Professional Documents
Culture Documents
Introduction………………………………………………………………………………………………………………………………………………
Removal / disposal of Hazardous Substances…………………………………………………………………………………………….
Pre-requirements………………………………………………………………………………………………………………………………………
Competency & Supervision………………………………………………………………………………………………………………………..
Permit……………………………………………………………………………………………………………………………………………………….
Soft Stripping Works………………………………………………………………………………………………………………………………….
Scaffold Erection………………………………………………………………………………………………………………………………………..
Environmental Considerations…………………………………………………………………………………………………………………..
Fire Plan…………………………………………………………………………………………………………………………………………………….
First Aid……………………………………………………………………………………………………………………………………………………..
Emergency arrangement……………………………………………………………………………………………………………………………
Reporting procedure………………………………………………………………………………………………………………………………….
Risks & Controls…………………………………………………………………………………………………………………………………………
Risk Assessment & Register……………………………………………………………………………………………………………………….
Method/Risk Assessment & Site Induction Sign Off……………………………………………………………………………………………
Introduction:
This method statement details the proposed demolition method for the agreed works at the DUBAI MUSIC
INSTITUTE. The works include soft strip, scaffold erection, demolition & dismantling of doors and windows.
The site is bounded by commercial and residential premises. The site itself is contained within its own
fencing.
The access to the site is via the existing entrance & the entrance will be a timber gate door erected out of
timber hoarding.
Parking on site is heavily restricted and is advised against. All visitors are advised to call ahead of arriving to
site as site logistics are subject to change as the works progress.
PPE REQUIREMENTS
All required PPE shall be in accordance with relevant standards. The following PPE / RPE is required to be
used as per categories identified below:
Supervision:
The following details any tasks that require direct works supervision and the names of the
designated (competent) supervisors.
Before commencing demolition work shop drawing approval need to receive from consultant. After
demolition Work inspection will be submitted along with required documents for work approval.
PERMIT
Permits are used for all high-risk activities. Identified below are the
permits applicable to these works and the duration for which the permits will be issued. Permits are
valid for a Maximum of one week and are to be signed off daily by the appropriate persons.
Should any storage containers situated in the site boundary contain any liquids these will be tested and removed by a
specialist waste collector. They will pump out the liquid and take it to a treatment plant. Any hazardous liquid found
on site will be treated with the upmost care.
Spill kits will be available on site and the operatives will be trained on how to use them. Any hazardous chemicals
removed from site will have a hazardous waste note
MEP services:
All the exiting MEP services will be tested by our team, third party before commencing the demolition
works. Before proceeding demolition in particular area internal coordination will be carried out and safely
dismantle MEP services around that area. If find any unusual activity of MEP services then will be notified
concern MEP team and consultant.
Fixtures and Fittings:
Any loose fixtures and fittings remaining will where of a suitable size be removed from the building whole, taken to
the loading area by hand before being loaded directly into the waiting waste skips, larger elements will be
dismantled/downsized using small tools, reduced into manageable sized sections and again transported to the
disposal point.
Suspended Ceilings:
Any suspended ceilings will be removed via mobile scaffold tower or podium steps, tiles will be lifted and twisted
from the suspension system and lowered to the ground, from here tiles will be bundled and then be periodically
loaded into the waste skip. Suspension system will be dismantled as tiles are removed with supports cut with
croppers, the system then loaded directly into waste skip.
Doors will be removed by operatives stripping off the door furniture, the door from its hinges again utilizing pinch
bars and mattocks, doors will then be either downsized for ease of disposal or carried whole to the disposal point.
Any stud partitioning is to be removed by the operatives using suitable hand-held tools, namely pinch bars, picks and
hammers. The wall structure is to be dismantled by removing the coverings using the hammers and pinch bars. Once
exposed, the remaining stud work is to be prized free and de-nailed or have nails hammered over. Resultant arising's
are to be transported to the loading area.
Floor Coverings:
Wooden floor coverings are to be removed by the operatives using mattock picks and shovels. Carpet tiles and vinyl
floor tiles are simply to be using hand tools, then bundled and taped with resultant materials transported to the
disposal point. Carpets where of a roll-able nature will be cut into strips, whilst still laid, and then rolled up for
collection in strips, these will then be transported to the disposal point.
