Development of Fishery Harbour in Dibba at Musandam Governorate

MATERIAL & WORK INSPECTION REQUEST SCHEDULE Date: 17-Feb-2024


Please be advised that the following elements of work will be available for inspection on 18-Feb-2024
PARTICIPANT TYPE Duration
Rev. SUB -
Sl# AREA/UNIT/ITEM WIR / MIR NO. DESCRIPTION OF INSPECTION DISCIPLINE DATE / TIME (Hours or Days) REMARKS
Nos, CON Contractor Engineer Employer Others

Inspection for Electrical Conduits in canopy slab pre pour stage (Highlight
1 FT-MEP SDMC-100-IR-MEP-FT-0005 00 BLDG    18-Feb-24 10:00 AM
Drawing attached)
Inspection for Admin building 2nd lift columns (2nos) at Grid 3 (Stair
2 AB SDMC-100-IR-CW-AB-0054 02 landing area) in 1st Floor reinforcement, pre pour form work and Concrete BLDG    18-Feb-24 FOR APPROVAL
(Dwg attached)
Inspection for Lift Wall form work and casting at 2nd Floor as Highlighted
3 AB SDMC-100-IR-CW-AB-0067 01 BLDG    18-Feb-24 11:30 AM
on drawing - Administration Building

Inspection for Staircase Reinforcement, Pre pour Form work and


4 AB SDMC-100-IR-CW-AB-0068 01 BLDG    18-Feb-24 10:30 AM
Concrete pouring from Second floor to MID Landing (Dwg attached)

Inspection for Plinth beam form work and concrete pouring at Fish Auction
5 FAH SDMC-100-IR-CW-FA-0026 01 BLDG    18-Feb-24 10:00 AM
Hall (Highlighted Dwg attached)

Inspection for plastering work application on Internal and External surface


6 FB1 SDMC-100-IR-CW-FB1-0137 17 BLDG    18-Feb-24 10:00 AM
of walls ( Highlighted in the drawing)

Inspection for plastering preparation with accessories & bonding coat


7 FB1 SDMC-100-IR-CW-FB1-0182 00 BLDG    18-Feb-24 10:00 AM
application inside area (Highlighted in the drawing)
Inspection for Column Settingout, pre pour form work and column starter
8 FT SDMC-100-IR-CW-FT-0027 02 above Plinth Beam Concrete pouring (Highlighted on drawing) - Ferry BLDG    18-Feb-24 FOR APPROVAL
Terminal Building (Highlighted Dwg attached)
Inspection for Backfilling with Selected Reclamation Material and FDT-
9 FT SDMC-100-IR-CW-FT-0059 03 INSIDE Plinth beam at Grid A3/A7 - J3/J7 from 2nd Layer- FERRY BLDG    18-Feb-24 9:30 AM
TERMINAL (As Highlighted Drawing)
Inspection for Roof Shade Slab setting out ,reinforcement , form work and
10 FT SDMC-100-IR-CW-FT-0069 00 casting at Grid A4-A5 (+3.76 Level) - (Highlighted on drawing) - Ferry BLDG    18-Feb-24 8:30 AM
Terminal Building
Inspection for Roof Shade Slab setting out ,reinforcement , form work and
11 FT SDMC-100-IR-CW-FT-0070 00 casting at Grid A7-A8 (+3.76 Level) - (Highlighted on drawing) - Ferry BLDG    18-Feb-24 8:30 AM
Terminal Building
Inspection for Surface preparation of inside Ground beam prior to
12 IP SDMC-100-IR-CW-IP-0018 01 BLDG    18-Feb-24 10:00 AM
Waterproofing at Ice Plant (Highlighted Dwg attached)
Inspection for Column setting out, reinforcement, form work and casting -
13 IP SDMC-100-IR-CW-IP-0019 00 4 nos. A1, A3, A5, B1, B5 - (Highlighted on drawing) - Ferry Terminal BLDG    18-Feb-24 8:30 AM
Building
Inspection for Excavation level and Backfilling with Selected Reclamation
14 SS5 SDMC-100-IR-CW-SS5-0001 01 BLDG    18-Feb-24 8:00 AM
Material & FDT up to Formation level - Substation # 05
Inspection for Backfilling with Selected Reclamation Material and FDT -
15 TB2 SDMC-100-IR-CW-TB2-0018 01 Inside Periphery Wall from Foundation Top level (+3.525m) to up to Plinth BLDG    18-Feb-24 8:30 AM
beam bottom - Tourism Building-2
Inspection for Compound wall column reinforcement, Shuttering and
16 INFRA-CW SDMC-100-IR-INFRA-CW-0072 04 Concrete. Footing no's 26,27,28,29,30,31,32,33 (Highlighted Drawing INFRA    18-Feb-24 FOR APPROVAL
attached)
Inspection for Compound wall back filling with selected reclamation
17 INFRA-CW SDMC-100-IR-INFRA-CW-0085 06 material and FDT From 5th Layer Footing no's 07 TO 35(Highlighted INFRA    18-Feb-24 4:00 PM
Drawing attached)
Inspection For reinforcement,form work,Concrete Pouring & Post Pour of
18 INFRA-G SDMC-100-IR-INFRA-G-0726 02 INFRA    18-Feb-24 FOR APPROVAL
Light pole Foundation 03 Nos- LP-81,LP-82,LP-83

