PROJECT AREA 3001 – STEPHENSON AVENUE

BIM Service & Extraction of Cast-in items Quantity for bridge Segments

BIM Consultant

1 2023.10.31 First Issue AWR GSH MRH


Rev Date Description Prepared Checked Approved

1
Contents

1. Scope of Works..............................................................................................3

2. Software Used................................................................................................4

3. Modeling Element details..............................................................................4

4. Exclusions.......................................................................................................5

1. Scope of Works

Understanding the Scope of Works:

2
1. Upgrade the Existing bridge segment model against the latest design package information
[LOD 200 to LOD 300].

Bridge Name No of Segment

BR1400 6

BR1903 4

2. All temporary elements have to be modelled in LOD 400 from scratch using the latest
temporary design drawings for the base plate and bolts (ferrules) that connect the
permanent structure. For other elements, modeling in LOD 300. Refer to the below images
for an understanding of temporary elements.

3. Identify the clashes between segment model and temporary model elements and list out the
clash report.

4. Extraction of quantity of cast-in items, like ferrules, base plates, connections plates, and
bolts for temporary & Permanent elements.

2. Software Used

a) Autodesk Revit (2023)


b) Excel -2023
3
3. Modeling Element details
The following model elements are considered for the development of 3D models. refer below images.

Permanent cast in items

Temporary cast in items

4
4. Exclusions
a) Steel Modelling for Fabrication drawing
b) Rebar modelling
c) 4D & 5D Process
d) BOQ Extractions from model.