JHA For Cable Glanding and Termination REV A
JHA For Cable Glanding and Termination REV A
DERMAGA GMS2-EXE-DER-MLNG-CVS-JHA-
MALAYSIA
OIL & GAS 0003
LNG DUA
SDN BHD MLNG Document No:
SDN. BHD
Revision: A
PROVISION OF EPCC FOR GMS1 & GMS 2 SUPERVISORY
COMPUTER AND FLOW COMPUTER UPGRADE FOR MALAYSIA Page 1 of 5
LNG SDN. BHD.
Status TBA
Area MLNG
Contractors
Worksheet
No. Description of Job Step Potential Who or what might Control Measure Action Party
hazard/Risk be harmed
Mobilization
1 Mobilize / Demobilize of Traffic Accident People & Asset To provide banks-man for Work Leader &
equipment and personnel vehicle reverse, negotiate Driver
using; corner / congested road.
i) Pickup Truck Strictly comply with plant
ii) Van speed limit
Materials fall from People & Asset Materials must be secured Work Leader &
pickup and latched properly. Driver
Protruding of materials
must not be > 1m from
vehicle.
No overhanging &
overloading materials and
tools on truck.
Source of ignition People & Asset Vehicle ignition key to be Work Leader &
while entering the switch off upon hearing the Driver
process area emergency alarm
Vehicle side window to be
open - alarm sound more
clear
Vehicle must strictly
comply with the General
Traffic Rules stipulated in
MLNG Traffic & Vehicle
Regulations
Comply with PTW
requirement upon entry
into process area.
Gas test by AGT.
Road barrier is to be
opened by OPS AST only.
2 Worksite preparation Slippery, falling & People & Asset - Ensure access Work leader
tripping area clear and
clean from any
obstruction
- Ensure safety
shoe in a good
condition
- Plan safe access
3 Handling equipment / cable Pinch Point People & Asset - Wear hand glove Work leader
- Competent
Personnel only
- Always alert &
aware with pinch
point area
Slippery, falling & People & Asset - Ensure access Work leader
tripping area clear and
clean from any
obstruction
- Ensure safety
shoe in a good
condition
- Plan safe access
4 Cable Glanding Pinch Point People & Asset - Wear hand glove Work leader /
Always alert & Construction
aware the pinch Supervisor
point area
6 Cable termination Slippery, falling & People & Asset - Ensure access Work leader /
tripping area clear and Construction
clean from any Supervisor
obstruction
- Ensure safety
shoe in a good
condition
- Re-inspection by
supervisor before
leave the work
place
- Place all
equipment to
designated
storage area
Pinch Point People & Asset - Wear hand glove Work leader /
Always alert & Construction
aware the pinch Supervisor
point area
7 House Keeping Slippery, falling & People & Asset - Ensure access Work leader /
tripping area clear and Construction
clean from any Supervisor
obstruction
- Ensure safety
shoe in a good
condition
- Re-inspection by
foreman before
leave the work
place
- Place all
equipment to
designated
storage area
General Notes
Approval Status
Prepared By Contractor