PROJECT NAME:HCCB TELANGANA GREEN FIELD

Nature of JOB : Material Unloading, Lifting, Date : 14/12/2023 JSA NO : 197


Shifting By the help of Farana
Name of the Contractor : System Logistics Location: Banda Timmapur
Name of Safety Officer : Mr. Mohd Rihan Contractor Project Engineer : Mr. Ashwanth Kumar
SL .NO Sequence of Job / Job Steps Potential Hazard Recommended Control Measures

1. Trained, competent and experienced workers should be deployed.


2. Ensure competency certificates.
3. Workers above 21 years and below 50 years of age are only allowed for
height work after passing vertigo test.
4. Pre entry medical check - up should be done. Vertigo test to be done for
height work workers.
5. Only Safety inducted workers should be deploy for the performing the
1) Untrained / Incompetent / Inexperienced worker.
work.
1 Mobilization of manpower 2) Lack of Knowledge.
6. Work related trainings, TBT to be provide before start the work.
3) Unfit worker
7. All workers are known about the work activity.
8. HCCBPL Construction guideline must be followed.
9. Task relevant PPES should be provided and PPES compliance register to be
maintained.
10. Pre task meeting should be proved before start the work activity like
height work training, hot work, fire watcher trainings.
11. Provision of drinking water and other welfare facilities shall be provided.

1.1 Vehicle Valid Licenseand TPI should be available.


1.2 Driver with valid driving license.
1.3 All vehicles entering into site must be in good condition.
1.4 Aware the driver to obey all the traffic rules inside the site.
1.5 Each vehicle enters the site with helper.

1. Unauthorized Vehicle entry 2.1 Flag man should be available.


2. Vehicle accident
Material reaching at site.
2 3. Damage of equipment’s and property 2.2 Wheel Stopper should be inplace both side.
Vehicle Entry.
4.Road 2.3 vehicle must be standing on Even surface.
accident 3.1 Tools and lifting tackles should have TPI.
3.2 Tools and tackles must be varify by Saftey officer.
3.3 Material Should be properly locked.

4.1Logistic plan to be prepared- Routs marked for transport vehicle and flag
man to be appointed for vehicle movement in standard speed 15Kph.

1.1 Tools and lifting tackles should have TPI Certificate.


2.1 Hand tools and power tools should be physically inspected by safety
officer.
1. slip, trip hazards,
3 Arranging tools and tackles 2.2 Tool lanyard must be used
2. Fall of tools
2.3. Must worn all appropriate PPE(s), e.g, safety shoes, helemt, Gloves, HV
Jacket.

1.1. Should take all Necessary work permits to perform this job.( lifting and
shifting work permit).
1.2. Farana, Tools and tackles must be inspected before start the work by the
safety officer.
1.3 Trained/competent person should perform this working activity.
1.4 Lifting tackles and MHE should have valid TPIC and must be inspected
physically before start the work.
2. Team work required when unloading material with proper PPE's to be worn
with shoulder pad.
3.1 . Material handling safety to be followed.
3.2 . Sorrounding area to be free from traffic and person movements.
4. Dedicated supervision to be provided.
1.Fall of Material, material damage 4.2. Always check for load balance, and clear a pathway before movement.
2.Hand cut injury. 5. Area should be barricaded, placed related signages and must not allow any
3.Body Injury. one under the load.
4 Material Unloading by farana (weight)
4.Load Collapse. 5.1. Materail should not be stacked on slope.
5.Hit near structure. 5.2.Maintain proper Space between beside stacking materail. Stack materail
6.Overhead Electrical Power Cables should be stable enough to prevent collapsing.
5.3. At time, surroundings can grow noisy, or a voice may simply not be heard
over distance. Establish hand signals.
5.4. Deploy signal man/flag man to guide the operator.
5.5. provide guide line rope both side of load to guide.
6.1. contact to the authorized person and shutdown the power and applying
LOTO, and give the proper PPE's.
6.2 Consider to all lines to be live and dangerous.
6.3 Always maintaine a safe distance at leat 10 feet from overhead power
lines.
6.4. Display Safety Sinages place at site.
6.5 Lifting plane will be summitted before start the work (weight 500 kg
above).

1. Area must barricaded.


2. Inspect the area immediately around the load and the route for clearance
and tripping hazards.
(Material shifting manually) 3 .Clear movable objects from the route check for uneven terrain clean up
1. Slips, Trips & Falls
5 Check the intended route and point of spills that could affect foot traction.
2. Crush Injury
placement
4. Trained work man shuold perform this job.
5.Use all appropriate PPE(s).
6. should take work permit from concern depot.
1. If load will block your vision, get help.
2.1. Grip the object firmly. Do not pinch object between your thumb and
forefinger. Wear gloves to improve grip.

2.2. Stand close to object, with feet solid and shoulder-width apart. Do not
reach over an obstacle to lift the load. Move whatever is in your way.
2.3. Squat down, bending your knees. Keep your back straight and upright.
1. Crush Injury
2.4. Grip the object firmly and pull it close to you.
6 Performing the Lift by manually 2.Back Injury
2.5. Tighten your abdomen.
3. foot Injury
2.6. Lift with your legs in a gradual and smooth movement. Keep your back
straight. Keep the load close to your body.
2.7. Do not twist your body while lifting.

2.8 Do not lift objects over your head. 3.1.


Use all appropriate PPE(s).
3.2. All activity should be perform under supervisor control.

1. Do not twist. Use your feet to turn your body.


1.Back Injury
2.1. Carry the load as close to your body as possible.
2.Slip & trip
7 Moving the Load by Manually 2.2 one should not lift more than 25 kg weight
3. Fall of Material
3. Keep your back straight & all worker should maintain coordination together
4. foot Injury
while Shifting.

1. Keep your back straight.


2.Tighten your abdomen.
8 Lowering the Load Back Injury(ergonomics issues)
3.Bend at the knees.
4. Keep the load close to your body & follow the Manullay lifting techniques.