Inspection for pipe encasement including base concrete from MH no - S-


19 INFRA-G SDMC-100-IR-INFRA-G-0735 02 INFRA    18-Feb-24 FOR APPROVAL
54C to S-55C (As per Highlighted drawing attached)

Inspection for duct pipe encasement at road crossing at RD -13 Car


20 INFRA-G SDMC-100-IR-INFRA-G-0754 02 INFRA    18-Feb-24 FOR APPROVAL
parking area (As per Highlighted drawing attached)

Inspection for Concrete pouring for haunching behind curbstone at RD-25


21 INFRA-G SDMC-100-IR-INFRA-G-0781 02 INFRA    18-Feb-24 FOR APPROVAL
(Highlighted in attached Drawing)

Page 1 of 4
Development of Fishery Harbour in Dibba at Musandam Governorate
MATERIAL & WORK INSPECTION REQUEST SCHEDULE Date: 17-Feb-2024
Please be advised that the following elements of work will be available for inspection on 18-Feb-2024
PARTICIPANT TYPE Duration
Rev. SUB -
Sl# AREA/UNIT/ITEM WIR / MIR NO. DESCRIPTION OF INSPECTION DISCIPLINE DATE / TIME (Hours or Days) REMARKS
Nos, CON Contractor Engineer Employer Others

Backfilling (Sub grade Fill Material) FDT with selected reclamation


22 INFRA-G SDMC-100-IR-INFRA-G-0793 02 material Sub grade Layer RD-25 & FS-02,FS-03 (as per the highlighted INFRA    18-Feb-24 FOR APPROVAL
drawing)
Inspection For reinforcement,form work,Concrete Pouring & Post Pour of
23 INFRA-G SDMC-100-IR-INFRA-G-0807 01 INFRA    18-Feb-24 FOR APPROVAL
High mast Pedestal 01 Nos- HM -NO-24

Inspection For reinforcement,form work,Concrete Pouring & Post Pour of


24 INFRA-G SDMC-100-IR-INFRA-G-0814 01 INFRA    18-Feb-24 FOR APPROVAL
High mast Pedestal 01 Nos- HM -NO-25

Inspection For Backfilling with selected Reclamation material at Northside


25 INFRA-G SDMC-100-IR-INFRA-G-0851 01 INFRA    18-Feb-24 10:30 AM
of Admin Building From 4th Layer and FDT (Highlighted Dwg attached)

Inspection For reinforcement,form work,Concrete Pouring & Post Pour of


26 INFRA-G SDMC-100-IR-INFRA-G-0904 02 INFRA    18-Feb-24 FOR APPROVAL
ELV Manholes Foundation and Wall, ELV-MH-23

Inspection For reinforcement,form work,Concrete Pouring & Post Pour of


27 INFRA-G SDMC-100-IR-INFRA-G-0905 02 INFRA    18-Feb-24 FOR APPROVAL
ELV Manholes Foundation and Wall, ELV-MH-22

Inspection For Excavation and blinding for light pole SLP-D-34, SLP-D-35,
28 INFRA-G SDMC-100-IR-INFRA-G-0912 02 INFRA    18-Feb-24 10:30 AM
SLP-D-36

