mm3

Ix = 779.1 × 103 mm4 Iy = 102.3 × 103 mm4

−3346×103 372×103
𝑓𝑏𝑡 = + = 51.59 N/mm2 < 165 N/mm2
103.9×103 19.4 ×103

DEFLECTION CHECK:
5 5576 × 60003
∂x = × = 10.06 mm
384 2×105 ×779.1×104

5 620 × 60003
∂y = × = 8.52 mm
384 2×105 ×102.3×104
∂ = √ (10.06)2 + (8.52)2 = 13.18 mm

HENCE OK.

LOAD AT PANEL POINTS OF TRUSS:


There are 22 panels of 1.43 m Length each.

a.) DEAD LOADS

Weight of asbestos sheet/panel length = 159 × 1.43 × 6 = 1364 N

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 16

Weight of 24 purlins directly on truss. Hence load due to weight of


purlin/panel = (24×6×127×9.81)/8 = 2242 N

Weight of truss, W = 10((L/3) +5) = 10((30/3) +5) = 150 N/m2

Total dead weight/panel = 1364 + 2242 + 3375 = 6980 N

Deal Load at each end panel point = ½*6980 = 3490 N

b.) IMPOSED LOAD

Live Load on truss = 2/3×581 = 387.33 N/m2 of horizontal area.

Live Load per panel = 387.33 × 6 × 1.43 × cos18.43° = 3152 N

c.) WIND LOAD

Max. Wind pressure = -867 N/m2 (Wind blows parallel to Rige)

Wind Load per panel = -867 × 6 × 1.43 = -7438 N (Uplift Load)

IN TABLE DRAWN BELOW:

2 In bracket indicates force due to wind load combination


1 In bracket indicates force from combination other than wind load
25 Percent reduction is applied to force from wind load combination
Left Reaction Right Reaction
Horizontal Vertical Horizontal Vertical
Dead Load 0.0 4164.7 0.0 4164.7
Reaction
Live Load 0.0 3504.1 0.0 3504.1
Reaction
Wind Load 79.6 -7200.0 79.6 -7200.0
Reaction

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 17

STEEL ROOF TRUSS (ANALYSIS RESULT)

Span = 3000 cm Spacing = 600 cm Slope = 1 in 3


Wind force = 100 kg/m2 Panels = 11 Purling at 143.74 cm
Member Length Compression Moment Tension Moment
Cm Kg kg.cm kg kg.cm
1 136.36 (2) 6346.5 2626.1 (1) 21640.2 8966.3
2 272.73 (2) 6343.8 1327.0 (1) 20904.2 4263.8
3 272.73 (2) 5262.1 545.4 (1) 18825.6 1655.9
4 272.73 (2) 4477.7 378.1 (1) 16735.7 1122.0
5 272.73 (2) 3693.0 340.2 (1) 14644.1 983.1
6 272.73 (2) 2521.7 583.0 (1) 11521.4 1532.2
7 143.74 (1) 22833.0 4541.5 (2) 6775.9 5956.8
8 143.74 (1) 22823.9 8712.8 (2) 6922.8 5238.9
9 143.74 (1) 20985.2 8794.3 (2) 6370.2 9836.2
10 143.74 (1) 20969.2 11513.5 (2) 6522.8 11335.2
11 143.74 (1) 18820.8 10994.3 (2) 5873.9 13045.1
12 143.74 (1) 18826.5 11756.7 (2) 6034.0 13259.7
13 143.74 (1) 16655.5 11186.8 (2) 5377.8 12692.6
14 143.74 (1) 16665.0 10037.4 (2) 5539.2 11929.6
15 143.74 (1) 14490.2 9521.2 (2) 4881.7 8885.0
16 143.74 (1) 14719.7 8353.3 (2) 5125.6 5786.7
17 143.74 (1) 14705.3 6195.1 (2) 5278.0 6106.1
18 45.45 (1) 592.7 773.0 (2) 225.9 415.0
19 136.36 (1) 668.2 2452.3 (2) 250.6 891.2
20 227.27 (1) 679.7 1093.1 (2) 254.2 395.5
21 318.18 (1) 676.1 438.0 (2) 252.8 161.1
22 409.09 (1) 998.6 179.5 (2) 373.7 69.0
23 204.55 (1) 604.8 576.2 (2) 226.3 228.9
24 500.00 (2) 4.0 0.0 (1) 10.3 0.0
25 163.89 (1) 1235.1 1640.6 (2) 465.8 541.4
26 227.27 (1) 1737.8 887.0 (2) 652.9 320.3
27 304.92 (1) 2343.1 627.5 (2) 879.5 233.8
28 388.36 (1) 2979.9 358.2 (2) 1118.3 142.3
29 209.54 (2) 107.3 518.4 (1) 287.2 1358.5
30 163.89 (2) 357.7 1208.6 (1) 900.0 3929.5
31 227.27 (2) 634.5 357.8 (1) 1689.4 1110.0
32 304.92 (2) 867.1 112.4 (1) 2311.8 310.8
33 388.36 (2) 1109.4 18.8 (1) 2958.4 71.0
34 284.77 (2) 1617.8 625.4 (1) 4314.9 1663.9
35 284.77 (2) 1780.5 628.6 (1) 4749.7 1593.5

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 18

STEEL A-TYPE ROOF TRUSSES (ISA SECTIONS)


Span = 30 m Slope = 1 in Purling at 1.44 m
Wind force = 100 kg/m2 150 kg/m2 200 kg/m2

Members No Length SPACING (m) SPACING (m) SPACING (m)


(m)
4.5 6.0 4.5 6.0 4.5 6.0
TIE 1 1.36 2-7070×6 2-9090×6 2-8080×6 2-9090×6 2-9090×6 2-100100×8
TIE 2 2.73 2-7070×6 2-9090×6 2-8080×6 2-9090×6 2-9090×6 2-100100×8
TIE 3 2.73 2-7070×6 2-9090×6 2-8080×6 2-9090×6 2-9090×6 2-100100×8
TIE 4 2.73 2-7070×6 2-9090×6 2-8080×6 2-9090×6 2-9090×6 2-100100×8
TIE 5 2.73 2-5050×6 2-7070×6 2-7070×6 2-8080×6 2-8080×6 2-9090×6
TIE 6 2.73 2-5050×6 2-7070×6 2-7070×6 2-8080×6 2-8080×6 2-9090×6
RAFTER 7 1.44 2-8080×6 2-100100×6 2-8080×6 2-100100×6 2-9090×6 2-9090×8
RAFTER 8 1.44 2-8080×6 2-100100×6 2-8080×6 2-100100×6 2-9090×6 2-9090×8
RAFTER 9 1.44 2-8080×6 2-100100×6 2-8080×6 2-100100×6 2-9090×6 2-9090×8
RAFTER 10 1.44 2-8080×6 2-100100×6 2-8080×6 2-100100×6 2-9090×6 2-9090×8
RAFTER 11 1.44 2-8080×6 2-100100×6 2-8080×6 2-100100×6 2-9090×6 2-9090×8
RAFTER 12 1.44 2-8080×6 2-100100×6 2-8080×6 2-100100×6 2-9090×6 2-9090×8
RAFTER 13 1.44 2-8080×6 2-100100×6 2-8080×6 2-100100×6 2-9090×6 2-9090×8
RAFTER 14 1.44 2-7070×6 2-9090×6 2-7070×6 2-9090×6 2-8080×6 2-100100×6
RAFTER 15 1.44 2-7070×6 2-9090×6 2-7070×6 2-9090×6 2-8080×6 2-100100×6
RAFTER 16 1.44 2-7070×6 2-9090×6 2-7070×6 2-9090×6 2-8080×6 2-100100×6
RAFTER 17 1.44 2-7070×6 2-9090×6 2-7070×6 2-9090×6 2-8080×6 2-100100×6
WEB 18 0.45 1-4040×6 1-4040×6 1-4040×6 1-4040×6 1-4040×6 1-4040×6
WEB 19 1.36 1-4040×6 1-4040×6 1-4040×6 1-4040×6 1-4040×6 1-4040×6
WEB 20 2.27 1-6060×6 1-6060×6 1-6060×6 1-6060×6 1-6060×6 1-6060×6
WEB 21 3.18 1-8080×6 1-8080×6 1-8080×6 1-8080×6 1-8080×6 1-8080×6
WEB 22 4.09 1-100100×6 1-100100×6 1-100100×6 1-100100×6 1-100100×6 1-100100×6
WEB 23 2.04 1-6060×6 1-6060×6 1-6060×6 1-6060×6 1-6060×6 1-6060×6
WEB 24 5.00 1-9090×6 1-9090×6 1-9090×6 1-9090×6 1-9090×6 1-9090×6
WEB 25 1.64 1-5050×6 1-5050×6 1-5050×6 1-5050×6 1-5050×6 1-5050×6
WEB 26 2.27 1-6060×6 1-6060×6 1-6060×6 1-6060×6 1-6060×6 1-6060×6
WEB 27 3.05 1-8080×6 1-8080×6 1-8080×6 1-8080×6 1-8080×6 1-8080×6
WEB 28 3.88 1-100100×6 1-100100×6 1-100100×6 1-100100×6 1-100100×6 1-100100×6
WEB 29 2.09 1-4040×6 1-4040×6 1-4040×6 1-4040×6 1-4040×6 1-4040×6
WEB 30 1.64 1-4040×6 1-5050×6 1-4040×6 1-5050×6 1-5050×6 1-6060×6
WEB 31 2.27 1-5050×6 1-5050×6 1-5050×6 1-5050×6 1-6060×6 1-6060×6
WEB 32 3.05 1-6060×6 1-6060×6 1-6060×6 1-7070×6 1-7070×6 1-8080×6
WEB 33 3.88 1-7070×6 1-7070×6 1-8080×6 1-9090×6 1-9090×6 1-100100×6
WEB 34 2.85 2-4040×6 2-5050×6 2-6060×6 2-6060×6 2-6060×6 2-7070×6
WEB 35 2.85 2-4040×6 2-5050×6 2-6060×6 2-6060×6 2-6060×6 2-7070×6