Any glass units and/or windows will be removed as complete units where possible, an exclusion zone/crash decks will
be employed as required and operatives will wear hard hats, safety boots, gloves and goggles. The glass will be
handled with care and placed into skips to be disposed of in a safe manner.
Fluorescent tubes:
Any fluorescent tubes are to be removed as required, they will be removed as if being changed, bulbs collected and
placed into a specialist waste coffin, this stored on site during soft strip works, removed as specialist waste once all
bulbs are removed.
In addition, any discarded, unidentified cylinders/drums/containers will be collected and tested for contamination,
these carried to a fenced off store on site, a collection of the COSHH items carried out once the buildings are cleared
by a specialist waste sub-contractor.
Soft strip materials on ground floors will be carried outside of the building and piled in their different waste streams.
A Bobcat may be utilized to remove the arisings from the ground floor. There is a large door on the ground floor on
the north east end of the building that is wide enough to allow a Bobcat to pass through. Operatives and machinery
are to be kept separate at all times.
An excavator with a selector grab will proceed to load the different piles into their bins. Once the bins are full, they
will be collected and taken to the appropriate recycling facility. Materials from the upper floors will be removed from
the building as below.
For each element following items will be considered as starting point in order to ensure that demolition works will be
carried out safely manner
SCAFFOLDING ERECTION
The scaffold will extend a maximum of 2m above the point of demolition and return onto the next elevation (where
possible) the scaffold will have diagonal bracing installed as an additional safety measure to be installed with the
scaffold.
All scaffolding will be inspected before it is used for the first time and then every 7 days, until it is removed. It will also
be inspected each time it is exposed to conditions likely to cause deterioration
All scaffolding inspection will be carried out by a competent person whose combination of knowledge, training and
experience is appropriate for the type and complexity of the scaffold to be inspected and using a visible tag system to
supplement inspection records.
ENVIRONMENTAL CONSIDERATION
Noise will be minimized by the use of modern, silenced plant, Noise monitoring equipment to be utilized
in sensitive areas as required and Operatives, contractors and visitors are to wear hearing protection in
any hearing protection zones that have been established (theses will be identified by the relevant
signage).
Dust will be minimized by the use of water spray (as required)
All reasonable measures will be taken by during construction works to prevent dirt being deposited on
the site access road and the main road. Such measures will include, but are not limited to:
Good housekeeping on site
Effective traffic management
Control of Vibration will be helped with the use of the most modern low vibration plant available in the industry
for the task will be used to reduce the level of noise emissions from machinery as far as reasonably practicable.
FIRE PLAN
A Fire and Emergency plan and Risk Assessment must be in place before works commence and inducted to all
employees and visitors. This is to be created and implemented by ORRO
Fire extinguishers suitable for the possible types of fire to be available on site.
Hot works to cease a minimum of 1 hour before end of shift for fire watch to take place.
FIRST AID
First Aid must be in accordance with the requirements of the Health and Safety (First-Aid) Regulations and must
be available prior to works starting on site.
Signage must be posted around the site of works indicating Site First Aiders and Location of First Aid boxes.
• Evaluate the risks and decide what control measures are required
For a contract such as this, we separately assess health and safety, COSHH and the Environment.
A full and thorough risk assessment will be carried out prior to any works
The following risks and control measures for the works will be;
• Fire
• Gas bottles to be chained to a proprietary trolley and placed in a cage after use. Location of gas storage cage
to be marked on the site plan and the plan located where the fire brigade can see it in the event of a site fire.
• Any hot works to be carried out under a Down well Hot Works Permit.
• Interface with the public: access and egress to be controlled by full time nominated Traffic
• Pedestrian routing to be established and maintained in accordance with Site Establishment Plan.
• Dedicated appointed banksmen to control all plant movements within site confines.
The site-specific assessments will be located within the site managers file and are made site specific by the site
supervisor for the particular work activity being carried out and to the substances to be used on the site. The below
list of risk assessments has been identified to be relevant to the works at the Avondale Square site.
Following further assessment more could be added during the duration of the project.
EMERGENCY ARRANGEMENT
Emergency Response Plans (ERP’s) are contained within a standalone document identified below and ready
in conjunction with the specific RAMS & the Construction Phase Plan (CPP), with displays placed with in
welfare areas or at workface entry points. Identified below are the relevant ERPs for the works.