Inspection For reinforcement,form work,Concrete Pouring & Post Pour of


29 INFRA-G SDMC-100-IR-INFRA-G-0920 01 INFRA    18-Feb-24 3:30 PM
ELV Manholes Foundation and Wall, ELV-MH-28

Inspection For reinforcement,form work,Concrete Pouring & Post Pour of


30 INFRA-G SDMC-100-IR-INFRA-G-0925 01 INFRA    18-Feb-24 3:30 PM
ELV Manholes Foundation and Wall, ELV-MH-33

Inspection For reinforcement,form work,Concrete Pouring & Post Pour of


31 INFRA-G SDMC-100-IR-INFRA-G-0926 01 INFRA    18-Feb-24 3:30 PM
ELV Manholes Foundation and Wall, ELV-MH-34

Inspection For reinforcement,form work,Concrete Pouring & Post Pour of


32 INFRA-G SDMC-100-IR-INFRA-G-0928 00 INFRA    18-Feb-24 3:30 PM
ELV Manholes Foundation and Wall, ELV-MH-42

Inspection For reinforcement,form work,Concrete Pouring & Post Pour of


33 INFRA-G SDMC-100-IR-INFRA-G-0929 00 INFRA    18-Feb-24 3:30 PM
ELV Manholes Foundation and Wall, ELV-MH-41
Post pour inspection for ELV Manholes no's ELV-MH-29, ELV-MH-75,
34 INFRA-G SDMC-100-IR-INFRA-G-0930 00 ELV-MH-76, ELV-MH-25, ELV-MH-26, ELV-MH-23, ELV-MH-22, NRMH- INFRA    18-Feb-24 9:00 AM
01
Excavation of trench and bedding concrete (C30) for UPVC duct pipe at
35 INFRA-G SDMC-100-IR-INFRA-G-0931 00 road crossing for LV Cable, Fire Fighting and Future Duct at RD-3 at INFRA    18-Feb-24 3:00 PM
West side of Prayer Hall (as per the highlighted drawing)
Excavation of trench and bedding concrete (C30) for UPVC duct pipe at
36 INFRA-G SDMC-100-IR-INFRA-G-0932 00 road crossing for Telecom Duct at RD-3 at East side of Prayer Hall (as INFRA    18-Feb-24 3:00 PM
per the highlighted drawing)
Inspection for Excavation, FDT, setting out, pre pour form work, placing of
37 INFRA-G SDMC-100-IR-INFRA-G-0933 00 polythene sheet and blinding for ELV manhole no ELV-MH-29 near Fish INFRA    18-Feb-24 10:30 AM
Auction Hall (Highlighted on drawing)
Inspection for Excavation, FDT, setting out, pre pour form work, placing of
38 INFRA-G SDMC-100-IR-INFRA-G-0934 00 polythene sheet and blinding for ELV manhole no ELV-MH-42 at East side INFRA    18-Feb-24 10:30 AM
of Prayer Hall (Highlighted on drawing)
Post pour Inspection of Casted CORE-LOC (CAU) 2M³ - 36 Nos. (A-
39 CAU-Post pour SDMC-100-IR-1330 01 Marine    18-Feb-24 FOR APPROVAL
1506 to A-1541)

Post pour Inspection of Casted CORE-LOC (CAU) 2M³ - 36 Nos. (A-


40 CAU-Post pour SDMC-100-IR-1354 01 Marine    18-Feb-24 FOR APPROVAL
1542 to A-1577)

Post pour Inspection of Casted CORE-LOC (CAU) 2M³ - 36 Nos. (A-


41 CAU-Post pour SDMC-100-IR-1375 01 Marine    18-Feb-24 FOR APPROVAL
1578 to A-1613)
Inspection for Backfilling in Main Breakwater (JV scope Ground
42 JV-GIW SDMC-100-IR-11752 01 Improvement) From chainage 0+700 to 0+820 - Layer-01 (As highlighted Marine    18-Feb-24 FOR APPROVAL
in drawing)

Page 2 of 4
Development of Fishery Harbour in Dibba at Musandam Governorate
MATERIAL & WORK INSPECTION REQUEST SCHEDULE Date: 17-Feb-2024
Please be advised that the following elements of work will be available for inspection on 18-Feb-2024
PARTICIPANT TYPE Duration
Rev. SUB -
Sl# AREA/UNIT/ITEM WIR / MIR NO. DESCRIPTION OF INSPECTION DISCIPLINE DATE / TIME (Hours or Days) REMARKS
Nos, CON Contractor Engineer Employer Others

