ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
2
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
3
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
4.0 Responsibilitas
No. Designation Qty Responsibility
Responsible for overall commercial, contractual & technical performances associated with specific
1 Project Manager 1
project. Reporting to the Project Director.
2 M&E Engineer 4 Planning and supervising installation activities.
Inspect, verify, and prepare work statement for a quality installation works. Material storage, fit for use
3 QA / QC Engineer 2 tools and equipment, and installation works
To provide toolbox and guidance to work and to ensure that work is carried out in a safe manner.
4 Safety Officer 1
Obtain permit to work, control the sequence according to MOS, approved shop drawings, and MSA,
ensure mechanical aspects of the work are according to the specifications, ensure safe practices are
5 Supervisor 3-5 followed and ensure quality of workmanships during execution. Ensure material temporary storage and
protection meet vendor and standards requirement. Ensure tools being used for installation are
calibrated and meet vendor and standards requirement
6 General Workers 10-15 To carry out all the mechanical aspects of the Fire Hydrant Underground Pipe installation.
4.0 Responsibilitas
No. Designation Qty Responsibility
Bertanggung jawab atas keseluruhan kinerja komersial, kontrak & teknis yang terkait dengan proyek
1 Project Manager 1 tertentu. Melaporkan kepada Direktur Proyek.
3 QA / QC Engineer 2 Memeriksa, memverifikasi, dan menyiapkan metode kerja untuk pekerjaan instalasi yang berkualitas.
Penyimpanan bahan, alat dan perlengkapan layak pakai, dan pekerjaan pemasangan.
Untuk menyediakan kotak peralatan dan panduan untuk bekerja dan untuk memastikan bahwa
4 Safety Officer 1 pekerjaan dilakukan dengan cara yang aman.
Mendapatkan izin untuk bekerja, mengontrol urutan sesuai dengan MOS, gambar kerja yang disetujui,
dan MSA, memastikan aspek mekanis pekerjaan sesuai dengan spesifikasi, memastikan praktik
keselamatan diikuti dan memastikan kualitas pengerjaan selama pelaksanaan. Pastikan penyimpanan
5 Supervisor 3-5
dan perlindungan sementara material memenuhi persyaratan vendor dan standar. Pastikan alat yang
digunakan untuk pemasangan dikalibrasi dan memenuhi persyaratan vendor dan standar
6 Pekerja 10-15 Melaksanakan seluruh aspek mekanis pada instalasi Pipa Bawah Tanah Fire Hydrant.
5
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
6
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
Table 3: List of Plants, Machinery and Equipment Table 3: List of Plants, Machinery and Equipment
7
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
a) Complete all necessary design information and prepare all the 6.1.1 Tahap Pra-Pelaksanaan
necessary designed drawings. a) Lengkapi semua informasi desain yang diperlukan dan siapkan
b) Submission of design drawings for approval. semua gambar desain yang diperlukan.
c) Prepare all necessary shop drawings and determine the actual b) Penyerahan shop drawing untuk disetujui.
position to commence installation with the mobilization of c) Mempersiapkan semua shop drawing yang diperlukan dan
menentukan posisi sebenarnya untuk memulai pemasangan dengan
required work force, tools and equipment. mobilisasi tenaga kerja, peralatan dan perlengkapan yang diperlukan.
8
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
d) Prepare all documents required in Specification submittals and all Spesifikasi dan semua dokumen/sertifikasi yang diperlukan dalam
documents/certification required in Specification. Spesifikasi.
e) Prepare material approval document, complete with confirmation e)Menyiapkan dokumen persetujuan bahan, lengkap dengan konfirmasi
of conformance between delivered material with approved kesesuaian antara bahan yang diserahkan dengan bahan yang disetujui
material (code/model/type, length, weight, width, materials, (kode/model/jenis, panjang, berat, lebar, bahan, jumlah, dll).
quantity, etc). f) Menyiapkan konfirmasi kesesuaian antara penyimpanan sementara
f) Prepare confirmation of conformance between temporary storage dan persyaratan/standar penyimpanan vendor.
and vendor storage requirement/standard. g) Menyiapkan konfirmasi kesesuaian antara alat dan kalibrasinya
g) Prepare confirmation of conformance between tools and its memenuhi persyaratan/standar vendor.
calibration meet vendor requirement/standard. h) Memastikan semua persetujuan yang diperlukan untuk melakukan
h) Ensure all approval required to perform work are obtained and pekerjaan diperoleh dan sesuai dengan dokumen yang disetujui oleh
conform with approved documents by Consultant Engineers and Konsultan Insinyur dan Arsitek.
Architect. i) Menyiapkan JSA yang disetujui oleh petugas HSE dan memastikan
adanya pengenalan keselamatan kepada semua pekerja sebelum
i) Prepare JSA approved by the HSE officer and ensure a safety
memulai pekerjaan fisik
induction to all worker prior to commence the physical work
d) Menyiapkan semua dokumen yang diperlukan dalam penyerahan
9
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
10
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
Mapping the pipeline by using the specified coordinates shall be Pemetaan pipa dengan menggunakan koordinat yang ditentukan
specified in the Approved Shop drawing. harus ditentukan dalam shop drawing yang telah di setujui.
Conducting soil excavation by using an excavator inside that has Pelaksanaan penggalian tanah dengan menggunakan ekskavator
been determined shall be Approved shop drawing. kedalamannya yang telah ditentukan harus sesuai dengan gambar
shop drawing.