1. Working area should be barricaded


2. Trained work man should perform this job
1. Slips, Trips & Falls 3. must be worn all appropriate ppes
2. Crush Injury 4. HOPT should inspect before start the work and maintain check list.
9 Material shifting by help of HOPT
3. load collapse
4. machanical failure 5. Area should clear and maintain good housekeeping
6. Load shall be Tie with reachat belt to avoide load collapse.
7. HOPT TPI certificate should be available at site

1.store heavy and unstable materail as low as possible to the floor. Keep the
assembling conveyor not more than 3 feet, Stacking should not done on
slope. 1.2.
ensure the material tied with rope and use safety shoes while working.

2. Job rotation to be done at some interval of time, carry the load as possiable
1. Foot crush as close to the body twisting,turning,bending of back should be avoided
2. Ergonomical hazards 3.1. Use of hand cut resistance gloves
10 Material stacking by Farana , HOPT 3. Sharp edges,cuts, Freacture
3.2. Proper barricade should be provided, unauthorised person shouldn't
4. Back injury. allowed material stacking area.First aid measures should be available at site.
4.
Always ensure enough manpower to lift material. Job rotation to be done at
some interval of time And refer SOP for safe lifting and handling of material.

5. Farana should have valid TPIC and must be inspected physically before
start the work.

1. Night work permit to be taken from concern engg.and safety dept.


2. Ensure proper illumination during dark hours.
11 Work during dark hours Darkness, fall of person, fall of machinery 3. Electrical cable should lead min 2 m height. No exposed electrical
wire.Earthing.
4. Route shall be illuminated.

1)All necessary appropriate PPE will be used(Helemt, Reflective Jackets,Dust


Mask)
2)Floor should cleard from dust and other debris before the work starts
2)NO vehicle or MHEs movement to be allowed while doing floor marking
work,
3)Ensure proper Supervison is provided,
1)Dust Allergy,
12 Floor marking-Total station & Manual
2)Hit by MHEs
4)Floor should cleard from dust and other debris before the work starts

5)Man and machine to be resitrted at the marking area to avoid any


unnessary incidents
6)By using Thread and ink/Stainer for floor marking

At Finishing
(1). Ensure work area clean from obstacle / waste/wet/equipment.
(2). Ensure all tools & equip. savely in place container.
- Scrach on sharp object (3). Ensure personel avoid pinch point, area hazard potensial slip trip and fall.
13 Housekeeping
-Domestic waste (4). Follow customer waste disposal and management plans
(5). Personnel use PPE properly (Safety Shoes, Body Vest, Gloves, Mask,
Helmet).

1. Keep the emergency exit area free from any obstacles.


2. Emergency lighting should be provided for that area.
Emergency evacuation or exit Slip, Trip or Fall hazards in to the exit way.
3. Workers & employees should be trained with emergency evacuation
14
procedure & exits.
4. In case detect any emergency situation gather in Safe assembly point.
5. emergenct rescue team, kit & equipment to be available at site

Prepared By Reviewed By Reviewed By Reviewed By Reviewed By Reviewed By Reviewe

Contarctor Safety Officer Contractor Site Engineer FABS Engineer FABS EHS Incharge CMC EHS Manager HCCB Project Manger HC
Responsibility

Site Engineer

Site Engineer

Site Engineer

Site Engineer

Site Engineer
Site Engineer

Site Engineer

Site Engineer

Site Engineer

Site Engineer

Site Engineer

Site Enginner

Site Enginner

Reviewed By Reviewed By Reviewed and Approved By

CMC EHS Manager HCCB Project Manger HCCB EHS Manager


PROJECT NAME:HCCB TELANGANA GREEN FIELD

Nature of JOB : Conveyor shifting and Date : 05/12/2023 JSA NO : 197


installation with the help of Farana
Name of the Contractor : System Logistics Location: Banda Timmapur
Name of Safety Officer : Mr. Mohd Rihan Contractor Project Engineer : Mr. Ashwanth Kumar
SL .NO Sequence of Job / Job Steps Potential Hazard Recommended Control Measures Responsibility

1. Trained, competent and experienced workers should be deployed.


2. Ensure competency certificates.
3. Workers above 21 years and below 50 years of age are only allowed for height work
after passing vertigo test.
4. Pre entry medical check - up should be done. Vertigo test to be done for height work
1) Untrained / Incompetent / Inexperienced workers.
worker. 5. Only Safety inducted workers should be deploy for the performing the work.
1 Mobilization of manpower Site Engineer
2) Lack of Knowledge. 6. Work related trainings, TBT to be provide before start the work.
3) Unfit worker 7. All workers are known about the work activity.
8. HCCBPL Construction guideline must be followed.
9. Task relevant PPES should be provided and PPES compliance register to be maintained.
10. Pre task meeting should be proved before start the work activity like height work
training, hot work, fire watcher trainings.
11. Provision of drinking water and other welfare facilities shall be provided.

At Mechanical Installation

1.1. Should take all Necessary work permits to perform this job.( lifting and shifting work
permit).
1.2. Farana, Tools and tackles must be inspected before start the work by the safety
officer.
1.3 Trained/competent person should perform this working activity.
1.4 Lifting tackles and MHE should have valid TPIC and must be inspected physically before
start the work.
2. Team work required when unloading material with proper PPE's to be worn with
shoulder pad.
3.1 . Material handling safety to be followed.
3.2 . Sorrounding area to be free from traffic and person movements.
1. Unsafety Farana and Driver 4. Dedicated supervision to be provided.
2. Material drop 4.2. Always check for load balance, and clear a pathway before movement.
Unloading conveyor and electrical cabinet
3. Struck by farana moving around 5. Area should be barricaded, placed related signages and must not allow any one under
1 (use Farana) Site Engineer
4. Farana overload the load.
Conveyor Weight 350 kg
5. Cut the Slings.( Damage Sling, Kinking, 5.1. Materail should not be stacked on slope.
Heat damage fitting). 5.2.Maintain proper Space between beside stacking materail. Stack materail should be
stable enough to prevent collapsing.
5.3. At time, surroundings can grow noisy, or a voice may simply not be heard over
distance. Establish hand signals.
5.4. Deploy signal man/flag man to guide the operator.
5.5. provide guide line rope both side of load to guide.
6.1. contact to the authorized person and shutdown the power and applying LOTO, and
give the proper PPE's.
6.2 Consider to all lines to be live and dangerous.
6.3 Always maintaine a safe distance at leat 10 feet from overhead power lines.
6.4. Display Safety Sinages place at site.
6.5 Lifting plane will be summitted before start the work (weight 500 kg above).