Sum of angle of 1363.70 1622.05 1492.29 1662.81 1649.5 1982.14


weight (kg)
Unit weight (kg) 10.10 9.01 11.05 9.24 12.22 11.01

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 19

DESIGN PROCEDURE OF TWO WAY SLABS


As the ratio of length & width of all slabs are less than 2,
two way slabs have been considered to design.

DESIGN CONSTANTS – Following design constants have been


adopted for steel & concrete as per IS 456 – 2000.

Steel – Fe 415 : (char. Strength) fy = 415 N/mm2

Concrete – M 20 (char. Comp. strength) fck = 20 N/mm2

(Max depth of N.A) : Xu max = 0.48 d

(Max limiting moment) : Mu lim = 0.138 fck bd2

(Factor): Ru max = 0.36 fck b Ku max. (1 - 0.42 Ku max) =2.76

Ku max = Xu max /d =0.48

Total Depth of slab D = 200 mm

Depth without Cover d = 175 mm

LOADS ON SLABS
(As per limit state method a factored load is considered after
calculating total load)

Dead load due to self weight of slab

Live Loads

TOTAL LOAD = Total of all loads


Factored load Wd = 1.50 × Total loads

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 20

CALCULATIONS OF BENDING MOMENTS ON SLABS:


While calculating of B.M. of slab is done, ly/lx ratio is first calculated
to obtain the value of αx & αy (where, αx & αy are B.M. coefficient)

(as per IS 456: 2000 Table 26)

Calculate ly/lx

Obtain value of αx & αy (from IS 456: 2000 Table 26)

For corresponding value of ly/lx,

Calculate B.M.: α =αy W

DESIGN OF REINFORCMENT-
To calculate the area the area of steel by following formula:

𝐴𝑠𝑡 𝑓𝑦
𝑀𝑢 = 0.87 𝑓𝑦 𝐴𝑠𝑡 𝑑 [1 − ]
𝑏𝑑 𝑓𝑐𝑘
SPACING OF BARS = area of one bar x 1000/Ast
Maximum spacing for main reinforcement

CHECH FOR SHEAR –


Shear force due to load Vu = Wd l/2
Nominal shear stress τv = Vu/bd
Percentage of tensile steel Pt = Ast × 100/bd %

Shear strength of concrete (table 19 page 73 IS 456: 2000)

If τv < τc than no shear reinforcement is required.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 21

DESIGN OF SLABS ABOVE STACK


Load on the slab:-
Self weight of slab = 0.20×24.2 = 4.84 KN/m2

Imposed load = 26.7 KN/m2

TOTAL LOAD = 31.54 KN/m2


Factored load = 31.54 × 1.5 = 47.31 KN/m2

Ly/Lx = 8.55/5.5 = 1.55 < 2

For Ly/Lx 1.5 1.75 1.55 For all Ly/Lx

-αx 0.075 0.084 0.0768 -αy = 0.047


+αx 0.056 0.063 0.0574 +αy = 0.035
Wu = 47.31 KN/m2 Lx = 5.5 m Wu Lx2 = 1431.12 KN

Span Position B.M Coefficient (α) Mu = α Wu Lx2 KN-m

Short – Support 0.0768 118.2


Short – Mid Span 0.0574 88.38
Long – Support 0.047 72.37
Long – Mid Span 0.035 53.89

DESIGN CALCULATION:-
Location Mu d Ast req Dia Spacing Ast provided
KN-m mm mm2 Mm Mm mm2
Short Span
Support 118.2 175 2785 12 40 2826
Mid Span 88.38 175 1766 12 60 1884

Long Span
Support 72.37 175 1364 12 80 1413
Mid Span 53.89 175 960.9 12 110 1027

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 22

Check for shear –


Shear force due to load Vu = Wd l/2
= (49.99 × 5.5)/2 = 138.7 KN
Nominal shear stress τv = Vu/bd
= (138.7 × 1000)/ (1000 × 175)
= 0.70 N/mm2
𝜋⁄ ×122 ×100
4
Percentage of tensile steel 𝑃𝑡 = = 1.61%
175×40

τc = 0.73
If τv < τc than no shear reinforcement is required.

DESIGN OF SLAB ABOVE OFFICE


Load on the slab:-
Self weight of slab = 0.10×24.2 = 2.42 KN/m2

Lime mortar = 0.07×17 = 1.19 KN/m2

Kota stone floor = 0.025×24 = 0.60 KN/m2

Live load = 2 KN/m2

TOTAL LOAD = 6.21 KN/m2


Factored load = 6.21 × 1.5 = 9.315 KN/m2

Ly/Lx = 8.55/5.5 = 1.55 < 2

For Ly/Lx 1.5 1.75 1.55 For all Ly/Lx

-αx 0.075 0.084 0.0768 -αy = 0.047


+αx 0.056 0.063 0.0574 +αy = 0.035

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 23

Wu = 9.315 KN/m2 Lx = 5.5 m Wu Lx2 = 281.77 KN

Span Position B.M Coefficient (α) Mu = α Wu Lx2 KN-m

Short – Support 0.0768 21.63


Short – Mid Span 0.0574 16.17
Long – Support 0.047 13.24
Long – Mid Span 0.035 9.86

DESIGN CALCULATION:-
Location Mu d Ast req Dia Spacing Ast provided
KN-m mm mm2 Mm Mm mm2
Short Span
Support 21.63 80 997 10 70 1121
Mid Span 16.17 80 673 10 110 713

Long Span
Support 13.24 80 528 8 90 558
Mid Span 9.86 80 376.86 8 130 386.46

Check for shear –


Shear force due to load Vu = Wd l/2
= (9.315 × 5.5)/2 = 25.6 KN
Nominal shear stress τv = Vu/bd
= (25.6 × 1000)/ (1000 × 175)
= 0.146 N/mm2
𝜋⁄ ×102 ×100
4
Percentage of tensile steel 𝑃𝑡 = = 0.64%
175×70

τc = 0.524
If τv < τc than no shear reinforcement is required.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 24

DESIGN OF BEAMS
1. Plinth Beam of all Sides (B1):
Given:

Total depth of beam (D) = 300 mm

Effective depth of beam (d) =260 mm

Width of beam (b) = 300 mm

Effective cover (d’) = 40 mm

Use, M-20 concrete, Fe-415 Steel

Strength of concrete (fck) = 20 N/mm2

Strength of steel (fy) = 415 N/mm2


5.48−.6
Height of wall above beam =
2

= 2.44 m

Weight of wall on beam = Unit weight of brick masonary ×

Height of wall × Thickness of wall

[Unit weight of wall masonary =19.5 KN/m3

Thickness of wall = 0.3m]

Weight of wall on beam = 19.5 × 2.44 × 0.3


= 14.27 KN/m

Self weight of beam = Unit weight of concrete × Width of

Beam × Depth of beam

[Unit weight of concrete = 25 KN/m3]

Self weight of beam = 25 × 0.3 × 0.3 = 2.25 KN/m

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 25

Total load on beam (W) = Weight of wall + Self weight of beam

= 14.27 + 2.25 = 16.52 KN/m

Design load for consideration (Factored load) = 1.5 × W

Wu = 1.5 × 16.52

= 24.78 KN/m

Effective length of span = c/c distance of column

Leff = 6.0 + 0.15 + 0.15 = 6.3 m

Factored moment (Mu) = (Wu leff2)/8

24.78×6.32
= =122.93 KN m
8

“Maximum shear occurs at support & is equals to half of the total


load”

Maximum shear (Vu) = (Wu leff)/2


24.78×6.3
= = 78.05 KN
2

Check whether it can be single reinforced beam

xu lim = 0.48d

= 0.48 × 260 = 124.8

Mu lim = 0.138 fckbd2

= 55.97 KN m

It is designed as doubly reinforced beam; C=T

0.36 fck b xu lim = 0.87 fy Ast 1

0.36 × 20 × 300 × 124.8 = 0.87 × 415 × Ast 1

Ast 1 = 746.622 mm 2

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 26

To find Ast 2

Mu – Mu lim = 0.87 fy (d-d’)

122.93 – 55.97 = 0.87 × 415 × (260-40)

Ast 2 = 842 mm2

Ast = Ast 1 + Ast 2 = 746.662 + 842 = 1588.99 mm2


𝑋𝑢𝑙𝑖𝑚−𝑑′
Steel in compression Esc = 0.0035 ( )
𝑋𝑢𝑙𝑖𝑚

124.8−40
𝐸𝑠𝑐 = ( ) = 2.37 × 10-3 mm2
124.8

From stress strain curve

Fsc = 352 N/mm2

On equating horizontal comp. to tensile force

Fsc Asc = 0.87 fy Ast 2

352 Asc = 0.87 × 415 × 842

Asc = 863 mm2

Provide 6 bars of 20 mm dia. in tension zone (Ast provided = 1885


mm2) & 3 bars of 20 mm dia. In compression zone (Ast provided =
942 mm2)

Vu = 78.05 KN = 7805.5 N
𝑉𝑢 7805.5
𝜏= = 300×260 = 1.01 N/mm2
𝑏𝑑
Ast 1256
𝑃𝑡 = × 100 = × 100 = 1.61 %
𝑏𝑑 300×260

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 27

From table 19 of IS -456

τ = 0.733
From table 20

τ =2.8 N / mm2
τc < τv < τc max
Shear reinforcement will be provided

Shear is to be taken by steel

Vus = Vu - τc bd

= 78055 – 0.733 × 300 × 260 = 20881 N

Using 2 legged 8 mm vertical stirrups


0.87×𝑓𝑦×𝐴𝑠𝑣×𝑑
𝑉𝑢𝑠 = 𝑆𝑣
𝜋
0.87×415×(2× ×82 )×260
4
20881 = 𝑆𝑣

Sv = 415.7 mm

Provide 300 mm spacing.

2. Mid Beam of all Sides (B2):


Design and Percentage of Reinforcement
of Mid Beam of all the sides in the Warehouse is same as Plinth
Beam i.e. 1.61%. Doubly Reinforced Beam is to be provided as same
as Plinth Beam in all the Mid Beams of Warehouse.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 28

3. Top Beam of Longer Side (B3):


Self weight of beam = 25 × 0.3 × 0.3 = 2.25 KN / m

Wu = 1.5 (2.25) = 3.375 KN/m

3.375×6.302
𝑀𝑢 = = 16.74 KN m
8

Maximum shear at support & half of total load


Wu L 1
V𝑢 = = × 3.375 × 6.30 = 10.63 KN
2 2

Check for singly reinforced beam

Mu lim = 0.138 fck bd2 = 0.138 × 20 × 300 × 2602= 55.97 KN-m

Mu lim > Mu
𝐴𝑠𝑡 𝑓𝑦
𝑀𝑢 = 0.87 × 𝑓𝑦 × 𝐴𝑠𝑡 × 𝑑 (1 − )
𝑏𝑑 𝑓𝑐𝑘

𝐴𝑠𝑡 415
16.74 × 106 = 0.87 × 415 × Ast × 260 × (1 − × )
300×260 20

Ast = 187.6 mm2

Provide 3 bars of 10 mm; Ast provided = 235.5 mm2

Check for shear reinforcement


𝑉𝑢 10.63 ×1000
𝜏𝑣 = 𝑏𝑑 = = 0.136 N/mm2
300×260
235.5
𝑃𝑡 = 300×260 = 0.30 %

τc = 0.384 N/mm2

τc max = 2.8 N/mm2


τc > τv Hence no shear reinforcement required.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 29

4. Top First & Fifth Beam of Shorter Side (B4):


Total weight of wall above beam
1
= 19.5 × 0.3 × [ × 5.94 ×1.98] = 44.10 KN
2

Self weight of beam = 25 × 0.3 × 0.3 = 2.25 KN/m

Total load W = 7.81 + 2.25 = 10.06 KN/m

Factored load Wu = 1.5 × (10.06) = 15.09 KN/m

Effective length between c/c of column = 5.94

15.09×5.942
Mu = = 66.55 KN m
8

Shear occurs at mid span and equal to half of total load


Wu L 1
Vu = = × 15.09 × 5.94 = 44.81 KN
2 2

Check for singly reinforced beam

Mu lim = 0.138 fck bd2 = 0.138 × 20 × 300 × 2602 = 55.97 × 106 KN-m

Mu > Mu lim

It is doubly reinforced section

Calculation of Ast 1: C=T

0.36 f ck × b × Xu lim = 0.87 × fy × Ast 1

0.36 × 20 × 300 × 0.48 × 260 = 0.87 × 415 × Ast 1

Ast 1 = 746 mm2

Calculation of Ast 2

Mu – Mu lim = 0.87× fy × Ast 2 (d - d’)

(66.55 – 55.97) × 106 = 0.87 × 415 × Ast 2 (260 - 40)

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 30

Ast 2 = 133.1 mm2

Ast = Ast 1 + Ast 2 = 746 + 133.1 = 879.19 mm2


𝑋𝑢 lim − 𝑑′ 124.8−40
𝐸𝑠𝑐 = 0.0035 ( ) = 0.0035( ) = 2.3 × 10-3
𝑋𝑢 𝑙𝑖𝑚 124.8

Fsc = 352 N / mm2

Equating horizontal compression and tensile force

Fsc Asc = 0.87 × fy × Ast 2

352 × Asc = 0.87 × 415 × 746

Asc = 136.52 mm2

Provide 5 bars of 16 mm dia. in tension zone (Ast provided = 1004.8


mm2) & Provide 2 bars of 10 mm dia. in compression zone (A st
provided = 157 mm2).