11
Excavated land must be cleaned of dirt/debris. After that, the soil Tanah galian harus dibersihkan dari kotoran/puing - puing. Setelah itu
was compacted using a compactor machine (Stemper) and dilakukan pemadatan tanah dengan menggunakan mesin pemadat
continued with backfilling with 5cm thick sand. Then the pipe is ( Stemper ) dan dilanjutkan dengan pengurukan pasir setebal 5cm.
installed in the excavated hole and inspected by the owner's Kemudian pipa dipasang pada lubang galian dan diperiksa oleh
representative, after that it is backfilled with backfill sand and perwakilan owner, setelah itu ditimbun kembali dengan pasir dan
excavated soil.Note: Use a submersible pump if the excavation is tanah galian. Catatan : Gunakan pompa celup apabila galian terndam
flooded. air.
The standard/guideline used to measure the elevation of HDPE Pedoman yang digunakan untuk mengukur elevasi pipa HDPE diukur
pipes is measured from the bottom line (BOP) to the road surface / dari rata garis bawah ( BOP) sampai dengan rata permukaan jalan /
following the agreed elevation line from the surveyor. The mengikuti garis elevasi pinjaman dari surveyor yang telah di sepakati
following is the sequence of the HDPE pipe connection process bersama. Berikut urutan proses penyambungan pipa HDPE :
Step 1: Periksa dan bersihkan pipa yang akan disambung baik dalam
Step 1: Check and clean the pipes to be connected both internally
maupun luar sehingga terbebas dari debu, minyak dan lain-
and externally so that they are free from dust, oil, etc.
lain.
12
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
Step 2: Place the pipe in the clamp where the end of the pipe is Step 2: Tempatkan pipa pada penjepit (clamp) dimana ujung pipa
facing the cutting plate, tighten until the pipe is straight. After berhadapan dengan plat pemotong, kencangkan sampai posisi pipa
making sure it is straight, place the cutting tool between the lurus. Setelah dipastikan lurus tempatkan alat pemotong diantara
two pipes, then cut both ends until they are even. kedua pipa, lalu potong kedua ujungnya sampai rata.
Step 3: Clean the remaining cuts with a clean cloth or tissue that has Step 3: Bersihkan sisa potongan dengan kain bersih atau tisu yang telah
been treated with alcohol. diberikan alkohol.
Step 4 :Place a heater between the ends of the pipe and heat the Step 4 : Pasang alat pemanas diantara ujung- ujung pipa dan panaskan
heating plate until it reaches the compound point. plat pemanas sampai mencapai titik senyawa nya.
13
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
Step 5: Connect and press both ends of the heated pipe until the Step 5 : Sambungkan dan tekanlah kedua ujung pipa yang sudah
appropriate compound pressure. dipanaskan sampai tekanan persenyawaan yang sesuai .
Step 6 : Biarkan dan tunggu sampai sambungan pipa HDPE dingin,dan
Step 6: Do the same thing for each pipe to be connected. tersambung sempurna .
14
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
Step 7: Do the same thing for each pipe to be connected. Step 7 : Lakukan hal yang sama pada setiap pipa yang akan
disambungkan.
After the pipe connection process is complete, the pipe height is Setelah proses penyambungan pipa selesai, selanjutnya
adjusted and checked according to the approved drawing. Then a partial dilakukan pengaturan dan pengecekan ketinggian pipa sesuai gambar
test (water pressure test) is carried out together with the owner's yang telah disetujui. Kemudian di lakukan partial test ( test tekanan air )
representative to ensure that there are no leaks at each HDPE pipe bersama dengan perwakilan owner untuk memastikan tidak ada
connection, and make a check report after all the processes are kebocoran pada setiap sambungan pipa HDPE nya, dan buat berita
complete, cover the excavation again with soil. acara pengecekan nya setelah semua proses selesai tutup kembali galian
dengan tanah.
6.2.2 Testing HDPE Pipe Installation 6.2.2 Pengetesan Instalasi Pipa HDPE
Hydrant pipe installations that are installed underground must Instalasi pipa hydrant yang di pasang di bawah tanah harus di
be tested, to test and determine the quality and results of each lakukan pengetesan, untuk menguji dan mengetahui kualitas dan hasil
connection. This pressure test refers to the work plan and requirements dari setiap penyambungan. Uji test tekan ini merujuk pada dokumen
(RKS) document: rencana kerja dan syarat ( RKS ) :
15
ROJECT 3RD STOREY BUILDING DATA CENTER NONGSA BATAM INDONESIA
Owner : Consultant Management : Main Contactor :
All equipment to carry out this test must be prepared, such as a Semua perlengkapan untuk melakukan pengujian ini harus
pressure pump, temporary pressure gauge connection, water hose and disiapkan seperti pompa tekan, sambungan sementara preesure gauge,
other equipment. See method and drawing follow below: selang air dan perlengkapan lainnya. Lihat cara dan gambarnya ikuti di
f. Once the pressure is reached close the filling valve. f. Periksa tiap sambungan pipa, apakah ada kebocoran.
g. Check each pipe connection for leaks. g. Pastikan tidak ada penurunan tekanan selama waktu yang telah di
h. Make sure there is no pressure drop during the agreed time. sepakati.
i. If seepage/leak occurs, empty the water in the pipe through the drain h. Apabila terjadi rembesan/kebocoran maka, kosongkan air di dalam
valve and direct the drain hose to the nearest waste point. pipa melalui katub pembungan nya dan arah kan selang
j. Make repairs to leaking connection points. pembuangan air nya menuju titik buangan air terdekat.
Re-test the pipe installation again. i. Lakukan perbaikan pada titik sambungan yang bocor.
j. Lakukan test ulang kembali pada instalasi pipa.
17
Picture 5. Pressure Test Fire Hydrant