1. Working area should be barricaded, and housekeeping should be done on daily basis.
2. Trained work man should perform this job.
1. Slips, Trips & Falls 3. must be worn all appropriate ppes
2. Crush Injury 4. HOPT should inspect before start the work and maintain check list.
Material shifting by help of HOPT( Hand 3.
2 Site Engineer
Operated Pallet Truck) load collapse 5. Area should clear and maintain good housekeeping

4. machanical failure 6. Load shall be Tie with reachat belt to avoide load collapse.
7. Ensure load object identified weight capacity and dimension, safety capacity load 75%
(SWL).

Alignment and Marking for conveyor and


3 1.Slip, Trip, Fall, Scratch (1). Personnel use PPE properly and working with awareness Site Engineer
electrical cabinet positioning

1. Conduct daily tool box talk.


2. Trained / Authorizes person for working activity.
3. Issue valid work permit on daily basis.
4. Deployed dedicated supervisor or controller to avoid any unauthorized person entry in
installation area.
5. Area should be barricaded to avoid outside hazard which will affect activity.
6. Area should be clear and free from obstruction. Suffiecent manpower provided for
shifting material from storage area to assemble area.
Installation and Positioning of Conveyors 1.Scrach on sharp object 7. Proper housekeeping to be provided in work location on daily basis.
(Ground level) 2.Material drop 8. Used of job specific PPE.( Safety helmet, goggle(splash), Nose Mask).
4 Site Engineer
using by Farana/HOPT 3.Crushing by material 9. First aid measures shall be available at site.
Weight (300kg to 350 kg) 4.Struck by farana moving around 10. Job related information, instruction and training should be given to all workers prior to
start the job and supervision to be maintained.
11. material lifting shifting techniques training should be given to all workers prior to start
the job.
12. Worker should not work alone there should be standby person available with him and
must be alert during work.
13. Provide HOPT , trolleys or team lifting for heavy loads.
14 .Ensure the working area is clear and free of obstruction to avoid fall & trip while
shifting material in assembly area.
1.1. Pre-use inspection check the driller (brace and bit). Electricity and mechanical.
1.2. Ensure authorize personnel working with competencies experiences
1.3. Personnel use PPE properly and working with awareness
2. Personnel use PPE properly (wear mask properly) and working with awareness
1. Unsafely drilling
3.1.Tools should be check by using checklist properly.
Fastening the conveyor to the installation 2. Splash and dust
5 3.2. Industrial pin tops should be connected to the machine. Site Engineer
surface 3. High turn
3.3. Cables should be free from any joints.
4. Drill cable
3.4. ELCB 30 mA should be provided for the all panel boards.
4.1. Posters should be displayed.Area should be barricaded.
4.2. Job related information, instruction and training should be given to all workers prior to
start the job and supervision to be maintained.

1) Used of job specific PPE.( Safety helmet, goggle(splash), Nose Mask, ear plug).
2.1) Use of splasj goggles and Hand gloves while injecting chemical into Anhoring hole.
2.2) Follow SDS for Diposbale method for empty Cartridges and Diposbale Plan.
2.3) Trained workers should be allowed for Grouting Chemical anchoring work
2.3) Before use the power tools, ensure all the tools using for Grouting is in good
condition.
1) Dust Allergy,
Chemical Anchoring (use by Machines 2.4) Follow Safe work pratice for chemical/Mortar Anchoring and ensure that the empty
6 2) Contact with skin and eyes, Site Engineer
Gun). cartridge are stored in the Specified location/Place
3) Envirnment hazard

2.5) Portable eye washer to be provided at site location.


2.6) Fire point provision at the storage area.
3.1. Spill kit at the storage area, secondary conataminant.
3.2. Material handling procedure to be followed as per SDS

At Electrical Installation and Commissioning (Ground Level).

Construction of cable ducts and conduits 1.1 Only authorised and trained person should be allowed to work.
1 Use portable electric power tools and 1.2. Install Barricade Sign & avoid area potential slip trip and fall & injury.
electrical equipment 1.3 Personnel use PPE properly and working with awareness.
2.1. Proper cable keep neatly
1.1. Sharp Object from edge of Tray and 2.2. Cable tray should making work only competent person.
Conduit 2.3. Should have more frequent checks for items more likely to become damage
2. Slip, Trip, Fall, Sratch 2.4. Close supervision is required.
3. Electrical shock due to plug or connector is 2.5. To implement safety checklist before commencing of work.
Site Enginner
damaged. 3.1. Monthly tagging system to be followed.
4. Use of incorrect power tools 3.2. Only trained and experienced person are allowed
Laying cable and wiring (Main power cable 3.3. Ensure any electrical equipment brought into the workplace by workers, is suitable for
2 is connected to main electrical cabinet by use.
Customer) 3.4. Hand held power tools should be insulated
4.1. Disc/wheel RPM should be more than power tools RPM.
4.2. Face shield/goggle shall be worn while working
4.3. All equipment will be routed through 30 mA RCCB

(1.1). Authorized personnel working competences and all related documents will be
submitted.
(1.2). Personnel use PPE properly and working with awareness.
(1.3). ELCB of 30 mA must be installed on electrical boards.
(1.4). Earthing must be provided.
(1.5). Rubber mat must available working near to DB panel.
(2.1). Authorized personnel working competences.
1.Electrical Shock
(2.2). Always mark your position particularly in blind spots and only move through
Circuit test (Check electrical and 2.Struck by Shuttle and pallets moving
pedestrian areas, if any; in the event of insufficient lighting, use high visibility clothing.
3 mechanical working properly) around Site Engineer
(2.3). Signal any operation faults of sensors to the person in charge of the System Logistics
Testing Automation 3.Risk of entanglement in moving mechanical
worksite and to the Customer’s personnel.
parts
(3.1). Use of pedestrian paths
(3.2). Correct segregation procedure and access prohibited to non-authorised persons near
machines being tested or checked
(3.3) PTW system should be followed.
(3.4) Working area should be barricaded.
(3.5) Provide appropriate signboards.
(3.6) Work should be carried out under the supervision.

At Finishing

(1.1). Ensure work area clean from obstacle / waste/wet/equipment.