Vu = 44.81 KN = 44810 N
𝑉𝑢 44810
τv = 𝑏𝑑 = 300×260 = 0.57 N/mm2

Ast 1004.8
Pt = × 100= × 100 = 1.28 %
𝑏𝑑 300×260

τc = 0.68 N / mm2
τc max =2.8 N / mm2
τc > τv
No shear reinforcement required.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 31

5. Second & Fourth Beam of Shorter Side (B5):

Area of wall above beam = [{(5.64+1.98)/2} + (1.98×5.64)]

= 16.75 m2

Weight of wall on beam = 19.5 × 16.75 × 0.3 = 97.98 KN

Total load of wall per meter = 97.98/5.64 = 17.37 KN/M

Self weight of beam = 25 × 0.3 × 0.3 = 2.25 KN/m

Total load on beam W = 17.37 + 2.25 = 19.62 KN/m

Factored load Wu = 1.5 × 19.62 = 29.4 KN/m

Effective length of span = C/C distance of column

Leff = 6.0 + 0.15 + 0.15 = 6.3 m

Factored moment (Mu) = (Wu leff2)/8

29.4×6.32
= =145.86 KN m
8

“Maximum shear occurs at support & is equals to half of the total


load”

Maximum shear (Vu) = (Wu leff)/2


29.4×6.3
= = 92.61 KN
2

Check whether it can be single reinforced beam

xu lim = 0.48d

= 0.48 × 260 = 124.8

Mu lim = 0.138 fckbd2 = 55.97 KN m

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 32

It is designed as doubly reinforced beam; C=T

0.36 fck b xu lim = 0.87 fy Ast 1

0.36 × 20 × 300 × 124.8 = 0.87 × 415 × Ast 1

Ast 1 = 746.622 mm 2

To find Ast 2

Mu – Mu lim = 0.87 fy (d-d’) Ast2

(145.86 – 55.97)×106 = 0.87 × 415 × (260-40) ×Ast 2

Ast 2 = 1131.6 mm2

Ast = Ast 1= + Ast 2 = 746.662 + 1131.6 = 1878 mm2


𝑋𝑢𝑙𝑖𝑚−𝑑′
Steel in compression Esc = 0.0035 ( )
𝑋𝑢𝑙𝑖𝑚

124.8−40
𝐸𝑠𝑐 = ( ) = 2.37 × 10-3 mm2
124.8

From stress strain curve

Fsc = 352 N/mm2

On equating horizontal comp. to tensile force

Fsc Asc = 0.87 fy Ast 2

352 Asc = 0.87 × 415 × 1131.6

Asc = 1160 mm2

Provide 6 bars of 20 mm dia. in tension zone (Ast provided = 1885


mm2) & 5 bars of 16 mm dia. In compression zone (Ast provided =
1205.76 mm2).

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 33

Vu = 92.61 KN = 92610 N
𝑉𝑢 92610
𝜏= = 300×260 = 1.18 N/mm2
𝑏𝑑
Ast 1885
𝑃𝑡 = × 100 = × 100 = 2.41 %
𝑏𝑑 300×260

From table 19 in IS -456

τc = 0.82
From table 20

τc max =2.8 N / mm2


τc < τv < τc max
Shear reinforcement will be provided

Shear is to be taken by steel

Vus = Vu - τc bd

= 92610 – 0.82 × 300 × 260 = 28650 N

Using 2 legged 8 mm vertical stirrups


0.87×𝑓𝑦×𝐴𝑠𝑣×𝑑
𝑉𝑢𝑠 =
𝑆𝑣
𝜋
0.87×415×(2× ×82 )×260
4
28650 = 𝑆𝑣

Sv = 329 mm

Provide 300 mm spacing.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 34

6. Center Beam of Shorter Side (B6):


1
Weight of wall = 19.5×0.3× [5.94 × 3.96 + ( × 5.94 ×1.04)]
2

= 19.5 × 0.3 × 26.12 = 155.67 KN

Self weight of beam = 25 × 0.3 × 0.3 = 2.25 KN/m

Total load W = 27.6 + 2.25 = 29.85 KN/m

Factored load Wu = 1.5 × (33.04) = 44.75 KN/m

Effective length between c/c of column = 5.94

44.75×5.942
𝑀𝑢 = = 197.36 KN m
8

Shear occurs at mid span and equal to half of total load


Wu L 1
𝑉𝑢 = = 2 × 44.75 × 5.94 = 132.90 KN
2

Check for singly reinforced beam

Mu lim = 0.138 fck bd2 = 0.138 × 20 × 300 × 2602 = 55.97 KN-m

Mu > Mu lim It is doubly reinforced section

Calculation of Ast by (0.36 f ck × b × Xu lim = 0.87 × fy × Ast 1)

Ast 1 = 746.6 mm2

Calculation of Ast 2 by Mu – Mu lim = 0.87× fy × Ast 2 (d - d’)

(197.36 – 55.97) × 106 = 0.87 × 415 × Ast 2 (260 -40)

Ast 2 = 1780 mm2

Ast = Ast 1 + Ast 2 = 1780 + 746 = 2526 mm2


𝑋𝑢 lim − 𝑑′ 124.8−40
𝐸𝑠𝑐 = 0.0035 ( ) = 0.0035( ) = 2.3 × 10-3
𝑋𝑢 𝑙𝑖𝑚 124.8

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 35

Equating horizontal compression and tensile force

Fsc Asc = 0.87 × fy × Ast 2 (Fsc = 352 N/mm2)

Asc =1825 mm2

Provide 6 bars of 25 mm dia. Ast provided= 2943.75 mm2 & Provide 7


bars of 20 mm dia. Ast provided= 2198 mm2.

Vu = 132.9 KN = 132900 N
𝑉𝑢
τv = =
132900
= 1.70 N/mm2
𝑏𝑑 300×260

Ast 2943.75
Pt = × 100 = × 100 = 3.77 %
𝑏𝑑 300×260

τc = 0.82 N/mm2; τc max =2.8 N/mm2


τc < τv < τc max Shear reinforcement will be provided.

Shear is to be taken by steel.

Vus = Vu - τc bd = 132900 – 0.82 × 300 × 260 = 68940 N

Using 2 legged 8 mm vertical stirrups


0.87×𝑓𝑦×𝐴𝑠𝑣×𝑑
𝑉𝑢𝑠 = 𝑆𝑣
𝜋
0.87×415×(2× 4 ×82 )×260
68940 =
𝑆𝑣

Sv = 136.81 mm Provide 300 mm spacing.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 36

7. Plinth Beam of Boundary Wall (B7):


Self weight of wall =19.5 × 0.23 × 1.85 = 8.29 KN/M

Self weight of beam = 25 × 0.3 × 0.3 = 2.25 KN/m

Wu = 1.5 (8.29 + 2.25) = 15.81KN/m

15.81×3.32
𝑀𝑢 = = 21.52 KN m
8

Maximum shear at support & half of total load


Wu L 1
V𝑢 = = × 15.81 × 3.3 = 26.08 KN
2 2

Check for singly reinforced beam

Mu lim = 0.138 fck bd2 = 0.138 × 20 × 300 × 2602 = 55.97 KN-m

Mu lim > Mu
𝐴𝑠𝑡 𝑓𝑦
𝑀𝑢 = 0.87 × 𝑓𝑦 × 𝐴𝑠𝑡 × 𝑑 (1 − )
𝑏𝑑 𝑓𝑐𝑘

𝐴𝑠𝑡 415
21.52 × 106 = 0.87 × 415 × Ast × 260 × (1 − × )
300×260 20

Ast = 245 mm2

Provide 6 bars of 8 mm dia.; Ast provided = 301.44 mm2

Check for shear reinforcement


𝑉𝑢 26.08 ×1000
𝜏𝑣 = 𝑏𝑑 = = 0.33 N/mm2
300×260
Ast 301.44 ×100
𝑃𝑡 = × 100 = = 0.386 %
𝑏𝑑 300×260

τc = 0.422 N/mm2 ; τc max = 2.8 N/mm2


τc > τv No shear reinforcement required.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 37

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 38

LOAD ON COLUMN C1:

Load on each Colum due to truss = 72 KN

Self Wt. of wall = 19.5 × 2.74 × 0.3 = 16.029 KN/m

Self Wt. of Beam = 25 × 0.3 × 0.3 = 2.25 KN/m

Self Wt. of Column = 25 × 0.3 × 0.3 × 7.98 = 17.95 KN

Spacing of Column = 6m

Total Load of Wall on Column = 16.029 × 6 = 96.174 KN

Total Load of Beam on Column = 2.25 × 6 = 13.5 KN

Total Load on Column = 72 + 17.95 + (2×96.174) + (3×13.5)

P = 322.798 KN

Factored Load Pu = 484.197 KN

Using M-20 and Fe-415


Height of Column above G.L = 5.48 m

Both end are fixed, it implies

Leff = 5.48 × 0.65 = 3.562 m = 3562 mm


𝐿𝑒𝑓𝑓 3562
= = 11.82
𝑏 300
(It is designed as Axially Loaded Short Column)

Size of Column = (300 × 300) mm = 90000 mm2

Using “P” Percentage Reinforced

Pu = 0.40 fck Ac + 0.67 fy Asc

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 39

𝑃 𝑃
484197 = 0.4 × 20 × 𝐴𝑔 (1 − ) + 0.67 × 415 × × 𝐴𝑔
100 100

484197 = 720000 – 7200 P + 250245 P

243045 P = 235803

P = 0.97%

Asc = (0.97 ×300 × 300)/100 = 873 mm2

Provide 8 bars of 12 mm ø c/c

Diameter not less than

a. ø/4 = 12/4 = 3 mm Use 6 mm Ties

Pitch: Not more than

a. Least lateral dimension = 300 mm


b. 16 × ø = 16 × 12 = 192 mm
c. 300 mm

Provide 6 mm Ties at 190 mm c/c.

