The document outlines the contractor's responsibilities during the Defects Liability period. The contractor must complete any outstanding work, address any notified defects or damages before the period expires, and remedy defects at their own cost if caused by their design, materials, workmanship, or failure to meet obligations. If defects are caused by other reasons, the contractor must be promptly notified and the variation procedure will apply to determine costs.
The document outlines the contractor's responsibilities during the Defects Liability period. The contractor must complete any outstanding work, address any notified defects or damages before the period expires, and remedy defects at their own cost if caused by their design, materials, workmanship, or failure to meet obligations. If defects are caused by other reasons, the contractor must be promptly notified and the variation procedure will apply to determine costs.
The document outlines the contractor's responsibilities during the Defects Liability period. The contractor must complete any outstanding work, address any notified defects or damages before the period expires, and remedy defects at their own cost if caused by their design, materials, workmanship, or failure to meet obligations. If defects are caused by other reasons, the contractor must be promptly notified and the variation procedure will apply to determine costs.
11.1 Completion of Outstanding Work and Remedying Defects
The main points outlined are: - The contractor is responsible for ensuring that the works and documents meet the contract requirements by the end of the Defects Notification Period or shortly thereafter. - The contractor must complete any outstanding work specified in a Taking-Over Certificate within a reasonable time instructed by the Engineer. - The contractor must address any defects or damages notified by the Employer before the expiry of the Defects Notification Period. - The contractor must be promptly notified of any defects or damages by the Employer or on behalf of the Employer. 11.2 Cost of Remedying Defects The main points outlined are: - The contractor is responsible for executing any work related to remedying defects at their own risk and cost if it is attributable to: (a) Any design for which the contractor is responsible, (b) Plant, materials, or workmanship not complying with the contract, or (c) Failure by the contractor to fulfill any other obligation. - If the work is attributable to any other cause, the contractor must be promptly notified by the employer or on their behalf, and the Variation Procedure outlined in Sub-Clause 13.3 shall apply.