(1.2). Ensure all tools & equip. are safely placed in container.
1. Scrach on sharp object (1.3). Ensure personel avoid pinch point, area hazard potential slip trip and fall.
1 Housekeeping Site Enginner
2. Industrial waste (2.1). Follow customer waste disposal and management plans.
(2.2). Personnel use PPE properly (Safety Shoes, Body Vest, Gloves, Mask, Helmet).

1. Keep the emergency exit area free from any obstacles.


Emergency evacuation or exit 1. Slip, Trip or Fall hazards in to the exit way.
2. Emergency lighting should be provided for that area.
1 Site Enginner
3. Workers & employees should be trained with emergency evacuation procedure & exits.
4. In case detect any emergency situation gather in Safe assembly point.

1. Night work permit to be taken from concern engg.and safety dept.


2. Ensure proper illumination during dark hours.
1 Work during dark hours Darkness, fall of person, fall of machinery Site Enginner
3. Electrical cable should lead min 2 m height. No exposed electrical wire.
4. Route shall be illuminated.

Prepared By Reviewed By Reviewed By Reviewed By Reviewed By Reviewed By Reviewed and Approved By

Contarctor Safety Officer Contractor Site Engineer FABS Engineer FABS EHS Incharge CMC EHS Manager HCCB Project Manger HCCB EHS Manager
PROJECT NAME:HCCB TELANGANA GREEN FIELD

Nature of JOB : Fast Rotation System Date : 05/12/2023 JSA NO :


Unloading, shifting and Installation(Use
by Farana and HOPT).
Name of the Contractor : System LogisticsLocation: Banda Timmapur
Name of Safety Officer : Mr. Mohd Rihan Contractor Project Engineer : Mr. Ashwanth Kumar
SL .NO Sequence of Job / Job Steps Potential Hazard Recommended Control Measures Responsibility
1. Trained, competent and experienced workers should be deployed.
2. Ensure competency certificates.
3. Workers above 21 years and below 50 years of age are only allowed for height work after
passing vertigo test.
4. Pre entry medical check - up should be done. Vertigo test to be done for height work
workers.
5. Only Safety inducted workers should be deploy for the performing the work.
6. Work related trainings, TBT to be provide before start the work.
1) Untrained / Incompetent / Inexperienced 7. All workers are known about the work activity.
worker. 8. HCCBPL Construction guideline must be followed.
1 Mobilization of manpower 2) Lack of Knowledge. Site Enginner
9. Task relevant PPES should be provided and PPES compliance register to be maintained.
3) Unfit worker 10. Pre task meeting should be proved before start the work activity like height work
training, hot work, fire watcher trainings.
11. Provision of drinking water and other welfare facilities shall be provided.

1) Allow only valid licence holder operator to operate vehicle.


2) Operator / Driver should be aware about the HCCB and Project Safety Guideline.
3) All necessary documents should be ensure as per HCCB requirement while entering the
1) Untrained / Incompetent / Inexperienced vehicle in the plant.
driver. 4) Alcoholic person strictly prohibited.
Mobile Plant, equipment Movement in 2) Over speeding. 5) Trained Signal Man to be deployed.
2 3) Drink and drive 6) Mobile phone not be allowed to driver or operator while driving. Site Enginner
the plant (Material Vehicle, Farana). 4) Vehicle hit to person or equipment or material. 7) Vehicle mechanical and hydraulic part condition and working to be inspect.
5) Using Mobile phone while driving 8) Job specific PPE's to be provided.
6) Vehicle failure - Mechanical / Hydraulic Failure. 9) Signal man must be assigned only for congested areas and where operator visibility is low.
10) Adhere speed and other traffic rules.
11) Stop vehicle policy for zebra lines and pedestrian cross areas.
12) TP certificates for mobile plant and equipment operator.

At Mechanical Installation

1.1. Should take all Necessary work permits to perform this job.( lifting and shifting work
permit)
1.2. Farana, Tools and tackles must be inspected before start the work by the safety officer.
1.3 Trained/competent person should perform this working activity.
1.4 Lifting tackles and MHE should have valid TPIC and must be inspected physically before
start the work.
2. Team work required when unloading material with proper PPE's to be worn with shoulder
pad.
1.Fall of Material, material damage 3.1 . Material handling safety to be followed.
1. Unloading FRS shuttles and Rails 2.Hand cut injury. 3.2 . Sorrounding area to be free from traffic and person movements.
1 Material. ( Use of Cranes and Farana). 4. Dedicated supervision to be provided. Site Enginner
FRS Shuttels Weight 150 kg. 3.Body Injury. 5. Area should be barricaded, placed related signages and must not allow any one under the
4.Load Collapse. load.
5.Hit near structure. 5.1. Materail should not be stacked on slope.
5.2.Maintain proper Space between beside stacking materail. Stack materail should be stable
enough to prevent collapsing.
6. Deploy signal man/flag man to guide the operator.
6.2.Material handling safety to be followed.
6.3. provide guide line rope both side of load to guide. Lifting plane will be summitted before
start the work (weight 500 kg above). HOPT or Fork lift to be provided while Unloading
material when required.

1.1. Should take all Necessary work permits to perform this job.( lifting and shifting work
permit)
1.2. Farana, Tools and tackles must be inspected before start the work by the safety officer.
1.3 Trained/competent person should perform this working activity.
1.4 Lifting tackles and MHE should have valid TPIC and must be inspected physically before
start the work.
2. Team work required when unloading material with proper PPE's to be worn with shoulder
pad.
3.1 . Material handling safety to be followed.
1.Fall of Material, material damage
Lifting and Insertion of FRS shuttles( use 3.2 . Sorrounding area to be free from traffic and person movements.
2.Hand cut injury.
2 by Farana). 4. Dedicated supervision to be provided. Site Enginner
3.Body Injury.
FRS shuttels Weight 200 kg 5. Area should be barricaded, placed related signages and must not allow any one under the
4.Load Collapse.
load.
5.Hit near structure
5.1. Materail should not be stacked on slope.
5.2.Maintain proper Space between beside stacking materail. Stack materail should be stable
enough to prevent collapsing.
6. Deploy signal man/flag man to guide the operator.
6.2.Material handling safety to be followed.
6.3. provide guide line rope both side of load to guide. Lifting plane will be summitted before
start the work (weight 500 kg above). HOPT or Fork lift to be provided while Unloading
material when required.