REPORTING PROCEDURE
The table below is to be used to identify the activities being undertaken as part of these RAMS. Each Risk
Assessment
should detail to the control measures associated with the task to be adopted, and any residual risk rating and
likelihood remaining post control measures.
RA Order No# Risk Assessment Title RA Ref No#
1 Hand Tools - Powered
2 Hand Tools – Non-Powered
3 Dust
4 Manual Handling
5 Exhaust Emissions
6 Loading & Unloading Flatbeds & Low Loaders
7 Noise
8 Slips, Trips and Falls
9 Leptospirosis
10 Work at Height
11
12
13
Risk Matrix
Probability of Severity of Harm
Harm 1: Minor 2: Moderate 3: Serious 4: Major 5: Catastrophic
1: Improbable Low Risk Low Risk Low Risk Low Risk Low Risk
2: Remote Low Risk Low Risk Medium Risk Medium Risk Medium Risk
3: Possible Low Risk Medium Risk Medium Risk High Risk High Risk
4: Probable Low Risk Medium Risk High Risk High Risk High Risk
5: Likely Low Risk Medium Risk High Risk High Risk High Risk
Damaged equipment High Pressure Air Site Visitors Members of the Public
4. CONTROLS MEASURE
Operatives shall be trained/competent in the use of the tool required with specific training for that item,
or briefing training on manufactures instructions.
Work area is to be clean/tidy before work commences and shall be free of obstacles/trip hazards.
Electrically powered tools shall not be exposed to rain or used in wet/damp surroundings unless
they are designed and protected for this purpose.
Electrically powered tools shall not be used in the vicinity of combustible fluids, dusts or gases
unless they are specially protected and certified for the use in these areas.
Operatives shall select the correct tool for the task that they intend to perform as identified by the
manufactures instructions and refrain from overloading the tool.
PPE identified by the manufacturer’s instructions shall be worn in addition to standard site
requirements.
Ensure all cables & air lines are managed to eliminate trip hazards as far as reasonably
practicable.
Operatives shall not overreach the work area, shall avoid abnormal body postures and maintain
proper balance at all times.
Power plug & air lines to be disconnected when the tool is not in use, before servicing and when
changing blades.
Tools shall be kept clean, in good working order and adequately stored when not in use.
Tools are to be inspected once a week using the PUWER Register Document by a competent
person. And visually inspect before use for damage.
Any defects are to be reported to management immediately & recorded on inspection sheets.
Tools are to have a valid PAT Tested by a competent person.
All electrical tools are to be powered using the least amount of voltage practicable i.e. 110v.
Working hours are to be recorded on to a Hand Arm Vibration register as required.
Under no circumstances are vibration exposure limits to be exceeded.
Safety features & protective guards are to be operational & adjusted by the user before start.
All tools to be fitted with the appropriate safety features, and are set to the correct adjustment
accordingly by the user before use.
Operatives are not to intentionally miss-use or tamper with anything provided for the provision of H&S.
Pneumatic tools airlines are to be fitted with secure couplers and whip checks arrestors.
Operatives to have sufficient awareness of potential hazards such as asbestos and lead coatings.
5. RISK RATING (After Likelihood Severity Risk
Controls)
1 5 LOW
4. CONTROLS MEASURE
Operatives are to only use Hand tools having received authorization, instruction, and training from the
Site Supervisor.
Operatives shall ensure the correct tool for the task is selected.
The selected tool shall be in good working order and sufficient to carry out the task.
Operatives shall be trained in the use of the selected tool and competent to carry out the task as per
manufactures instructions.
Specific demolition tools are only to be used trained Demolition Operatives.
Toolbox talks are to be given in how to wield hand tools which require physical motion and force as
per Manufactures requirements and Manual Handling guidelines.
Operatives shall wear the appropriate PPE for the task identified by the manufacturer’s
instructions in addition to standard site requirements.
Operatives using hand tools shall be supervised by a competent person.
The work area shall be suitably free of debris/trip hazards before, during and after work has finished.
Sufficient space will be provided between and around persons using hand tools to prevent collision
or impact with others, or others using tools.
Equipment that is discovered to be faulty is to be reported to management, and removed from use.
All tools to be fitted with the appropriate safety feature and set to the correct adjustment
accordingly by the user before use.
