System Logistics JSA 1
System Logistics JSA 1
4.1Logistic plan to be prepared- Routs marked for transport vehicle and flag
man to be appointed for vehicle movement in standard speed 15Kph.
1.1. Should take all Necessary work permits to perform this job.( lifting and
shifting work permit).
1.2. Farana, Tools and tackles must be inspected before start the work by the
safety officer.
1.3 Trained/competent person should perform this working activity.
1.4 Lifting tackles and MHE should have valid TPIC and must be inspected
physically before start the work.
2. Team work required when unloading material with proper PPE's to be worn
with shoulder pad.
3.1 . Material handling safety to be followed.
3.2 . Sorrounding area to be free from traffic and person movements.
4. Dedicated supervision to be provided.
1.Fall of Material, material damage 4.2. Always check for load balance, and clear a pathway before movement.
2.Hand cut injury. 5. Area should be barricaded, placed related signages and must not allow any
3.Body Injury. one under the load.
4 Material Unloading by farana (weight)
4.Load Collapse. 5.1. Materail should not be stacked on slope.
5.Hit near structure. 5.2.Maintain proper Space between beside stacking materail. Stack materail
6.Overhead Electrical Power Cables should be stable enough to prevent collapsing.
5.3. At time, surroundings can grow noisy, or a voice may simply not be heard
over distance. Establish hand signals.
5.4. Deploy signal man/flag man to guide the operator.
5.5. provide guide line rope both side of load to guide.
6.1. contact to the authorized person and shutdown the power and applying
LOTO, and give the proper PPE's.
6.2 Consider to all lines to be live and dangerous.
6.3 Always maintaine a safe distance at leat 10 feet from overhead power
lines.
6.4. Display Safety Sinages place at site.
6.5 Lifting plane will be summitted before start the work (weight 500 kg
above).
2.2. Stand close to object, with feet solid and shoulder-width apart. Do not
reach over an obstacle to lift the load. Move whatever is in your way.
2.3. Squat down, bending your knees. Keep your back straight and upright.
1. Crush Injury
2.4. Grip the object firmly and pull it close to you.
6 Performing the Lift by manually 2.Back Injury
2.5. Tighten your abdomen.
3. foot Injury
2.6. Lift with your legs in a gradual and smooth movement. Keep your back
straight. Keep the load close to your body.
2.7. Do not twist your body while lifting.
1.store heavy and unstable materail as low as possible to the floor. Keep the
assembling conveyor not more than 3 feet, Stacking should not done on
slope. 1.2.
ensure the material tied with rope and use safety shoes while working.
2. Job rotation to be done at some interval of time, carry the load as possiable
1. Foot crush as close to the body twisting,turning,bending of back should be avoided
2. Ergonomical hazards 3.1. Use of hand cut resistance gloves
10 Material stacking by Farana , HOPT 3. Sharp edges,cuts, Freacture
3.2. Proper barricade should be provided, unauthorised person shouldn't
4. Back injury. allowed material stacking area.First aid measures should be available at site.
4.
Always ensure enough manpower to lift material. Job rotation to be done at
some interval of time And refer SOP for safe lifting and handling of material.
5. Farana should have valid TPIC and must be inspected physically before
start the work.
At Finishing
(1). Ensure work area clean from obstacle / waste/wet/equipment.
(2). Ensure all tools & equip. savely in place container.
- Scrach on sharp object (3). Ensure personel avoid pinch point, area hazard potensial slip trip and fall.
13 Housekeeping
-Domestic waste (4). Follow customer waste disposal and management plans
(5). Personnel use PPE properly (Safety Shoes, Body Vest, Gloves, Mask,
Helmet).
Contarctor Safety Officer Contractor Site Engineer FABS Engineer FABS EHS Incharge CMC EHS Manager HCCB Project Manger HC
Responsibility
Site Engineer
Site Engineer
Site Engineer
Site Engineer
Site Engineer
Site Engineer
Site Engineer
Site Engineer
Site Engineer
Site Engineer
Site Engineer
Site Enginner
Site Enginner
At Mechanical Installation
1.1. Should take all Necessary work permits to perform this job.( lifting and shifting work
permit).
1.2. Farana, Tools and tackles must be inspected before start the work by the safety
officer.
1.3 Trained/competent person should perform this working activity.
1.4 Lifting tackles and MHE should have valid TPIC and must be inspected physically before
start the work.
