DESCRIPTION OF MATERIALS QUANTITY UNIT UNIT COST TOTAL COST

1.2”X3”X12’ COCO LUMBER 115 PCS PIECE


2.2”X3”X10’ COCO LUMBER 110 PCS PIECE
3.1/2 THK PHENOLIC BOARD 18BOARDS PIECE 930 16,740
4.2” ORDINARY NAIL 10 KLS
4” ORDINARY NAIL 25kls KILO 145/kl 5,075

5. 3’’ CONCRETE NAIL 10KLS KILO 165/kl 1,650


I- FORMS AND SCAFFOLDING

TOTAL PRICE: 23,465.00 php


DESCRIPTION OF MATERIALS QUANTITY UNIT UNIT COST TOTAL COST
1.WASHED SAND 15 CUBIC CUBIC 1,450 21,750
2.3/4 GRAVEL 30 CUBIC CUBIC 1,450 43,500
3.CEMENT (FORTUNE CEMENT) 180 BAGS BAGS 265 47,700
II-CONCRETE WORKS

TOTAL PRICE: 112,950.00 php


DESCRIPTION OF MATERIALS QUANTITY UNIT UNIT COST TOTAL COST
1.16MM Ø X 6M DEF.BAR 100 PCS PIECE 392 39,200
2.12MM Ø X 6M DEF.BAR 150 PCS PIECE 264 39,600
3. NO.16 TIE WIRE 3 BANDLE BANDLE 1,800 5,400
III-STEEL WORKS

TOTAL PRICE: 84,200.00 php


PHP 220,615.00