(1). Ensure personnel avoid of sharp object area.


(2). Personnel must wear correct PPE properly and working with awareness.
(2.1). Ensure the personnel good comunicate and cooperate.
(3). Personnel use PPE properly and working with awareness.
(1). Ensure the unit installation based on drawing step.
1.Scrach on sharp object (2). Use key / special tools that fit with the machine's needs.
Installation of accessories / supports and 2.Material drop (3). Attention to the pinch point area.
3 electrical components 3.Crushing by material (4). Personnel must wear correct PPE properly and working with awareness Site Enginner
4.Struck by farana moving around (1). Ensure the route operation and procedures.
(2). Ensure object cranes and hoists not over weight or heght and didn’t bloking view
operator.
4.Struck by farana moving around (1). Ensure the route operation and procedures.
(2). Ensure object cranes and hoists not over weight or heght and didn’t bloking view
operator.
(3). Always mark your position particularly in blind spots and only move through pedestrian
areas, if any; in the event of insufficient lighting, use high visibility clothing
(4). Personnel must wear correct PPE properly and working with awareness

At Electrical Installation and Commissioning

1.1 Only authorised and trained person should be allowed to work.


Construction of cable ducts and conduits 1.2. Install Barricade Sign & avoid area potential slip trip and fall & injury.
1 Use portable electric power tools and 1.3 Personnel use PPE properly and working with awareness.
electrical equipment 2.1. Proper cable keep neatly
2.2. Cable tray should making work only competent person.
2.3. Should have more frequent checks for items more likely to become damage
1.1. Sharp Object from edge of Tray and Conduit
2.4. Close supervision is required.
2. Slip, Trip, Fall, Sratch
2.5. To implement safety checklist before commencing of work.
3. Electrical shock due to plug or connector is Site Enginner
3.1. Monthly tagging system to be followed.
damaged.
3.2. Only trained and experienced person are allowed
4. Use of incorrect power tools 3.3. Ensure any electrical equipment brought into the workplace by workers, is suitable for
use.
3.4. Hand held power tools should be insulated
Laying cable and wiring (Main power 4.1. Disc/wheel RPM should be more than power tools RPM.
2 cable is connected to main electrical 4.2. Face shield/goggle shall be worn while working
cabinet by Customer) 4.3. All equipment will be routed through 30 mA RCCB

(1). The cable to Insert cable tray smoothly and avoid the sharp object.
(2). Personnel must wear correct PPE properly and working with awareness.
Circuit test (Check electrical and (3). Authorized personnel working competences.
3 1.Electrical Shock (4). Make sure all connection installations are in accordance with the electrical drawing and Site Enginner
mechanical working properly)
confirmed.
(5). Use the right PPE and tool to carryout your work (Helmet, Work Uniforms, Safety
Glasses, Safety Shoes, Gloves, etc.). Ensure high voltage gloves are ready.

(1.1). Authorized personnel working competences and all related documents will be
submitted.
(1.2). Personnel use PPE properly and working with awareness.
(1.3). ELCB of 30 mA must be installed on electrical boards.
(1.4). Earthing must be provided.
(1.5). Rubber mat must available working near to DB panel.
1.Electrical Shock
(2.1). Authorized personnel working competences.
2.Struck by Shuttle and pallets moving around
4 Testing Automation (2.2). Always mark your position particularly in blind spots and only move through pedestrian Site Enginner
3.Risk of entanglement in moving mechanical areas, if any; in the event of insufficient lighting, use high visibility clothing.
parts
(2.3). Signal any operation faults of sensors to the person in charge of the System Logistics
worksite and to the Customer’s personnel .
(3.1). Use of pedestrian paths
(3.2). Correct segregation procedure and access prohibited to non-authorised persons near
machines being tested or checked

At Finishing

(1). Ensure work area clean from obstacle / waste/wet/equipment.


(2). Ensure all tools & equip. safely placed in the right container.
1. Scrach on sharp object (3). Ensure personel avoid pinch point, area hazard potensial slip, trip and fall.
1 Housekeeping 2. Industrial Waste (4). Follow customer waste disposal and management plans. Site Enginner
(5). Personnel must wear correct PPE properly (Safety Shoes, Body Vest, Gloves, Mask,
Helmet).

1. Keep the emergency exit area free from any obstacles.


Emergency evacuation or exit 1. Slip, Trip or Fall hazards in to the exit way. 2. Emergency lighting should be provided for that area.
2 3. Workers & employees should be trained with emergency evacuation procedure & exits. Site Enginner
4. In case detect any emergency situation gather in Safe assembly point.
5. emergenct rescue team, kit & equipment to be available at site

1. Night work permit to be taken from concern engg.and safety dept.


2. Ensure proper illumination during dark hours.
1 Work during dark hours Darkness, fall of person, fall of machinery 3. Electrical cable should lead min 2 m height. No exposed electrical wire. Site Enginner
4. Route shall be illuminated.

Prepared By Reviewed By Reviewed By Reviewed By Reviewed By Reviewed By Reviewed and Approved By

Contarctor Safety Officer Contractor Site Engineer FABS Engineer FABS EHS Incharge CMC EHS Manager HCCB Project Manger HCCB EHS Manager
PROJECT NAME:HCCB TELANGANA GREEN FIELD

Nature of JOB : Unloading, Lifting and Date : 05/12/2023 JSA NO : 197


Shifting of Elevator with the help of
Farana
Name of the Contractor : System LogisticsLocation: Banda Timmapur
Name of Safety Officer : Mr. Mohd Rihan Contractor Project Engineer : Mr. Ashwanth Kumar
SL .NO Sequence of Job / Job Steps Potential Hazard Recommended Control Measures Responsibility

1. Trained, competent and experienced workers should be deployed.


2. Ensure competency certificates.
3. Workers above 21 years and below 50 years of age are only allowed for height work after passing vertigo test.
4. Pre entry medical check - up should be done. Vertigo test to be done for height work workers.
5. Only Safety inducted workers should be deploy for the performing the work.
1) Untrained / Incompetent / Inexperienced worker.
6. Work related trainings, TBT to be provide before start the work.
1 Mobilization of manpower 2) Lack of Knowledge. Site Enginner
7. All workers are known about the work activity.
3) Unfit worker
8. HCCBPL Construction guideline must be followed.
9. Task relevant PPES should be provided and PPES compliance register to be maintained.
10. Pre task meeting should be proved before start the work activity like height work training, hot work, fire
watcher trainings.
11. Provision of drinking water and other welfare facilities shall be provided.