2. Team work required when unloading material with proper PPE's to be worn with
shoulder pad.
3.1 . Material handling safety to be followed.
3.2 . Sorrounding area to be free from traffic and person movements.
1. Unsafety Farana and Driver 4. Dedicated supervision to be provided.
2. Material drop 4.2. Always check for load balance, and clear a pathway before movement.
Unloading conveyor and electrical cabinet
3. Struck by farana moving around 5. Area should be barricaded, placed related signages and must not allow any one under
1 (use Farana) Site Engineer
4. Farana overload the load.
Conveyor Weight 350 kg
5. Cut the Slings.( Damage Sling, Kinking, 5.1. Materail should not be stacked on slope.
Heat damage fitting). 5.2.Maintain proper Space between beside stacking materail. Stack materail should be
stable enough to prevent collapsing.
5.3. At time, surroundings can grow noisy, or a voice may simply not be heard over
distance. Establish hand signals.
5.4. Deploy signal man/flag man to guide the operator.
5.5. provide guide line rope both side of load to guide.
6.1. contact to the authorized person and shutdown the power and applying LOTO, and
give the proper PPE's.
6.2 Consider to all lines to be live and dangerous.
6.3 Always maintaine a safe distance at leat 10 feet from overhead power lines.
6.4. Display Safety Sinages place at site.
6.5 Lifting plane will be summitted before start the work (weight 500 kg above).
1. Working area should be barricaded, and housekeeping should be done on daily basis.
2. Trained work man should perform this job.
1. Slips, Trips & Falls 3. must be worn all appropriate ppes
2. Crush Injury 4. HOPT should inspect before start the work and maintain check list.
Material shifting by help of HOPT( Hand 3.
2 Site Engineer
Operated Pallet Truck) load collapse 5. Area should clear and maintain good housekeeping
4. machanical failure 6. Load shall be Tie with reachat belt to avoide load collapse.
7. Ensure load object identified weight capacity and dimension, safety capacity load 75%
(SWL).
1) Used of job specific PPE.( Safety helmet, goggle(splash), Nose Mask, ear plug).
2.1) Use of splasj goggles and Hand gloves while injecting chemical into Anhoring hole.
2.2) Follow SDS for Diposbale method for empty Cartridges and Diposbale Plan.
2.3) Trained workers should be allowed for Grouting Chemical anchoring work
2.3) Before use the power tools, ensure all the tools using for Grouting is in good
condition.
1) Dust Allergy,
Chemical Anchoring (use by Machines 2.4) Follow Safe work pratice for chemical/Mortar Anchoring and ensure that the empty
6 2) Contact with skin and eyes, Site Engineer
Gun). cartridge are stored in the Specified location/Place
3) Envirnment hazard
Construction of cable ducts and conduits 1.1 Only authorised and trained person should be allowed to work.
1 Use portable electric power tools and 1.2. Install Barricade Sign & avoid area potential slip trip and fall & injury.
electrical equipment 1.3 Personnel use PPE properly and working with awareness.
2.1. Proper cable keep neatly
1.1. Sharp Object from edge of Tray and 2.2. Cable tray should making work only competent person.
Conduit 2.3. Should have more frequent checks for items more likely to become damage
2. Slip, Trip, Fall, Sratch 2.4. Close supervision is required.
3. Electrical shock due to plug or connector is 2.5. To implement safety checklist before commencing of work.
Site Enginner
damaged. 3.1. Monthly tagging system to be followed.
4. Use of incorrect power tools 3.2. Only trained and experienced person are allowed
Laying cable and wiring (Main power cable 3.3. Ensure any electrical equipment brought into the workplace by workers, is suitable for
2 is connected to main electrical cabinet by use.
Customer) 3.4. Hand held power tools should be insulated
4.1. Disc/wheel RPM should be more than power tools RPM.
4.2. Face shield/goggle shall be worn while working
4.3. All equipment will be routed through 30 mA RCCB
(1.1). Authorized personnel working competences and all related documents will be
submitted.
(1.2). Personnel use PPE properly and working with awareness.
(1.3). ELCB of 30 mA must be installed on electrical boards.
(1.4). Earthing must be provided.
(1.5). Rubber mat must available working near to DB panel.
(2.1). Authorized personnel working competences.
