Doc No:

DERMAGA GMS2-EXE-DER-MLNG-CVS-JMS-
MALAYSIA
OIL & GAS 0003
LNG DUA
SDN BHD MLNG Document No:
SDN. BHD

Revision: A
PROVISION OF EPCC FOR GMS1 & GMS 2 SUPERVISORY
COMPUTER AND FLOW COMPUTER UPGRADE FOR MALAYSIA Page 1 of 3
LNG SDN. BHD.

PROJECT : PROVISION OF EPCC FOR GMS1 &


GMS 2 SUPERVISORY COMPUTER
AND FLOW COMPUTER UPGRADE
FOR MALAYSIA LNG SDN. BHD.

CLIENT : MALAYSIA LNG DUA SDN. BHD.

CONTRACT NO. : DTC0BTU/MLNG/2018/38

DOCUMENT TITLE : JOB METHOD STATEMENT FOR


CABLE GLANDING AND
TERMINATION

A 26-08-19 ISSUE FOR REVIEW MSMS MAR SAAR


Prepared By Reviewed By Approved By
Discipline Technical Project
Revision Date Description Engineer Manager Manager
DERMAGA OIL & GAS SDN BHD
Doc No:
GMS1-EXE-DER-MLNG-SYS-
MALAYSIA DERMAGA OIL &
JMS-0003
LNG SDN. BHD GAS SDN BHD
MLNG Document No:

Revision: A
PROVISION OF EPCC FOR GMS1 & GMS 2 SUPERVISORY
COMPUTER AND FLOW COMPUTER UPGRADE FOR MALAYSIA Page 2 of 4
LNG SDN. BHD.

DOCUMENT REVIEW STATUS

Page 2 of 3
Doc No:
GMS1-EXE-DER-MLNG-SYS-
MALAYSIA DERMAGA OIL &
JMS-0003
LNG SDN. BHD GAS SDN BHD
MLNG Document No:

Revision: A
PROVISION OF EPCC FOR GMS1 & GMS 2 SUPERVISORY
COMPUTER AND FLOW COMPUTER UPGRADE FOR MALAYSIA Page 3 of 4
LNG SDN. BHD.

JOB METHOD STATEMENT

PC-TBA

Work Description: Cable glanding and termination

No. JOBS STEPS REMARKS ACTION


PARTY
1 Pre-Job briefing before start work Contractor

2 Approach and see a condition of work area Contractor

3 Laying cable to the area Contractor

4 Cut the cable and glanding work Contractor

5 Termination work Contractor


6 Housekeeping Contractor

Page 3 of 3