Inspection For Pre-Pour (Form Work, and Embeded Items) , Concrete


43 Capping Beam SDMC-100-IR-11900 01 Pouring & Post Pour of Capping beam Part-07 of Public transport quay Marine    18-Feb-24 3:00 PM
wall
Inspection For Pre-Pour (Form Work, Reinforcement and Embeded
44 Capping Beam SDMC-100-IR-11946 01 Items) , Concrete Pouring & Post Pour of Capping beam Part-11 of Public Marine    18-Feb-24 3:00 PM
transport quay wall
Inspection For Pre-Pour (Form Work, Reinforcement and Embeded
45 Capping Beam SDMC-100-IR-11999 01 Items) , Concrete Pouring & Post Pour of Capping beam Part-15 of Public Marine    18-Feb-24 3:00 PM
transport quay wall
Inspection For Pre-Pour (Form Work, Reinforcement and Embeded
46 Capping Beam SDMC-100-IR-12024 01 Items) , Concrete Pouring & Post Pour of Capping beam Part-19 of Public Marine    18-Feb-24 3:00 PM
transport quay wall
Inspection For Pre-Pour (Form Work, Reinforcement and Embeded
47 Capping Beam SDMC-100-IR-12026 01 Items) , Concrete Pouring & Post Pour of Capping beam Part-09 of Public Marine    18-Feb-24 3:00 PM
transport quay wall
Inspection For Pre-Pour (Form Work, Reinforcement and Embeded
48 Capping Beam SDMC-100-IR-12042 01 Items) , Concrete Pouring & Post Pour of Capping beam Part-23 of Public Marine    18-Feb-24 3:00 PM
transport quay wall
Inspection For Pre-Pour (Form Work, Reinforcement and Embeded
49 Capping Beam SDMC-100-IR-12052 01 Items) , Concrete Pouring & Post Pour of Capping beam Part-13 of Public Marine    18-Feb-24 3:00 PM
transport quay wall
Inspection For Pre-Pour (Form Work, Reinforcement and Embeded
50 Capping Beam SDMC-100-IR-12074 01 Items) , Concrete Pouring & Post Pour of Capping beam Part-17 of Public Marine    18-Feb-24 3:00 PM
transport quay wall
Inspection For Pre-Pour (Form Work, and Embeded Items) , Concrete
51 Capping Beam SDMC-100-IR-12087 01 Marine    18-Feb-24 3:00 PM
Pouring & Post Pour of Capping beam Part-08 of PTQW
Inspection For Pre-Pour (Form Work, Reinforcement and Embeded
52 Capping Beam SDMC-100-IR-12088 01 Items) , Concrete Pouring & Post Pour of Capping beam Part-21 of Public Marine    18-Feb-24 3:00 PM
transport quay wall
Inspection For Pre-Pour (Form Work, and Embeded Items) , Concrete
53 Capping Beam SDMC-100-IR-12127 01 Pouring & Post Pour of Capping beam Part-10 of Public transport quay Marine    18-Feb-24 3:00 PM
wall
Inspection For Pre-Pour (Form Work, and Embeded Items) , Concrete
54 Capping Beam SDMC-100-IR-12129 01 Pouring & Post Pour of Capping beam Part-12 of Public transport quay Marine    18-Feb-24 3:00 PM
wall
Inspection For Pre-Pour (Form Work, and Embeded Items) , Concrete
55 Capping Beam SDMC-100-IR-12142 01 Pouring & Post Pour of Capping beam Part-25 of Public transport quay Marine    18-Feb-24 3:00 PM
wall
Inspection For Pre-Pour (Form Work, and Embeded Items) , Concrete
56 Capping Beam SDMC-100-IR-12156 01 Pouring & Post Pour of Capping beam Part-14 of Public transport quay Marine    18-Feb-24 3:00 PM
wall
Inspection For Pre-Pour (Form Work, and Embeded Items) , Concrete
57 Capping Beam SDMC-100-IR-12175 02 Pouring & Post Pour of Capping beam Part-16 of Public transport quay Marine    18-Feb-24 3:00 PM
wall
Inspection For Pre-Pour (Form Work, and Embeded Items) , Concrete
58 Capping Beam SDMC-100-IR-12198 02 Pouring & Post Pour of Capping beam Part-18 of Public transport quay Marine    18-Feb-24 3:00 PM
wall
Inspection For Pre-Pour (Form Work, and Embeded Items) , Concrete
59 Capping Beam SDMC-100-IR-12213 01 Pouring & Post Pour of Capping beam Part-20 of Public transport quay Marine    18-Feb-24 3:00 PM
wall
Inspection For Pre-Pour (Form Work, Reinforcement and Embeded
60 Capping Beam SDMC-100-IR-12215 01 Items) , Concrete Pouring & Post Pour of Capping beam Part-27 of Public Marine    18-Feb-24 3:00 PM
transport quay wall
Inspection For Pre-Pour (Form Work, and Embeded Items) , Concrete
61 Capping Beam SDMC-100-IR-12223 01 Pouring & Post Pour of Capping beam Part-22 of Public transport quay Marine    18-Feb-24 3:00 PM
wall
Inspection For Pre-Pour (Form Work, and Embeded Items) , Concrete
62 Capping Beam SDMC-100-IR-12236 01 Pouring & Post Pour of Capping beam Part-24 of Public transport quay Marine    18-Feb-24 3:00 PM
wall
Inspection For Pre-Pour (Form Work, and Embeded Items) , Concrete
63 Capping Beam SDMC-100-IR-12247 01 Pouring & Post Pour of Capping beam Part-26 of Public transport quay Marine    18-Feb-24 3:00 PM
wall