1.Electrical Shock
(2.2). Always mark your position particularly in blind spots and only move through
Circuit test (Check electrical and 2.Struck by Shuttle and pallets moving
pedestrian areas, if any; in the event of insufficient lighting, use high visibility clothing.
3 mechanical working properly) around Site Engineer
(2.3). Signal any operation faults of sensors to the person in charge of the System Logistics
Testing Automation 3.Risk of entanglement in moving mechanical
worksite and to the Customer’s personnel.
parts
(3.1). Use of pedestrian paths
(3.2). Correct segregation procedure and access prohibited to non-authorised persons near
machines being tested or checked
(3.3) PTW system should be followed.
(3.4) Working area should be barricaded.
(3.5) Provide appropriate signboards.
(3.6) Work should be carried out under the supervision.
At Finishing
Contarctor Safety Officer Contractor Site Engineer FABS Engineer FABS EHS Incharge CMC EHS Manager HCCB Project Manger HCCB EHS Manager
PROJECT NAME:HCCB TELANGANA GREEN FIELD
At Mechanical Installation
1.1. Should take all Necessary work permits to perform this job.( lifting and shifting work
permit)
1.2. Farana, Tools and tackles must be inspected before start the work by the safety officer.
1.3 Trained/competent person should perform this working activity.
1.4 Lifting tackles and MHE should have valid TPIC and must be inspected physically before
start the work.
2. Team work required when unloading material with proper PPE's to be worn with shoulder
pad.
1.Fall of Material, material damage 3.1 . Material handling safety to be followed.
1. Unloading FRS shuttles and Rails 2.Hand cut injury. 3.2 . Sorrounding area to be free from traffic and person movements.
1 Material. ( Use of Cranes and Farana). 4. Dedicated supervision to be provided. Site Enginner
FRS Shuttels Weight 150 kg. 3.Body Injury. 5. Area should be barricaded, placed related signages and must not allow any one under the
4.Load Collapse. load.
5.Hit near structure. 5.1. Materail should not be stacked on slope.
5.2.Maintain proper Space between beside stacking materail. Stack materail should be stable
enough to prevent collapsing.
6. Deploy signal man/flag man to guide the operator.
6.2.Material handling safety to be followed.
6.3. provide guide line rope both side of load to guide. Lifting plane will be summitted before
start the work (weight 500 kg above). HOPT or Fork lift to be provided while Unloading
material when required.
1.1. Should take all Necessary work permits to perform this job.( lifting and shifting work
permit)
1.2. Farana, Tools and tackles must be inspected before start the work by the safety officer.
1.3 Trained/competent person should perform this working activity.
1.4 Lifting tackles and MHE should have valid TPIC and must be inspected physically before
start the work.
2. Team work required when unloading material with proper PPE's to be worn with shoulder
pad.
3.1 . Material handling safety to be followed.
1.Fall of Material, material damage
Lifting and Insertion of FRS shuttles( use 3.2 . Sorrounding area to be free from traffic and person movements.
2.Hand cut injury.
2 by Farana). 4. Dedicated supervision to be provided. Site Enginner
3.Body Injury.
FRS shuttels Weight 200 kg 5. Area should be barricaded, placed related signages and must not allow any one under the
4.Load Collapse.
load.
5.Hit near structure
5.1. Materail should not be stacked on slope.
5.2.Maintain proper Space between beside stacking materail. Stack materail should be stable
enough to prevent collapsing.
6. Deploy signal man/flag man to guide the operator.
6.2.Material handling safety to be followed.
6.3. provide guide line rope both side of load to guide. Lifting plane will be summitted before
start the work (weight 500 kg above). HOPT or Fork lift to be provided while Unloading
material when required.
(1). The cable to Insert cable tray smoothly and avoid the sharp object.
(2). Personnel must wear correct PPE properly and working with awareness.
Circuit test (Check electrical and (3). Authorized personnel working competences.
3 1.Electrical Shock (4). Make sure all connection installations are in accordance with the electrical drawing and Site Enginner
mechanical working properly)
confirmed.
(5). Use the right PPE and tool to carryout your work (Helmet, Work Uniforms, Safety
Glasses, Safety Shoes, Gloves, etc.). Ensure high voltage gloves are ready.
(1.1). Authorized personnel working competences and all related documents will be
submitted.
(1.2). Personnel use PPE properly and working with awareness.
(1.3). ELCB of 30 mA must be installed on electrical boards.
(1.4). Earthing must be provided.
