List of RFA/RFI for COMMENT/APPROVAL/UPDATE

March 6, 2024
Days Days
Date Submitted Date Submitted
RFI/RFA Number: Description: Running Running Remarks:
to RMC to JSLA
(RMC): (JSLA):

/STRUCTURAL/
QDST: PARTIAL approvd 8flr to 9flr
RFA-SD-S-025A Proposed Beams & Girders Cutting List (8F-SD Level) 7-Jul-23 243 (1/19/24 PARTIAL APPROVED 10,11,12 FLOOR,
8 AND 9 FLOOR RESUBMIT)

advance copy emailed to JSLA 7-05-23


RFA-SD-S-026A propose slab cutting list (2f to sd level) 5-Jul-23 5-Jul-23 245 245
QDST: PARTIAL 2F, 3F, 4F, 5F, 6F, 7F, 8F
RFA-SD-S-153 PROPOSED CANOPY FRAMING (PAMCORE STEEL) 29-Feb-24 29-Feb-24 6 6

RFI-S-029 REQUEST FOR SLAB DETAILS ON 10TH & 13TH FLOOR 29-Feb-24 29-Feb-24 6 6

/ARCHITECTURAL/
RFA-MET-A-007 PROPOSED METHODOLOGY ON GAP BETWEEN STAIR 1 & CHB 4-Mar-24 4-Mar-24 2 2

PROPOSED METHODOLOGY ON GAP BETWEEN COLUMN AND CHB OR


RFA-MET-A-008 4-Mar-24 4-Mar-24 2 2
SHEARWALL AND CHB
PROPOSED CORRECTION METHODOLOGY FOR MIS-ALIGNED PRECAST
RFA-MET-A-009 4-Mar-24 4-Mar-24 2 2
WALL @ 7F

RFA-MAT-A-028 PROPOSED OPTIMASTIK PU2KHT WATERPROOFING 4-Mar-24 4-Mar-24 2 2

RFA-SD-A-035 PROPOSED USE OF 6IN THK CHB FOR LUSG ROOM 4-Mar-24 4-Mar-24 2 2
REQUEST FOR APPROVAL OF DETAILED PLAN OF METAL FLUSH DOOR AND
RFA-SD-A-026A 5-Mar-24 5-Mar-24 1 1
LOUVER DOOR ( FIL ASIA GLASS)

/CSD/

/ELECTRICAL/
RFA-SD-EE-014 PROPOSED LOCATION OF F-ADMIN AND MC-SHOP AT 2F LVSG ROOM 21-Dec-23 21-Dec-23 76 76

/FIREPRO/

/PLUMBING SANITARY/
RFA-SD-PS-014 PROPOSED LAYOUT OF ADDITIONAL DRAIN @ 7TH FLOOR 2-Mar-24 2-Mar-24 4 4

/MECHANICAL/
RFI-ME-002 EXHAUST FAN AT GF TOILET & PUMP ROOM 4-Mar-24 4-Mar-24 2 2

/ACCELEROGRAPH/
RFA-SD-ACC-003A PROPOSED SD & LOCATION OF ACCELEROGRAPH 6-Mar-24 6-Mar-24 0 0

Legend
Font color: Tab Color:
Black Newly submitted Less than 7days Partial
Green Partially approved (JSLA & QDST signed)
Purple QDST commented
Red 7 days up running days