Page 3 of 4
Development of Fishery Harbour in Dibba at Musandam Governorate
MATERIAL & WORK INSPECTION REQUEST SCHEDULE Date: 17-Feb-2024
Please be advised that the following elements of work will be available for inspection on 18-Feb-2024
PARTICIPANT TYPE Duration
Rev. SUB -
Sl# AREA/UNIT/ITEM WIR / MIR NO. DESCRIPTION OF INSPECTION DISCIPLINE DATE / TIME (Hours or Days) REMARKS
Nos, CON Contractor Engineer Employer Others

Joint Survey Inspection for 3 ~ 6 Ton Layer From Sta. 0+260 to Sta.
64 JOINT SURVEY SDMC-100-IR-12281 02 0+270 (Crest) Level till +6.50 at Lee Breakwater. (as per the attached Marine    18-Feb-24 FOR APPROVAL
Drawing)
Inspection of Survey levels and alignment of ROP Quaywall after vibro
65 Survey SDMC-100-IR-12295 01 Marine    18-Feb-24 FOR APPROVAL
compaction

Inspection for 1st layer Backfilling above Excavation Level (Reclamation


66 JV-GIW SDMC-100-IR-12308 01 fill) in Main Breakwater (JV scope Ground Improvement) from chainage Marine    18-Feb-24 FOR APPROVAL
0+550 to 0+630 - 1st Layer (As highlighted in drawing)
Excavation level inspection +3.5 level inspection prior to start backfilling in
67 JV-GIW SDMC-100-IR-12316 01 main breakwater ( JV scope Ground Improvement) From chainage 0+850 Marine    18-Feb-24 FOR APPROVAL
to 0+900 (as per the attached Drawing)
Excavation level inspection +3.2 level inspection prior to start backfilling in
68 JV-GIW SDMC-100-IR-12317 01 main breakwater ( JV scope Ground Improvement) From chainage 0+480 Marine    18-Feb-24 FOR APPROVAL
to 0+540 (as per the attached Drawing)
Inspection for Reinforcement & Formwork and Concrete Pouring of Cast
69 Kerb SDMC-100-IR-12325 01 Marine    18-Feb-24 FOR APPROVAL
in-situ Kerb (Type C) -19 Nos at Revetment F2
Excavation level inspection +3.2 level inspection prior to start backfilling in
70 JV-GIW SDMC-100-IR-12340 01 main breakwater ( JV scope Ground Improvement) From chainage 0+450 Marine    18-Feb-24 FOR APPROVAL
to 0+480 (as per the attached Drawing)
Joint Survey of Laying of Quarry Run rock layer 1-1000kg (Crest) From
71 JOINT SURVEY SDMC-100-IR-12342 01 Sta. 1+220 ~ 1+260, Level till +5.38 at Main Breakwater (as per the Marine    18-Feb-24 FOR APPROVAL
attached Drawing)
Inspection for Crushed Rock & Blinding Layer below Run-on Slab and
72 Run on Slab SDMC-100-IR-12364 01 Blinding Concrete prior to run-on Slab at Public Transport Quaywall (Panel Marine    18-Feb-24 10:00 AM
No-17 to 24) -42.7 Meters
Inspection for Casted CORE-LOC (CAU) - 2M³ - 36 Nos. (A-20688 to A-
73 CAU-Post pour SDMC-100-IR-12377 00 Marine    18-Feb-24 8:30 AM
20723)

Inspection For Pre-Pour & Concrete Pouring of Concrete Armour Unit -


74 CAU SDMC-100-IR-12378 00 Marine    18-Feb-24 11:00 AM
2M³ (12 Pcs)

Inspection for Installation of Concrete Kerb (Type C) From sta.0+000 to


75 Kerb Installation SDMC-100-IR-12379 00 Marine    18-Feb-24 9:30 AM
0+050 at Revetment F2 (as per the attached Drawing)

Inspection for Reinforcement & Formwork and Concrete Pouring of Cast


76 Kerb SDMC-100-IR-12380 00 Marine    18-Feb-24 9:30 AM
in-situ Kerb (Type C) -No: (1) at Revetment F2