1) Allow only valid licence holder operator to operate vehicle.


2) Operator / Driver should be aware about the HCCB and Project Safety Guideline.
3) All necessary documents should be ensure as per HCCB requirement while entering the vehicle in the plant.
1) Untrained / Incompetent / Inexperienced driver. 4) Alcoholic person strictly prohibited.
2) Over speeding. 5) Trained Signal Man to be deployed.
Mobile Plant, equipment Movement in 3) Drink and drive 6) Mobile phone not be allowed to driver or operator while driving.
2 Site Enginner
the plant (Material Vehicle, Farana). 4) Vehicle hit to person or equipment or material. 7) Vehicle mechanical and hydraulic part condition and working to be inspect.
5) Using Mobile phone while driving 8) Job specific PPE's to be provided.
6) Vehicle failure - Mechanical / Hydraulic Failure. 9) Signal man must be assigned only for congested areas and where operator visibility is low.
10) Adhere speed and other traffic rules.
11) Stop vehicle policy for zebra lines and pedestrian cross areas.
12) TP certificates for mobile plant and equipment operator.

At Mechanical Installation

(1.1). Pre-start inspection of crane mechnical and electrical integrity, specification and capacity.
(1,2). Only licensed & qualified operator to drive crane.
(1.3). All material must be stored in areas agreed on with the Customer.
(1.4). Ensure the route operation and procedures.
(1.5). Lift the load only to the minimum indispensable height
(1.6). Install baricade for loading and unloading machine.
(1.7). Personnel must wear correct PPE and working with awareness.
1. Unsafely Crane and Driver (2.1). Make sure the machine parts when lifted there is a safety (locked) / tied rope.
Unloading movimentation and lifting
2. Material drop (2.2). During lifting no personnel around the crane.
1 Elevator (use Crane/Farana) Site Enginner
3. Struck by cranes moving around (2.3). Personnel use PPE properly and working with awareness.
Weight 400 kg
4. Crane overload (2.4). Ensure the route operation and procedures.
(2.5). Ensure object forklit and cranes not over weight or heght and didn’t bloking view operator.
(3). Always mark your position particularly in blind spots and only move through pedestrian areas, if any; in the
event of insufficient lighting, use high visibility clothing.
(4.1). Personnel use PPE properly and working with awareness.
(4.2). Pre-use inspection check forklift mechnical electrical integrity, specification and capacity.
(4.3). Ensure Load object Identified weight capacity and dimension, safety capacity load 75%.
(4.4) Lifting plane will be summitted before start the work (weight 500 kg above).

Identifying the position of elevators at (1.1.). Personnel must hi visibility PPE and working with awareness.
2 1. Running over by forklift trucks or other moving vehicle o Site Enginner
the worksite (1.2). Always mark your position particularly in blind spots and only move through pedestrian areas

1.1. Keep the work area tidy • Use PPE to protect lower limbs
3 Checking material at worksite 1. Tripping, falling to the ground, impact against material 1.2 Pre-use inspection check the driller (brace and bit). Electricity and mechanical. Site Enginner
1.3. Correct PPE must be worn to protect lower limbs

(1).Correct PPE must be worn and working with awareness


(2) Vertigo tested workers should be allowed to work at height
Lifting of parts into the position,
(3). Ensure that your footwear is clean and dry before climbing
Mounting and installation tasks(By
4 1. Fall from height, slippery or unstable floor platform /sur (4). Ensure three points of contact at all times while ascending & descending structures i.e. two feet and one Site Enginner
Farana)
hand
Weight (200 -250 kg)
(5). Work within arm’s reach from the structure & never over reach
(6).Wearing harness proprerly , check integrity of supports and PPE

1.1. Should take all Necessary work permits to perform this job.( lifting and shifting work permit)
1.2. Farana, Tools and tackles must be inspected before start the work by the safety officer.
1.3 Trained/competent person should perform this working activity.
1.4 Lifting tackles and MHE should have valid TPIC and must be inspected physically before start the work.
2. Team work required when unloading material with proper PPE's to be worn with shoulder pad.
3.1 . Material handling safety to be followed.
1.Fall of Material, material damage 3.2 . Sorrounding area to be free from traffic and person movements.
Erection of Elevator mast by 2.Hand cut injury. 4. Dedicated supervision to be provided.
5 Site Enginner
Crane/Farana 3.Body Injury. 5. Area should be barricaded, placed related signages and must not allow any one under the load.
4.Load Collapse. 5.1. Materail should not be stacked on slope.
5.Hit near structure. 5.2.Maintain proper Space between beside stacking materail. Stack materail should be stable enough to prevent
collapsing.
6. Deploy signal man/flag man to guide the operator.
6.2.Material handling safety to be followed.
6.3. provide guide line rope both side of load to guide. Lifting plane will be summitted before start the work
(weight 500 kg above). HOPT or Fork lift to be provided while Unloading material when required.
1) Allow only valid licence holder operator to operate vehicle.
2) Operator / Driver should be aware about the HCCB and Project Safety Guideline.
3) All necessary documents should be ensure as per HCCB requirement - Lifting tools and vehicle examination
form, TPI, Insurance.
4) Alcoholic person strictly prohibited.
5) Trained Signal Man to be deployed.
6) Mobile phone not be allowed to driver or operator while driving.
1) Slip, trip
7) Vehicle mechanical and hydraulic part condition and working to be inspect.
2) Sharp edges
8) Before start the work inspect all lifting tools such as D shackles, Bow shackles, Web slings, wire rope slings,
3) Load Hitting to plant facility
crane wire rope, crane hydraulic parts, limit switch, level indicator is in working, siren or horns is working.
4) Fall hazard
Erection of Elevator mast by moble 9) Operator should have a clear view of the road.
6 5) Over Loading Site Enginner
crane/Farana(Tailing Lifting) 11) Ensure the work area or access is even to avoid toppling of crain.
6) Vision block
12) Material should be lift as per shape, size and weight.
7) Lifting tools, Machanical failure
13) Work should be carried out as per the submitted lifting plan / Method statement(above Weight 500 kg).
8) Uncontrolled load, Suspended load
15) Enclosed supervision should be provided.
9) Improper rigging, Improper Signalling
16) Guide rope should be provided.
17) Ensure no one be enter below suspended load.
18) Make sure load should not be suspended for long-time.
19) Area should be barricaded and display appropriate signage.
20) PPE's to be provided - Full Body Safety Harness to be provided while installing lifting tools.
23) Trained riggers should be deploy
24) Proper communication should be maintained between riggers and operator and flagman.