(1.5). Rubber mat must available working near to DB panel.
1.Electrical Shock
(2.1). Authorized personnel working competences.
2.Struck by Shuttle and pallets moving around
4 Testing Automation (2.2). Always mark your position particularly in blind spots and only move through pedestrian Site Enginner
3.Risk of entanglement in moving mechanical areas, if any; in the event of insufficient lighting, use high visibility clothing.
parts
(2.3). Signal any operation faults of sensors to the person in charge of the System Logistics
worksite and to the Customer’s personnel .
(3.1). Use of pedestrian paths
(3.2). Correct segregation procedure and access prohibited to non-authorised persons near
machines being tested or checked
At Finishing
Contarctor Safety Officer Contractor Site Engineer FABS Engineer FABS EHS Incharge CMC EHS Manager HCCB Project Manger HCCB EHS Manager
PROJECT NAME:HCCB TELANGANA GREEN FIELD
At Mechanical Installation
(1.1). Pre-start inspection of crane mechnical and electrical integrity, specification and capacity.
(1,2). Only licensed & qualified operator to drive crane.
(1.3). All material must be stored in areas agreed on with the Customer.
(1.4). Ensure the route operation and procedures.
(1.5). Lift the load only to the minimum indispensable height
(1.6). Install baricade for loading and unloading machine.
(1.7). Personnel must wear correct PPE and working with awareness.
1. Unsafely Crane and Driver (2.1). Make sure the machine parts when lifted there is a safety (locked) / tied rope.
Unloading movimentation and lifting
2. Material drop (2.2). During lifting no personnel around the crane.
1 Elevator (use Crane/Farana) Site Enginner
3. Struck by cranes moving around (2.3). Personnel use PPE properly and working with awareness.
Weight 400 kg
4. Crane overload (2.4). Ensure the route operation and procedures.
(2.5). Ensure object forklit and cranes not over weight or heght and didn’t bloking view operator.
(3). Always mark your position particularly in blind spots and only move through pedestrian areas, if any; in the
event of insufficient lighting, use high visibility clothing.
(4.1). Personnel use PPE properly and working with awareness.
(4.2). Pre-use inspection check forklift mechnical electrical integrity, specification and capacity.
(4.3). Ensure Load object Identified weight capacity and dimension, safety capacity load 75%.
(4.4) Lifting plane will be summitted before start the work (weight 500 kg above).
Identifying the position of elevators at (1.1.). Personnel must hi visibility PPE and working with awareness.
2 1. Running over by forklift trucks or other moving vehicle o Site Enginner
the worksite (1.2). Always mark your position particularly in blind spots and only move through pedestrian areas
1.1. Keep the work area tidy • Use PPE to protect lower limbs
3 Checking material at worksite 1. Tripping, falling to the ground, impact against material 1.2 Pre-use inspection check the driller (brace and bit). Electricity and mechanical. Site Enginner
1.3. Correct PPE must be worn to protect lower limbs
1.1. Should take all Necessary work permits to perform this job.( lifting and shifting work permit)
1.2. Farana, Tools and tackles must be inspected before start the work by the safety officer.
1.3 Trained/competent person should perform this working activity.
1.4 Lifting tackles and MHE should have valid TPIC and must be inspected physically before start the work.
2. Team work required when unloading material with proper PPE's to be worn with shoulder pad.
3.1 . Material handling safety to be followed.
1.Fall of Material, material damage 3.2 . Sorrounding area to be free from traffic and person movements.
Erection of Elevator mast by 2.Hand cut injury. 4. Dedicated supervision to be provided.
5 Site Enginner
Crane/Farana 3.Body Injury. 5. Area should be barricaded, placed related signages and must not allow any one under the load.
4.Load Collapse. 5.1. Materail should not be stacked on slope.
5.Hit near structure. 5.2.Maintain proper Space between beside stacking materail. Stack materail should be stable enough to prevent
collapsing.
6. Deploy signal man/flag man to guide the operator.
6.2.Material handling safety to be followed.
6.3. provide guide line rope both side of load to guide. Lifting plane will be summitted before start the work
(weight 500 kg above). HOPT or Fork lift to be provided while Unloading material when required.
1) Allow only valid licence holder operator to operate vehicle.
2) Operator / Driver should be aware about the HCCB and Project Safety Guideline.
3) All necessary documents should be ensure as per HCCB requirement - Lifting tools and vehicle examination
form, TPI, Insurance.