LOAD ON FOOTING F1:

Column Size = 300×300 mm

Pu = 484.197 KN

Soil Bearing Capacity = 150 KN/m2

Using M-20 and Fe-415


Self Weight of Footing = (10×484.197)/100

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 40

(10% of Total Load) = 48.41 KN

Total Load = 484.197 + 48.41 = 532.607 KN

Area of Footing = Total Load/Soil Bearing Capacity

Area of Footing = 532.607/150 = 3.55 m2

Size of Footing = 1.88 m ≈ 2 m

Provide Footing of 2×2 m

Soil Reaction for Factored Load

1.5 × 484.197
𝑞𝑢 = = 181.57 𝐾𝑁/𝑚2
2×2

Let Critical Section is at distance‘d’ from face of Column

VU = Soil pressure from shaded area

= qu × B [{(B-b)/2} - d]

Vu = 362 × (850 - d)

Assume 0.2% steel for M-20 concrete

τc = 0.32 N/mm2
Minimum depth required:

τc bd = Vu : 0.32 × 2000 × d = 362 × (850 - d)

d = 307 mm ~ 310 mm

Check for Bending:


Mu lim = 0.138 × fck bd2

= 0.138×20×2000×3102 = 530.47 × 106N-mm

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 41

Mu = qu (B – b)2/8 × B

= 0.181(2000-300)2/8 × 2000

= 130.772 × 106 N-mm < Mu lim.

Check for two way shear:


Perimeter of critical section = 4 × (b + d)

= 4 × (300+310) = 2440 mm

Area of critical section = 2440 × d

= 2440 × 310

upward pressure (shaded area)


Two way shear stress =
Area of critical section
0.116 [(2000×2000)−(610×610)]
=
2440 × 310

= 0.556 N/mm2
Max. Shear stress permitted = 0.25√fck = 0.25√20 = 1.118 N /mm2

Mu = 130.722 × 106 N-mm

Ast fy
Mu = 0.87 × fy × Ast × d [1 − ]
bd fck

A 415
130.722 × 106 = 0.87 × 415 × Ast × 310 [1 − (2000×310
st
)
]
20

Ast = 1217 mm2

Using 12 mm bars.
𝜋⁄ ×122 ×2000
4
𝑆𝑝𝑎𝑐𝑖𝑛𝑔 = = 185.7 mm
1217

Ast provided = 1256 mm2 Provide 12 mm bars @ 180 mm c/c

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 42

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 43

LOAD ON COLUMN C2:

Load on each Column due to truss = 72 KN

Self Wt. of wall = 2 × 96.174 = 192.348 KN/m

Self Wt. of Beam = 13.5 × 3 = 40.5 KN/m

Self Wt. of Column = 25 × 0.3 × 0.3 × 7.98 = 17.95 KN

Spacing of Column = 6m

Self Wt. of Gabble Wall

= 19.5 × 0.3 [(5.94×3.96) + {2× (1/2)×5.94×1.04}]

= 19.5 × 0.3 [23.52 + 6.18] = 173.73 KN

Total Load on Column = 192.348 + 40.5 + 17.95 + 173.73

P = 424.528 KN

Factored Load Pu = 636.79 KN

Using M-20 and Fe-415


Height of Column above G.L = 5.48 m

Both end are fixed, it implies

Leff = 5.48 × 0.65 = 3.562 m = 3562 mm


𝐿𝑒𝑓𝑓 3562
= = 11.82
𝑏 300
(It is designed as Axially Loaded Short Column)

Size of Column = (300 × 300) mm = 90000 mm2

Using “P” Percentage Reinforced

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 44

Pu = 0.40 fck Ac + 0.67 fy Asc


𝑃 𝑃
636790 = 0.4 × 20 × 90000 (1 − ) + 0.67 × 415 × × 90000
100 100

636790 = 720000 – 7200 P + 250245 P

243045 P = 83210

P = 1.2%

Asc = (1.2 ×300 × 300)/100 = 1080 mm2

Provide 6 bars of 16 mm ø c/c

Diameter not less than

b. ø/4 = 16/4 = 4 mm Use 6 mm Ties

Pitch: Not more than

d. Least lateral dimension = 300 mm


e. 16 × ø = 16 × 16 = 256 mm
f. 300 mm

Provide 6 mm Ties at 250 mm c/c.

LOAD ON FOOTING F2:


Column Size = 300×300 mm

Pu = 636.79 KN

Soil Bearing Capacity = 150 KN/m2

Using M-20 and Fe-415


Self Weight of Footing = (10×636.79)/100

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 45

(10% of Total Load) = 63.67 KN

Total Load = 636.79 + 63.67 = 700.58 KN

Area of Footing = Total Load/Soil Bearing Capacity

Area of Footing = 700.58/150 = 4.67 m2

Size of Footing = 2.16 m ≈ 2.20 m

Provide Footing of 2.20×2.20 m

Soil Reaction for Factored Load

1.5 × 636.79
𝑞𝑢 = = 197.35 𝐾𝑁/𝑚2
2.20 × 2.20

Let Critical Section is at distance ‘d’ from face of Column

VU = Soil pressure from shaded area

= qu × B [{(B-b)/2} - d]

= 0.197 × 2200 [(2200-300)/2 – d]

VU = 433.4 × (950 - d)

Assume 0.2% steel for M-20 concrete τc = 0.32 N/mm2


Minimum depth required:

τc bd = VU : 0.32 × 2200 × d = 433.4 × (950 - d)

d = 362 mm ~ 370 mm

Check for Bending:


Mu lim = 0.138 × fck bd2

= 0.138×20×2200×3702 = 831.25 × 106N-mm

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 46

Mu = qu (B – b)2 /8 × B

= 0.197×(2000-300)2/8 × 2200

= 195.57 × 106 N-mm < Mu lim.

Check for two way shear:


Perimeter of critical section = 4 × (b + d)

= 4 × (300+370) = 2680 mm

Area of critical section = 2680 × d

= 2680 × 370

upward pressure (shaded area)


Two way shear stress =
Area of critical section
0.197 [(2200×2200)−(370×370)]
=
2680 × 370

= 0.93 N/mm2
Max. Shear stress permitted = 0.25√fck = 0.25√20 = 1.118 N /mm2

Mu = 195.57 × 106 N-mm

Ast fy
Mu = 0.87 × fy × Ast × d [1 − ]
bd fck

A 415
195.57 × 106 = 0.87 × 415 × Ast × 370 [1 − (2200×370
st
)
]
20

Ast = 1521 mm2

Using 12 mm bars.
𝜋⁄ ×122 ×2200
4
𝑆𝑝𝑎𝑐𝑖𝑛𝑔 = = 163 mm
1521

Ast Provided = 1554.3 mm2 Provide 12 mm bars @ 160 mm c/c

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 47

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 48

LOAD ON COLUMN C3:

Load on each Colum due to truss = 72 KN

Self Wt. of wall = 2 × 96.174 = 192.348 KN/m

Self Wt. of Beam = 13.5 × 3 = 40.5 KN/m

Self Wt. of Column = 25 × 0.3 × 0.3 × 7.98 = 17.95 KN

Spacing of Column = 6m

Total Wt. of Gabble Wall

= 19.5 × 0.3 [(1/2) × 5.94 × 1.98]

