TERMINAL 2
PROPOSAL
1
CONTENTS
Overview........................................................................................................................................................................ 3
Company Profile.......................................................................................................................................................... 3
Project Management.................................................................................................................................................. 5
Project Organization................................................................................................................................................... 6
This proposal is for the Bicycle Parking Area at Changi Airport terminal 2. CAG requires the
following works to be undertaken:Temporary relocation of existing bicycle racks, Pave the marked
area to match existing pavement level, Cut and install floor tiles, Painting of the new kerb to match
existing, Installation of bicycle racks.
COMPANY PROFILE
Asiapac Contracts Pte Ltd (“Asiapac”) was established in October 2012. Since then, Asiapac
has expanded our position in the market we serve. We offer a wide range of services including metal
fabrication, civil construction and electrical installations and electronics.
The people who make up the team at Asiapac embody our values of strength, performance
and passion. They have helped us to develop solutions, systems and project methods required to
bring innovation, quality and value to the projects we deliver to our clients.
At Asiapac, our core values revolve around Integrity, Transparency, Accountability and
Discipline. We demand excellence in all that we do, deliver on our promises on time and within
budget, and continuously searching for newer and better ways to provide the best solutions for our
customers. We are committed to everything that we do, especially our people, their safety and
development.
We strive to be the Contractor and Employer of choice by safely and consistently delivering
successful and innovative projects and services. Asiapac is fully committed and it is our promise to
all our clients that We Can Make It.
SCOPE OF WORK
To construct the bicycle parking area at Changi Airport Terminal 2. The work should be completed by
31 Mar 2024.
3
Bicycle parking area View
4
PROJECT MANAGEMENT
The detailed work that Asiapac will carry out for the construction of the bicycle parking area
at the key project phases is demonstrated below.
a) Planning
• Attend kick off meeting with CAG.
• Create project contact directory. This will ensure that we contact the correct person to
schedule installation date and for access into their premise on the day/night of the work.
• Conduct site survey to check interfaces with existing equipment and services.
• Conduct on-site surveys to identify safe and appropriate material delivery route(s) into the
work site.
• Work with CAG to plan alternative route and signages for airport users when areas in CAB is
hoarded up for the works.
• Refine method statement and develop risk assessment for CAG’s review.
d) Handover Phase
• Submit the document in a ring file (2 sets of paper-print and 3 CD copies) which comprises
approved shop drawings.
5
PROJECT ORGANIZATION
1. Organization structure
The following organization structure shows the project delivery team that will be involved in
this project.
Project Director
Eugene Tan
Project Manager
Adrian Tan
Safety Officer
Natarajan Dineshkumar
Team 1 Team 2
2x Technicians 2x Technicians
The project delivery team will be responsible for the following key areas of the project including:
i) Project Management – The Project Manager makes sure that the construction of the bicycle
parking Project is planned and implemented according to requirements, managing suppliers,
and coordination with CAG’s project team, in-house term maintenance contractors. He is
accountable for the project to be delivered on time;
ii.) Safety Management – All safety controls will be reviewed for compliance to the company’s
safety policies and Singapore’s workplace safety and health regulations;
iii.) Site Management – The Site Manager is responsible for overseeing the site works,
coordinating the site activities including installation, interfacing and integration works. He
will also coordinate with CAG’s representative on daily deliverables and submission of all
required permits to relevant parties.
To ensure the successful implementation of the construction of the bicycle parking area
Project that meets CAG’s requirements, our project delivery team integrates strong project
management skills with technical expertise for installation work in operational environments.
Please refer to the following pages for CVs of the key members of the project delivery team.
6
EUGENE TAN
INTRODUCTORY PROFILE
CORE COMPETENCIES
PROFESSIONAL EXPERIENCE
7
ADRIAN TAN
INTRODUCTORY PROFILE
Responsible for all aspects of site installation including setting to work, compliance to
safety regulations, implementing of permit-to-work systems, testing and trials
CORE COMPETENCIES
PROFESSIONAL EXPERIENCE
Supervise site installation team to install 521 roller castor decks, crash barriers, modify
existing roller decks and weighing machines for DHL Express Singapore Hub
Supervise site installation to install 106 CCTV cables, 24 units fiber-optic cables and 18
power cables at Changi Airport Terminal 1
Manage site installation to hack down and rebuild baggage handling system control room
in Changi Airport Terminal 1
Manage the construction of Level 4 X-ray rooms at Changi Airport Terminals 1, 2 and 3
PROFESSIONAL DEVELOPMENT
8
NATARAJAN DINESHKUMAR
INTRODUCTORY PROFILE
Passionate about safety and holding a strong belief that every worker should go home
safely at the end of the work day.
Responsible for all aspects of site safety including carrying out safety audit.
CORE COMPETENCIES
PROFESSIONAL EXPERIENCE
Ministry of Manpower (MOM) approved Safety Officer across a wide range of construction
projects from temporary structures, public facilities and residential buildings.
Experienced in managing safety in Addition & Alternation (A&A) works in high human
traffic area.
Major project holding the role of Safety Officer includes Marina One mixed-use
development show suite situated in the downtown core area, Wildlife Reserve Singapore
Night Safari Tram Station.
PROFESSIONAL DEVELOPMENT
9
INSTALLATION / CONSTRUCTION PLAN
1 Workflow Overview
To construct the bicycle parking area at Terminal 2. The work should be completed by 31 Mar
2024.
We will provide the following essential machinery and equipment that will be required for
the construction of the bicycle parking area at Terminal 2.
2.2. Palletjacks
There will be minimum 2 pallet jacks on site.
Used to transport materials within the installation areas
Plywood will be laid for the movement of palletjacks to protect the
finished surface.
10
HOUSEKEEPING AND ENVIRONMENT
1. Housekeeping
General housekeeping will be carried out during the course of the project works on a daily basis.
1. Project References
11
12
Annex A – Project Schedule and Resource Allocation
It is estimated that the entire work for the construction of the bicycle parking area at Terminal 2 can
be completed within 1 month from the contract award. Please see attached for the proposed
project schedule and resource allocation.
13