1. must worn all appropriate PPE's like Goggles, Gloves,Steel toe Shoes,Safety Helmet and Safety vest.
1.Fall of person 2. Trained person must access the height by using full body safety harness with double lanyard.
7 Removing of web sling rope/belt Site Enginner
2. Fall of tools equipment 3. FBH must be anchorage at differant place and maintain 3 point contact while removing belt.
4. FBH must be inspected and have valid TPI, maintain record.

1. Ensure inspect the tools and tackels before start the work, and Training should be provided at all.
2.1. Ensure personnel avoid of sharp object area.
2.2. Personnel must wear correct PPE properly and working with awareness.
2.3. Ensure the personnel good comunicate and cooperate.
1. Fall of material and person
3.1. Ensure the unit installation based on drawing step.
2. Scrach on sharp object
8 Accessories mounting 3.2. Use key / special tools that fit with the machine's needs. Site Enginner
3. Crushing by material
3.3. Attention to the pinch point area.
4. Struck by farana moving around
(4). Personnel must wear correct PPE properly and working with awareness
4.1. Ensure the route operation and procedures.
4.2. Ensure object cranes and hoists not over weight or height and didn’t bloking view operator.
4.3. Personnel must wear correct PPE properly and working with awareness

At Finishing

(1.1). Ensure work area clean from obstacle / waste/wet/equipment.


(1.2). Ensure all tools & equip. are safely placed in container.
1. Scratch on sharp object
1 Housekeeping (1.3). Ensure personel avoid pinch point, area hazard potential slip trip and fall. Site Enginner
2. Industrial waste
(2.1). Follow customer waste disposal and management plans.
(2.2). Personnel use PPE properly (Safety Shoes, Body Vest, Gloves, Mask, Helmet).

1. Night work permit to be taken from concern engg.and safety dept.


2. Ensure proper illumination during dark hours.
1 Work during dark hours Darkness, fall of person, fall of machinery Site Enginner
3. Electrical cable should lead min 2 m height. No exposed electrical wire.Earthing.
4. Route shall be illuminated.

1. Keep the emergency exit area free from any obstacles.


2. Emergency lighting should be provided for that area.
Emergency evacuation or exit Slip, Trip or Fall hazards in to the exit way. 3. Workers & employees should be trained with emergency evacuation procedure & exits.
1 4. In case detect any emergency situation gather in Safe assembly point. Site Enginner
5. emergenct rescue team, kit & equipment to be available at site

Prepared By Reviewed By Reviewed By Reviewed By Reviewed By Reviewed By Reviewed and Approved By

Contarctor Safety Officer Contractor Site Engineer FABS Engineer FABS EHS Incharge CMC EHS Manager HCCB Project Manger HCCB EHS Manager
PROJECT NAME:HCCB TELANGANA GREEN FIELD

Nature of JOB : Unloading, Lifting and Shifting of SVL Date : 05/12/2023 JSA NO : 197
and Rail with the help of Farana
Name of the Contractor : System Logistics Location: Banda Timmapur
Name of Safety Officer : Mr. Mohd Rihan Contractor Project Engineer : Mr. Ashwanth kumar
SL .NO Sequence of Job / Job Steps Potential Hazard Recommended Control Measures Responsibility

1. Trained, competent and experienced workers should be deployed.


2. Ensure competency certificates.
3. Workers above 21 years and below 50 years of age are only allowed for height work after passing
vertigo test.
1) Untrained / Incompetent / Inexperienced 4. Pre entry medical check - up should be done. Vertigo test to be done for height work workers.
worker. 5. Only Safety inducted workers should be deploy for the performing the work.
1 Mobilization of manpower 2) Lack of Knowledge. 6. Work related trainings, TBT to be provide before start the work. Site Enginner
3) Unfit worker 7. All workers are known about the work activity.
8. HCCBPL Construction guideline must be followed.
9. Task relevant PPES should be provided and PPES compliance register to be maintained.
10. Pre task meeting should be proved before start the work activity like height work training, hot work,
fire watcher trainings.
11. Provision of drinking water and other welfare facilities shall be provided.

1) Allow only valid licence holder operator to operate vehicle.


2) Operator / Driver should be aware about the HCCB and Project Safety Guideline.
1) Untrained / Incompetent / Inexperienced 3) All necessary documents should be ensure as per HCCB requirement while entering the vehicle in the
driver. plant.
2) Over speeding. 4) Alcoholic person strictly prohibited.
Mobile Plant, equipment Movement in the plant 3) Drink and drive 5) Trained Signal Man to be deployed.
2 (Material Vehicle, Farana). 4) Vehicle hit to person or equipment or 6) Mobile phone not be allowed to driver or operator while driving. Site Enginner
material. 7) Vehicle mechanical and hydraulic part condition and working to be inspect.
5) Using Mobile phone while driving 8) Job specific PPE's to be provided.
6) Vehicle failure - Mechanical / Hydraulic 9) Signal man must be assigned only for congested areas and where operator visibility is low.
Failure. 10) Adhere speed and other traffic rules.
11) Stop vehicle policy for zebra lines and pedestrian cross areas.
12) TP certificates for mobile plant and equipment operator.