= 34.40 KN

Total Load on Column = 192.348 + 40.5 + 17.95 + 34.40

P = 285.198 KN

Factored Load Pu = 427.79 KN

Using M-20 and Fe-415


Height of Column above G.L = 5.48 m

Both end are fixed, it implies

Leff = 5.48 × 0.65 = 3.562 m = 3562 mm


𝐿𝑒𝑓𝑓 3562
= = 11.82
𝑏 300
(It is designed as Axially Loaded Short Column)

Size of Column = (300 × 300) mm = 90000 mm2

Using “P” Percentage Reinforced

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 49

Pu = 0.40 fck Ac + 0.67 fy Asc


𝑃 𝑃
427790 = 0.4 × 20 × 90000 (1 − ) + 0.67 × 415 × × 90000
100 100

427790 = 720000 – 7200 P + 250245 P

243045 P = 292210

P = 0.90%

Asc = (0.90 × 300 × 300)/100 = 810 mm2

Provide 8 bars of 12 mm ø c/c

Diameter not less than

c. ø/4 = 12/4 = 3 mm Use 6 mm Ties

Pitch: Not more than

g. Least lateral dimension = 300 mm


h. 16 × ø = 16 × 12 = 192 mm
i. 300 mm

Provide 6 mm Ties at 190 mm c/c.

LOAD ON FOOTING F3:


Column Size = 300×300 mm

Pu = 427.79 KN

Soil Bearing Capacity = 150 KN/m2

Using M-20 and Fe-415


Self Weight of Footing = (10×427.79)/100

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 50

(10% of Total Load) = 42.77 KN

Total Load = 427.79 + 42.77 = 470.56 KN

Area of Footing = Total Load/Soil Bearing Capacity

Area of Footing = 470.56/150 = 3.13 m2

Size of Footing = 1.77 m ≈ 1.8 m

Provide Footing of 1.8×1.8 m

Soil Reaction for Factored Load

1.5 × 427.79
𝑞𝑢 = = 198.05 𝐾𝑁/𝑚2
1.8 × 1.8

Let Critical Section is at distance ‘d’ from face of Column

VU = Soil pressure from shaded area

= qu × B [{(B-b)/2} - d]

Vu = 356.4 × (750 - d)

Assume 0.2% steel for M-20 concrete τc = 0.32 N/mm2


Minimum depth required:

τc bd = Vu : 0.32 × 1800 × d = 356.4 × (750 - d)

d = 287 mm ~ 300 mm

Check for Bending:


Mu lim = 0.138 × fck bd2

= 0.138×20×1800×3002 = 447.120 × 106N-mm

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 51

Mu = qu (B – b)2 /8 × B

= 0.198(1800-300)2/8 × 1800

= 100.23 × 106 N-mm < Mu lim.

Check for two way shear:


Perimeter of critical section = 4 × (b + d)

= 4 × (300+300) = 2400 mm

Area of critical section = 2400 × d

= 2400 × 300

upward pressure (shaded area)


Two way shear stress =
Area of critical section
0.198 [(1800×1800)−(300×300)]
=
2400 × 300

= 0.86 N/mm2
Max. Shear stress permitted = 0.25√fck = 0.25√20 = 1.118 N /mm2

Mu = 100.23 × 106 N-mm

Ast fy
Mu = 0.87 × fy × Ast × d [1 − ]
bd fck

A 415
100.23 × 106 = 0.87 × 415 × Ast × 310 [1 − (2000×310
st
)
]
20

Ast = 960 mm2

Using 12 mm bars.
𝜋⁄ ×122 ×1800
4
𝑆𝑝𝑎𝑐𝑖𝑛𝑔 = = 211.95 mm
960

Ast Provided = 1017.36 mm2 Provide 12 mm bars @ 200 mm c/c.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 52

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 53

LOAD ON COLUMN C4:

Self weight of wall (3m span) = 3 × 0.22 × 1.85 × 19.5

= 23.80 KN

Self weight of beam = 25 × 0.25 × 0.30 × 3

= 5.625 KN

Self weight of column = 25 × 0.25 × 0.3 × 2.15

= 4.03 KN

Total load on column = 33.45KN

Pu = 50.18 KN

Size of column = 250 × 300

Ag = 75000 mm4

Pu = 0.46fck Ac + 0.67fy Asc


𝑃 𝑃
50.18 × 103 = 0.4 × 20 × 𝐴𝑔 (1 − ) + 0.67 × 415 × × 𝐴𝑔
100 100

50.18 × 103 = 600000 - 6000p + 208537.5p

P = 0.37 %

We provide min. reinforcement of 0.8 %

50.18 × 103 = (7.93+2.22) Ag

Ag = 49431mm2

Asc = (0.8×49431)/10 = 395mm2

Provide 6 bars of 10mm

Ast provided = 471mm2

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 54

Diameter not less than

d. ø/4 = 10/4 = 2.5 mm Use 6 mm Ties

Pitch: Not more than

j. Least lateral dimension = 300 mm


k. 16 × ø = 16 × 10 = 160 mm
l. 300 mm

Provide 6 mm Ties at 160 mm c/c.

LOAD ON FOOTING F4:

P = 50.18 KN

Self weight of footing = 50.18/10 = 5.018 KN

Total load = 55.198 KN

S.B.C. = 100 KN/m2

Area of footing A = 55.198/100 = 0.55 m2

L=B=0.74m

We provided footing of 0.8×0.8 m

Soil Reaction for Factored Load

1.5 × 55.98
𝑞𝑢 = = 129.37 𝐾𝑁/𝑚2
0.8 × 0.8
Let Critical Section is at distance ‘d’ from face of Column

VU = 103.49 × (250 - d)

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 55

Assume 0.2% steel for M-20 concrete τc = 0.32 N/mm2


Minimum depth required:

τc bd = Vu : 0.32 × 800 × d = 103.49 × (250 - d)

d = 72 mm ~ 80 mm

Check for Bending:


Mu lim = 0.138 × fck bd2

= 0.138×20×800×802 = 14.13 × 106 N-mm

Mu = qu (B – b)2 /8 × B

= 0.129(800-80)2/8 × 800 = 6.687 × 106 N-mm < Mu lim.

Check for two way shear:


Perimeter of critical section = 4 × (b + d) = 1320 mm

Area of critical section = 1320 × d = 1320 × 80

upward pressure (shaded area)


Two way shear stress =
Area of critical section
0.129 [(800×800)−(80×80)]
= = 0.774 N/mm2
1320 × 80
Max. Shear stress permitted = 0.25√fck = 0.25√20 = 1.118 N/mm2

Mu = 6.687 × 106 N-mm

Ast fy
Mu = 0.87 × fy × Ast × d [1 − ]
bd fck

A 415
6.687 × 106 = 0.87 × 415 × Ast × 80 [1 − (800×80
st
)
]
20

Ast = 251.7 mm2 Using 12 mm bars.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 56

𝜋⁄ ×102 ×800
4
𝑆𝑝𝑎𝑐𝑖𝑛𝑔 = = 249 mm ~ 220 mm
251.7

Provide 10 mm bars @ 220 mm c/c Ast provided = 285.45 mm2

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 57

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 58

DESIGN OF STEP FOOTING OF STACK

Thickness of wall = 0.30 m

Height of wall =1m

Unit weight of masonary = 19.5 KN/m2

Density of soil = 16 KN/m3

Angle of repose =300

Soil bearing capacity = 100 KN/m2

Modulus of rupture = 160 KN/m2

=19.5 × 1 × 0.30

=5.85 KN/m

Weight of concrete slab = 25 × 0.20 × 0.30

=1.5 KN/m

Super imposed load = 8.07 KN/m

Total weight of foundation = 8.07 + 1.5 + 5.85

= 15.42 KN/m

Weight of foundation: 10% of total weight

= (15.42 × 10)/100

= 1.542 KN/m

Total weight on soil = 15.42 + 1.542 = 16.96 KN/m

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 59

Width of foundation = Total weight/s.b.c.

