Inspections
As per applicable
Pre-pour inspections As applicable Drawing / EPCMD
1. Specification / H H H S S
(Rebar, formwork, embedded items etc.) Specification / Procedure 2QM00FMTCS014
drawing
Release for Concrete manufacture and supply As per applicable As per applicable EPCMD
2. H H H S S
(Pour Card) Procedure / Specification Specification 2QM00FMTCS015
EPCMD
Self compacting concrete :
2QM00FMTCS101
Sampling
Concrete cube sampling & testing at CMTL As per applicable As per applicable EPCMD
4. H W S -S S
(Civil Material Testing Laboratory) procedure / Specification Specification 2QM00FMTCS009 Testing-H
3
Legend: CES: Central Engineering Service - Inspection
Reliance Construction
Contractor Engineer Reliance QMD Reliance O&M / CES
Discipline Engg. Lead
Date
Name
Signature
ITP No : EPCMD 2 QM 00 ITP CS 002
Rev No : 03 Inspection and Test Plan For
Date : 16.07.2013 Structural Concrete
Sheet No : 3 of 3
Reference No(s) and Description of Area: Unit No: Serial No:
Structure(s):
Inspections
Release for structural steel / equipment As per applicable As per applicable EPCMD
9. H H S S S
erection. procedure / Specification Specification 2QM00FMTCS006
Applicable construction procedures EPCMD 3 CONS JEP CS003, EPCMD 3 CONS JEP CS014 to be followed for execution of relevant activities.
3
Legend: CES: Central Engineering Service - Inspection
Reliance Construction
Contractor Engineer Reliance QMD Reliance O&M / CES
Discipline Engg. Lead
Date
Name
Signature