4) Alcoholic person strictly prohibited.
5) Trained Signal Man to be deployed.
6) Mobile phone not be allowed to driver or operator while driving.
1) Slip, trip
7) Vehicle mechanical and hydraulic part condition and working to be inspect.
2) Sharp edges
8) Before start the work inspect all lifting tools such as D shackles, Bow shackles, Web slings, wire rope slings,
3) Load Hitting to plant facility
crane wire rope, crane hydraulic parts, limit switch, level indicator is in working, siren or horns is working.
4) Fall hazard
Erection of Elevator mast by moble 9) Operator should have a clear view of the road.
6 5) Over Loading Site Enginner
crane/Farana(Tailing Lifting) 11) Ensure the work area or access is even to avoid toppling of crain.
6) Vision block
12) Material should be lift as per shape, size and weight.
7) Lifting tools, Machanical failure
13) Work should be carried out as per the submitted lifting plan / Method statement(above Weight 500 kg).
8) Uncontrolled load, Suspended load
15) Enclosed supervision should be provided.
9) Improper rigging, Improper Signalling
16) Guide rope should be provided.
17) Ensure no one be enter below suspended load.
18) Make sure load should not be suspended for long-time.
19) Area should be barricaded and display appropriate signage.
20) PPE's to be provided - Full Body Safety Harness to be provided while installing lifting tools.
23) Trained riggers should be deploy
24) Proper communication should be maintained between riggers and operator and flagman.
1. must worn all appropriate PPE's like Goggles, Gloves,Steel toe Shoes,Safety Helmet and Safety vest.
1.Fall of person 2. Trained person must access the height by using full body safety harness with double lanyard.
7 Removing of web sling rope/belt Site Enginner
2. Fall of tools equipment 3. FBH must be anchorage at differant place and maintain 3 point contact while removing belt.
4. FBH must be inspected and have valid TPI, maintain record.
1. Ensure inspect the tools and tackels before start the work, and Training should be provided at all.
2.1. Ensure personnel avoid of sharp object area.
2.2. Personnel must wear correct PPE properly and working with awareness.
2.3. Ensure the personnel good comunicate and cooperate.
1. Fall of material and person
3.1. Ensure the unit installation based on drawing step.
2. Scrach on sharp object
8 Accessories mounting 3.2. Use key / special tools that fit with the machine's needs. Site Enginner
3. Crushing by material
3.3. Attention to the pinch point area.
4. Struck by farana moving around
(4). Personnel must wear correct PPE properly and working with awareness
4.1. Ensure the route operation and procedures.
4.2. Ensure object cranes and hoists not over weight or height and didn’t bloking view operator.
4.3. Personnel must wear correct PPE properly and working with awareness
At Finishing
Contarctor Safety Officer Contractor Site Engineer FABS Engineer FABS EHS Incharge CMC EHS Manager HCCB Project Manger HCCB EHS Manager
PROJECT NAME:HCCB TELANGANA GREEN FIELD
Nature of JOB : Unloading, Lifting and Shifting of SVL Date : 05/12/2023 JSA NO : 197
and Rail with the help of Farana
Name of the Contractor : System Logistics Location: Banda Timmapur
Name of Safety Officer : Mr. Mohd Rihan Contractor Project Engineer : Mr. Ashwanth kumar
SL .NO Sequence of Job / Job Steps Potential Hazard Recommended Control Measures Responsibility
At Mechanical Installation
1.1 Pre-use inspection check farana mechnical electrical integrity, specification and capacity.
1.2. Only qualified & licensed driver must operate farana and cranes.
1.3 All material must be stored in areas agreed on with the Customer.
1.4 . Ensure the route operation and procedures.
1.5. Lift the load only to the minimum indispensable height
1.Unsafety Farana Crane and Driver 1.6. Install baricade for loading and unloading machine.
2. Material drop 1.7 Personnel must wear correct PPE properly and working with awareness
1 Unloading SVL Shuttles and Rails Material. ( Use of 3. Struck by moving Farana/Cranes 2.1. Make sure the machine parts when lifted there is a safety (locked) / tied rope. Site Enginner
Cranes and Farana) 4. Farana/Crane overload 2.2. During lifting no personnel should be around the farana.