= 16.96/100

= 0.1696 m
𝑤 1−sin ∅
Depth of foundation = ×(1+sin ∅) 2
𝑎×𝜌

16.96 1−sin 30
= .1696×16 × (1+sin 30)2
= 6.25 × 0.1111

= 0.695 m

So we assume,

Width of foundation = 0.8 m

Depth of foundation = 0.75 m

Depth of concrete slab:

3𝑞
D = 𝛼 × √𝑀

15 3×16.96
= 100 × √160×0.75×0.80

= 0.109 m ≈ 0.15 m or 15 cm.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 60

ESTIMATION

Quantity
S. Particular of items Length Breadth Height (in cu.
no. & details of works No. (in m) (in m) (in m) m) Explanatory notes
Earthwork in
excavation in
1 foundation:
L = 31.66 m because
30 cm walls of stack 20 31.66 0.8 0.75 379.92 No. of junction = 0
For longer span
column footing (C1) 16 2 2 2.5 160
For shorter span
column footing (C2) 8 2.2 2.2 2.5 96.8
For end column
footing (C3) 4 1.8 1.8 2.5 32.4
30 cm wall of office 1 31.66 0.8 0.75 18.996
30 cm walls of outer L = 182.12 m because
slab 1 182.12 0.8 0.75 109.272 No. of junction = 0
For columns of
boundary walls 40 0.8 0.8 0.8 20.48
Total 817.86

Brick work in whole


2 structure
Brick work in
boundary wall:
L = 74.7 - 4.88 (16-
column of size
Longer span 2 69.82 0.2 1.82 53.37 0.3×0.3)
L = 51.28 - 2.74 (9-
Shorter span 1 48.48 0.2 1.82 18.53 column)
L = 51.28 - 9.14 (gate
length) - 2.44 (8-
Second shorter span 1 39.7 0.2 1.82 15.17 column)
Total 87.057

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 61

Brick work in
Warehouse wall:
L = 54.86 - 3.04 (10-
Longer span 2 51.82 0.3 4.88 154.26 column of size 0.3×0.3)
Ht = 5.49 - 0.61 (2-
Beams)

Deduction:
Shutter in one span
both sides 14 2.44 0.3 2.44 25.405
Ventilation in both
sides 12 0.61 0.3 0.61 1.36
Windows in both span 12 0.61 0.3 0.61 1.36

Net brick work in


longer span 126.05

L = 29.95 - 1.83 (6-


Shorter span 2 28.14 0.3 4.88 83.71 column of size 0.3 × 0.3)
Ht = 5.49 - 0.61 (2-
columns of size 0.3 × 0.3)

Deduction:
Doors 4 0.96 0.3 2.13 2.49
Shutter 1 2.44 0.3 2.44 1.82
Window 1 0.914 0.3 0.914 0.26

Net brick work 79.14

Brick work in stack:


L = Total center line
length of 0.30m wall =
1st footing 20 31.66 0.5 0.2 63.32 31.66 m
2nd footing 20 31.66 0.4 0.2 50.64 No. of stacks = 20
Plinth wall 20 31.66 0.3 1.2 227.94

Total Brick work in


stack 341.9

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 62

Brick work in office


H= 3.65 above plinth
1st footing 31.66 0.5 0.2 3.166 wall
Total height of 0.30m
wide wall = 3.65 + 0.2
2nd footing 31.66 0.4 0.2 2.532 =3.85 m
Plinth wall 31.66 0.3 3.85 36.56
Deduction:
Door 1 1.12 0.3 2.13 0.72
Window 1 0.91 0.91 0.3 0.25
Net brick work 41.3
Brick work in gabble Area = 30 × 5/2 = 75,
wall: 45 Volume = 75 × 0.3 = 45
Brick work under the
outer slab of
warehouse:
Longer span = 56.38 m,
1st footing 146.38 0.5 0.2 14.6387 Shorter span = 33.02 m
Long span = 56.38 + 0.15
= 56.53 m, Shorter span
2nd footing 146.38 0.4 0.2 11.71 = 33.02 + 0.3 = 33.32 m
Total length = (2 × 56.53)
Plinth wall 146.38 0.3 1.2 52.696 + 33.32 = 146.38m
Total brick work in
stack 79.04
3 Calculation of P.C.C.
L= Total center line
P.C.C. in stack 21 31.66 0.8 0.1 53.19 length = 31.66m
P.C.C. in column
footing of warehouse
& boundary wall
Warehouse column:
C1 16 2 2 0.1 6.4
C2 8 2.2 2.2 0.1 3.872
C3 4 1.8 1.8 0.1 1.296
Total 11.568
boundary wall column 40 0.8 0.8 0.1 2.56
Total P.C.C. in column
footing 14.3

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 63

P.C.C. under the


footing of outer slab 146.38 0.8 0.1 11.71

Total area = 448.39,


P.C.C. in the passage 0.1 44.83 Volume = 448.39 × 0.1

Total P.C.C. in
warehouse 124.08

Calculation of cement
concrete in wall
4 footing

C.C. under the footing


of outer of stacks & L = Total c/c length of
office 21 31.66 0.8 0.15 79.8 one stack

C.C. under the footing L= Total c/c length of


of outer slab 146.38 0.8 0.15 17.56 wall = 146.38m

C.C. over 0.10 m


P.C.C. in the passage:

Large span passage


area:
A1 2 54.864 0.33 0.15 5.43
A2 2 54.864 0.61 0.15 10.04

Shorter span passage


area:
A3 8 27.43 1.52 0.15 50.03

C.C. on the floor of


office over the D.P.C. 9.14 6.1 0.05 2.8

Total C.C. in whole


structure 165.63

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 64

Calculation of R.C.C.
5 in whole structure
R.C.C. in footing of
boundary columns 40 0.9 0.9 0.2 6.48

R.C.C. in footing of
warehouse columns:
Footing of C1 16 2 2 0.31 19.84
Footing of C2 8 2.2 2.2 0.37 14.32
Footing of C3 4 1.8 1.8 0.3 3.89

R.C.C. in columns of
warehouse:
Column C1 16 0.3 0.3 7.67 11.044
Column C2 8 0.3 0.3 7.61 5.479
Column C3 4 0.3 0.3 7.68 2.764

R.C.C. in columns of L = 1.85 + 0.8 - 0.08 =


boundary wall 40 0.25 0.3 2.57 7.71 2.57

R.C.C. in slab of stack 20 9.14 6.1 0.2 223.01

R.C.C. in slab of office 1 9.14 6.1 0.1 5.6

R.C.C. in outer slab of


warehouse:
Longer span 2 56.39 1.524 0.2 34.37
Shorter span 1 29.97 1.524 0.2 9.134

R.C.C. in beams:
Beam 1 (for longer
span) 18 6 0.3 0.3 9.72 9 - beams in one side
Beam 1 (for shorter
span) 10 5.94 0.3 0.3 5.35 5 - beams in one side

Beam 2 (for longer


span) 18 6 0.3 0.3 9.72
Beam 2 (for shorter
span) 10 5.94 0.3 0.3 5.35

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 65

Beam 3 (Top beam of


longer side) 18 6 0.3 0.3 9.72

Beam 4 (Top 1st & 5th 4 - in both top beams of


of shorter span 4 5.94 0.3 0.3 2.031 shorter side

Beam 5 (Top 2nd &


4th beam of shorter
span) 4 5.94 0.3 0.3 2.031

Beam 6 (Top centre 2 - in both top center


beam of shorter span) 2 5.94 0.3 0.3 1.069 beam of shorter side

32 - in both longer &


Beam 7 (a) 32 6 0.3 0.3 17.28 shorter side
Beam 7 (b) 2 4.57 0.3 0.3 0.823
Beam 7 (c) 2 5.18 0.3 0.3 0.932
Beam 7 (d) 2 5.832 0.3 0.3 1.05
Beam 7 (e) 1 3.35 0.3 0.3 0.302
Total R.C.C. work in
beam 7 20.675

Total R.C.C. work in


beams 65.378

Total R.C.C. work in


whole structure 404.705

6 REINFORCEMENT
19.041
In beam 1 15.066 1.61% 78.5 Qt. 1.61% of total volume 1
19.041
In beam 2 15.066 1.61% 78.5 Qt. 1.61% of total volume 2
In beam 3 9.72 0.30% 78.5 2.289 Qt. 0.30% of total volume 3
In beam 4 2.031 1.21% 78.5 1.921 Qt. 1.2% of total volume 4
In beam 5 2.031 2.41% 78.5 3.842 Qt. 2.41% of total volume 5
In beam 6 1.069 3.77% 78.5 3.163 Qt. 3.77% of total volume 6
In beam 7 20.422 0.38% 78.5 6.091 Qt. 0.38% of total volume 7
55.388
Total Qt. Or 5538.8≈5539 Kg.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 66