The user is to ensure all safety features are working correctly before use.
Non-spark, Non-conductive tools to be used.
Operatives shall NOT deliberately miss-use equipment, or tamper with any mechanism provided
for safety.
RA03 DUST
1. GENERAL HAZARDS 2. GROUPS AT RISK
Dust Eye irritation SBS Employees Other Contractors
Cross contamination Public contamination Site Visitors Members of the Public
Systemic illness Dust migrating to public Young Persons Vulnerable groups
Neighboring Properties Wind/Gust migration Migrant Workers Environment
3. RISK RATING Likelihood Severity Risk
(Before Controls) 4 4 HIGH
4. CONTROLS MEASURE
So far as is reasonably practicable work methods which limit the production of dust shall be
implemented.
So far as is reasonably practicable dust shall be kept below the Workplace Exposure Limit (WEL) of
0.3 mg/m³ over a Time Weighted Average (TWA) of 8 hours.
An appropriate means of dust suppression shall be used for tasks creating dust.
Remote demolition is to be completed in it majority by muncher/grab/bucket demolition, with reduced used of
Hydraulic Breaker to reduce dust production from Hydraulic Breaking.
Clean well maintained welfare facilities shall be provided, which shall include showers for dusty works to prevent
workers from migrating dust out from the site on their persons when traveling from site.
Any on site drains will be protected to prevent the ingress of excessive silt.
Spoil heaps will be dampened down regularly to prevent gust/wind migrating dust
Tracking routes will be dampened down regularly to vehicle movements and plant tracking ‘kicking up’ dust.
Dust level monitoring shall be carried out throughout site especially at the site perimeter and records kept of this.
Operatives will be given regular health screening, which shall include lung function tests
Operatives shall be given a toolbox Talk on silicosis
Operatives shall be supplied with appropriate eye protection and respiratory protection equipment (RPE).
Operatives shall be face fitted for and trained in the use of appropriate RPE.
Clean well maintained welfare facilities shall be provided, which shall include showers for dusty works.
So far as is reasonably practicable hand-held tools/equipment shall be fitted with dust capture systems.
Waste materials shall be removed on a regular basis to prevent dust-spread.
All dust generating Activities are to be Supervised.
RA07 NOISE
1. GENERAL HAZARDS 2. GROUPS AT RISK
Hearing loss/damage Imped communication SBS Employees Other Contractors
Tinnitus Disorientation Site Visitors Members of the Public
Headaches Nuisance Young Persons Vulnerable groups
Nausea Disrupts wildlife Migrant Workers Environment
3. RISK RATING Likelihood Severity Risk
(Before Controls) 4 5 HIGH
4. CONTROLS MEASURE
Noise levels shall be assessed prior to work commencing which can be obtained from
manufactures guidance for equipment.
In the event that noise levels are above the low action limit of 70dbA, hearing protection plugs
and/or ear defenders will be provided.
In the event that noise levels are above the exposure limit of 75dbA, where possible
plant/machinery shall be placed inside an enclosure to reduce noise levels.
In the event of noise levels being above the higher exposure limit of 85dbA – the works are to be re-
assessed to reduce the noise levels to the low level.
Where hearing protection PPE is required to be worn signage shall be put in place to enforce this & to
warn persons that they are entering an area of high noise level exposure.
Health surveillance shall be provided for all operatives who work continually in high noise areas.
Job rotation to be employed to limit exposure.
Noise level monitoring shall be carried out around the site perimeter and within the site boundary
and via portable hand-held devices to gauge point of work emissions.
Placing loud machinery, a good distance away from operatives and sensitive neighbors.
Providing training and information to operatives who may encounter loud noise risk areas via TBT’s.
Provision of PPE either in the form of ear defenders or in-ear plugs shall be available to operatives
whilst on site regardless of noise levels if they request it.
Setting up screens and barriers to deflect sound away from working areas.
Ensuring that equipment is securely fixed or on noise dampening mats to prevent additional noise from
vibration.
Equipment shall be maintained at regular intervals to ensure compliance with section 60/61
requirements.
Methods of communication such as hand signals to be utilized by staff operating in areas of high noise
or where noise may affect communication.
Contract: Date:
Site Address:
Reference: Revision:
Site Induction/Briefing given by