3.1. Ensure the route operation and procedures.
3.2. Ensure object on Farana or Cranes is not over weight or too high and blocking the view of operator.
3.3. Always mark your position particularly in blind spots and only move through pedestrian areas, if
any; in the event of insufficient lighting, use high visibility clothing
4.1.Pre-start inspection must be completed to check farana and cranes mechnical and electrical
integrity, specification and capacity.
4.2. Ensure Load object Identified weight capacity and dimension, safety working load(SWL) 75%
(1). Personnel must wear PPE properly and working with awareness
1. Slip, Trip, Fall, Scratch (2). Ensure all permit for hot work / Welding activities are in place
2 Installation of Rails 2. Welding , hot work 2.1. Personnel must use proper PPE for the welding operation (Shields, Gloves, etc.) Site Enginner
2.2. Area below and nearby must be properly isolated and access closed/limited.
1) Used of job specific PPE.( Safety helmet, goggle(splash), Nose Mask(as per N95), ear plug).
2.1) Use of splasj goggles and Hand gloves while injecting chemical into Anhoring hole.
2.2) Follow SDS for Diposbale method for empty Cartridges and Diposbale Plan.
2.3) Trained workers should be allowed for Grouting Chemical anchoring work
1) Dust Allergy, 2.3) Before use the power tools, ensure all the tools using for Grouting is in good condition.
2) Contact with skin and eyes, 2.4) Follow Safe work pratice for chemical/Mortar Anchoring and ensure that the empty cartridge are
4 Chemical Anchoring (use by Machines Gun). stored in the Specified location/Place Site Engineer
3) Envirnment hazard
2.5) Portable eye washer to be provided at site location.
2.6) Fire point provision at the storage area.
3.1. Spill kit at the storage area, secondary conataminant.
3.2. Material handling procedure to be followed as per SDS
(1). Pre-use inspection check lifing equipment mechnical electrical integrity, specification and capacity.
(2). Only qualified & licensed driver must operate forklift and cranes.
(3). All material must be stored in areas agreed on with the Customer
6 Lifting and Insertion of SVL shuttles 1. Unsafely Farana, Crane and electrical/Mechani(4). Ensure the route operation and procedures. Site Enginner
(5). Lift the load only to the minimum indispensable height
(6). Install baricade for loading and unloading machine.
(7). Personnel must wear correct PPE properly and working with awareness
1.Ensure that proper safety gears is used. These include safety shoes,helmet,rubber electrical gloves,
rubber mat, fire extinguisher.
2.Person should be well experienced who is doing the work.
3.Do the LOTO procedure to the incoming supply panel by only authorized person.
4.Proper illumination should be provided at work place.
5.Keep the first aid box near to the work place.
1. Live Circuit 6. Employee should be trained with safe electrical working procedure.
3 Circuit test (Check electrical and mechanical working prope2. Electrical Shock 7.Proper ground earthing should be provided to the overall electrical equipment. Site Enginner
8.Work should be done under continuous supervision.
9.Before starting any test, make the proper plan including a circuit diagram for the test.
10.Be very care fully while using certain test equipment’s like meggers,earth tester, multimeter.
11. When the working with unfamiliar equipment read the operating manual carefully before starting
the work.
12.Ensure that the electrical work permit is taken from authorized person for the work.
(1.1). Authorized personnel working competences and all related documents will be submitted.
(1.2). Personnel use PPE properly and working with awareness.
(1.3). ELCB of 30 mA must be installed on electrical boards.
(1.4). Earthing must be provided.
(1.5). Rubber mat must available working near to DB panel.
(2.1). Authorized personnel working competences.
1. Electrical Shock (2.2). Always mark your position particularly in blind spots and only move through pedestrian areas, if
2. Struck by Shuttle and pallets moving around any; in the event of insufficient lighting, use high visibility clothing.
4 Testing automatic mission 3. Risk of entanglement in moving mechanical (2.3). Signal any operation faults of sensors to the person in charge of the System Logistics worksite and Site Enginner
parts to the Customer’s personnel .
(3.1). Use of pedestrian paths
(3.2). Correct segregation procedure and access prohibited to non-authorised persons near machines
being tested or checked
(3.3) PTW system should be followed.
(3.4) Working area should be barricaded.
(3.5) Provide appropriate signboards.
(3.6) Work should be carried out under the supervision.
At Finishing
Contarctor Safety Officer Contractor Site Engineer FABS Engineer FABS EHS incharge CMC EHS Manager HCCB Project Manger HCCB EHS Manager