7 PLASTERING
898.73
Boundary wall 485.8 1.85 Sq.m. (74.67×4)+(51.30×2)+(42.26×2)=485.8
Ware house 1860.13
wall 339.44 5.48 Sq.m. (54.86×4)+(30×4)=339.44

Deduction
Total area of 89.23
shutter 15 2.43 2.43 Sq.m.
Total area of 4.46
window w1 12 0.6 0.6 Sq.m.
Total area of 4.46
ventilation 12 0.6 0.6 Sq.m.
Total area of 10.08
door 4 1.2 2.1 Sq.m.
Total area of 0.83
window w2 0.91 0.91 Sq.m.
109.06
Total deduction Sq.m.
Area of gable 300
wall Sq.m. 2×(1/2×15×5)×4

Total area of
plastering in 300
ware house wall Sq.m.

Outer wall of
ware house
112.76
Long wall 2 56.38 m 56.38×2
Short wall of
back side 33.02 33.02 m
Short wall of
front side 3.04 m
Total length of 148.82
wall m 112.76+33.02+3.04
Total area of 148.82
wall 148.82 1 Sq.m.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 67

Plastering in office

Shorter span 6 6.1 36.6 m 6.1×3×2


Longer span 4 9.15 36.6 m 9.15×2×2
Toilet long wall 2 2.13 4.26 m 2.13×2
Short wall 2 1.21 2.42 m 1.21×2
Office long wall 2 3.04 6.08 m 3.04×2
Short wall 2 3.04 6.08 m 3.04×2
Total length 92.08 92.08 m 36.6×2+2.42+4.26+6.08×2
Total height 3.66 3.66 m

337.01
Total plaster Sq.m. 3.66×92.08

Deduction
10.08
Door 4 1.2 2.1 Sq.m. (1.2×2.1)×4
0.82
Window 1 0.91 0.91 Sq.m. (0.91×0.91) × 1
0.405
Ventilator 2 0.45 0.45 Sq.m. (0.45×0.45) × 2

325.69
Net plaster Sq.m. 337-10.08-0.82

8 MURRUM FILLING
In stacks 20 9.2 6.1 1
1116.30
Total volume Cu.m. (9.15×6.1×1) × 20
132.76
in outer slab 2 54.86 1.21 1 Cu.m. (54.86×1×1.21) × 2
39.954
Shorter span 33.02 1.21 1 Cu.m. 33.02×1.21×1

1289.06
Total Murrum Filling Cu.m. 40+132.76+1116.30

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 68

9 FINE AGGREGATE

Thickness 0.5
Longer span 2 74.67 9.15 0.05

68.32
Total volume Cu.m. (74.67×9.15×0.05) × 2
27.45
Shorter span 2 30 9.15 0.05 Cu.m. (309×150×0.05) × 2

95.77
Total fine aggregate Cu.m. 68.32+27.45

CALCULATION OF
10 TRUSS

7200 Wt. Of Half Truss= 7200


Wt. of One Truss 2 Kg. 14400 Kg Kg.

14400 115200
Total Wt. Of Truss 8 Kg. Kg Or 1152 Qt.

CALCULATION OF
11 ROOF SHEETS

Total Area of Roof 1760


Sheets 2 55 m. 16 m. Sq.m. No. Of Inclined Faces= 2
4.46
Area of One Sheet 1 3.65m. 1.22m. Sq.m.
1760/ Total Area/ Area of One
Number of Sheets 4.46 395 Sheet
10% area of sheets
get increased due to 395 ×
overlapping 10/100 39.5≈40
Total No. Of Sheets 435

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 69

FINAL COST

Item
No. Description Or Particulars Quantity Unit Rate Amount
Excavation in all type of soil up to required
depth for column, footing including
1 throwing off the soil 817.86 Cu.m. 181 ₹ 148,031

Providing brick masonary in First class open


bhatta good quality brick working 1:6
2 Cement Mortar 799.487 Cu.m. 3200 ₹ 2,558,358

Providing and laying at site 0.10 m thick


plain cement concrete 1:4:8 Including
3 formwork 124.08 Cu.m. 2800 ₹ 347,200

Providing and Laying at site 0.15 m thick


cement concrete 1:1.5:3 (M-20) Including
4 formwork 165.63 Cu.m. 4905 ₹ 812,415

Providing and placing reinforced cement


concrete M-20 for column, beams, slabs
and other structural members, including
formwork, compacting & curing without
5 reinforcement 404.705 Cu.m. 5095 ₹ 2,061,971

Providing and placing reinforcement with


6 binding wire and cutting as per drawing 5538.8 Kg. 46 ₹ 254,784

Providing and laying plaster work over all


masonary and RCC work 20mm thick in 1:4
CM including scaffolding ,curing Inner
7 Plaster 3424.31 Sq.m. 140 ₹ 479,403

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 70

8 Providing Murrum filling below Stacks Slab 1290 Cu.m. 600 ₹ 774,000

Providing fine Aggregate On Road around


9 Warehouse 96 Cu.m. 1100 ₹ 105,600

Providing Truss structure Below the Steel


10 Sheets, Rates including with labour 115200 Kg. 64 ₹ 7,372,800

11 Providing Steel Sheets as Roof of Truss 435 No. 850 ₹ 369,750

Provide Semosum on Boundary wall, Outer


wall of Ware-House and Acrylic Distemper
12 on Office Room & Guard's Room ₹ 90,000

Total :- ₹ 15,374,312

Add 2.5 % for electrical, water charges and


13 choukidar etc. ₹ 384,357
Net
Total :- ₹ 15,758,669
Say as:- ₹ 15,759,000

Add 15 % of Total Cost for Contractor's


14 Profit ₹ 2,363,850
GRAND
TOTAL:- ₹ 18,121,850
Say as:- ₹ 18,122,000

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 71

CONCLUSION

 The Rate of Construction of Warehouse is Rs. 1030 per Sq. Ft2.

 The design of R.C.C. structured is done by Limit State Theory.

 All the slabs are designed as two way Slabs, by the method
provided by IS 456: 2000.

 It is evident that load in a slab below office is so less, that slab


were safe in all aspects with the minimum reinforcement as
per IS 456: 2000.

 The Reinforcement is 1.61 % in slab below Stacks.

 Beams are designed individually as fixed beams with doubly


and singly reinforced of 300 mm × 300 mm.

 Columns are designed as Axially Loaded Short Column of


dimension 300 mm × 300 mm.

 Isolated footing was provided of maximum size 2.2 m × 2.2 m


and safe bearing capacity of soil is 150 KN/m2.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922


ANKIT GUPTA | B.E. (CIVIL) | SAIT, Indore 72

REFERENCES

 Requirement, Market Potentiality and Assumptions for


warehouse is referred by Food Corporation of India and
Madhya Pradesh Warehouse Corporation

 IS 456:2000 Indian Standard Code of practice for Plain &


Reinforced Concrete

 SP 16 Indian Standard Codes of Design Aids for Reinforced


Concrete

 SP 38 Hand book of Typified Designs for Structures with Steel


Roof Truss

 IS 875:1987 Code of practice for Design of Load for Building &


Structure (Part 1 – Dead Load, Part 2 – Imposed Load and Part
3 – Wind Load)

 IS 4082:1996 Stacking and Storage of Construction Materials


and Components at Site

 R.C.C. Theory & Design: S.S. Bhavikatti – New Age International


Publishers

 Design of Steel Structure: Dr. B.C. Punmia, Ashok Kumar Jain,


Arun Kumar Jain – Laxmi Publishing Company

 Estimation and Costing: Dr. B.N. Dutta – UBS Publisher and


Distributers Pvt. Ltd.

https://amity.academia.edu/AnkitGupta AMITY UNIVERSITY | NOIDA | +91 94 25 758922

View publication stats

You might also like