At Mechanical Installation

1.1 Pre-use inspection check farana mechnical electrical integrity, specification and capacity.
1.2. Only qualified & licensed driver must operate farana and cranes.
1.3 All material must be stored in areas agreed on with the Customer.
1.4 . Ensure the route operation and procedures.
1.5. Lift the load only to the minimum indispensable height
1.Unsafety Farana Crane and Driver 1.6. Install baricade for loading and unloading machine.
2. Material drop 1.7 Personnel must wear correct PPE properly and working with awareness
1 Unloading SVL Shuttles and Rails Material. ( Use of 3. Struck by moving Farana/Cranes 2.1. Make sure the machine parts when lifted there is a safety (locked) / tied rope. Site Enginner
Cranes and Farana) 4. Farana/Crane overload 2.2. During lifting no personnel should be around the farana.
3.1. Ensure the route operation and procedures.
3.2. Ensure object on Farana or Cranes is not over weight or too high and blocking the view of operator.
3.3. Always mark your position particularly in blind spots and only move through pedestrian areas, if
any; in the event of insufficient lighting, use high visibility clothing
4.1.Pre-start inspection must be completed to check farana and cranes mechnical and electrical
integrity, specification and capacity.
4.2. Ensure Load object Identified weight capacity and dimension, safety working load(SWL) 75%

(1). Personnel must wear PPE properly and working with awareness
1. Slip, Trip, Fall, Scratch (2). Ensure all permit for hot work / Welding activities are in place
2 Installation of Rails 2. Welding , hot work 2.1. Personnel must use proper PPE for the welding operation (Shields, Gloves, etc.) Site Enginner
2.2. Area below and nearby must be properly isolated and access closed/limited.

1. Ensure goggles, Nose mask should be available.


Anchoring -- 1. Dust particles fying into eyes. 2. Using earplugs , nose mask and safety transparent googles during drilling.
Drilling holes into the concrete floor through base plate 2. Noise pollution. 3. Inspect the hammer drill machine before use.
3 using an electric hammer drill machine . 3. Explose to elecrtical energy. 3.2. Inspect power cords for any defects. Site Enginner
Hammer mechanical anchor bolts inside drilled holes and 4. Hand injury, Cut, Burn 4.1. Trained or exprienced work men should perform the activity.
tighten the nut bolts. 5. Electrical Shock 4.2. Personnel must wear PPE properly and working with awareness
5. check for valid inspection tag & checklist for used power tools before use.

1) Used of job specific PPE.( Safety helmet, goggle(splash), Nose Mask(as per N95), ear plug).
2.1) Use of splasj goggles and Hand gloves while injecting chemical into Anhoring hole.
2.2) Follow SDS for Diposbale method for empty Cartridges and Diposbale Plan.
2.3) Trained workers should be allowed for Grouting Chemical anchoring work
1) Dust Allergy, 2.3) Before use the power tools, ensure all the tools using for Grouting is in good condition.
2) Contact with skin and eyes, 2.4) Follow Safe work pratice for chemical/Mortar Anchoring and ensure that the empty cartridge are
4 Chemical Anchoring (use by Machines Gun). stored in the Specified location/Place Site Engineer
3) Envirnment hazard
2.5) Portable eye washer to be provided at site location.
2.6) Fire point provision at the storage area.
3.1. Spill kit at the storage area, secondary conataminant.
3.2. Material handling procedure to be followed as per SDS

(1.1). Ensure personnel avoid of sharp object area.


(1.2). Personnel must wear correct PPE properly and working with awareness.
(2.1). Ensure the personnel good comunicate and cooperate.
1. Scrach on sharp object (2.2) Ensure the Unit stand straight.
Installation of accessories / supports and electrical 2. Material drop (3.1). Ensure the unit installation based on drawing step.
5 components 3. Crushing by material (3.2). Use key / special tools that fit with the machine's needs. Site Enginner
4. Struck by farana moving around (3.3). Attention to the pinch point area.
(4.1). Ensure the route operation and procedures.
(4.2). Ensure object cranes and hoists not over weight or heght and didn’t blocking view operator.
(4.3). Always mark your position particularly in blind spots and only move through pedestrian areas, if
any; in the event of insufficient lighting, use high visibility clothing

(1). Pre-use inspection check lifing equipment mechnical electrical integrity, specification and capacity.
(2). Only qualified & licensed driver must operate forklift and cranes.
(3). All material must be stored in areas agreed on with the Customer
6 Lifting and Insertion of SVL shuttles 1. Unsafely Farana, Crane and electrical/Mechani(4). Ensure the route operation and procedures. Site Enginner
(5). Lift the load only to the minimum indispensable height
(6). Install baricade for loading and unloading machine.
(7). Personnel must wear correct PPE properly and working with awareness

At Electrical Installation and Commissioning


Construction of cable ducts and conduits 1.1 Only authorised and trained person should be allowed to work.
1 Use portable electric power tools and electrical 1.2. Install Barricade Sign & avoid area potential slip trip and fall & injury.
equipment 1.3 Personnel use PPE properly and working with awareness.
2.1. Proper cable keep neatly
2.2. Cable tray should making work only competent person.
1.1. Sharp Object from edge of Tray and Conduit 2.3. Should have more frequent checks for items more likely to become damage
2. Slip, Trip, Fall, Sratch 2.4. Close supervision is required.
3. Electrical shock due to plug or connector is 2.5. To implement safety checklist before commencing of work. Site Enginner
damaged. 3.1. Monthly tagging system to be followed.
4. Use of incorrect power tools 3.2. Only trained and experienced person are allowed
3.3. Ensure any electrical equipment brought into the workplace by workers, is suitable for use.
3.4. Hand held power tools should be insulated
Laying cable and wiring (Main power cable is connected 4.1. Disc/wheel RPM should be more than power tools RPM.
2 to main electrical cabinet by Customer) 4.2. Face shield/goggle shall be worn while working
4.3. All equipment will be routed through 30 mA RCCB

1.Ensure that proper safety gears is used. These include safety shoes,helmet,rubber electrical gloves,
rubber mat, fire extinguisher.
2.Person should be well experienced who is doing the work.
3.Do the LOTO procedure to the incoming supply panel by only authorized person.
4.Proper illumination should be provided at work place.
5.Keep the first aid box near to the work place.
1. Live Circuit 6. Employee should be trained with safe electrical working procedure.
3 Circuit test (Check electrical and mechanical working prope2. Electrical Shock 7.Proper ground earthing should be provided to the overall electrical equipment. Site Enginner
8.Work should be done under continuous supervision.
9.Before starting any test, make the proper plan including a circuit diagram for the test.
10.Be very care fully while using certain test equipment’s like meggers,earth tester, multimeter.
11. When the working with unfamiliar equipment read the operating manual carefully before starting
the work.
12.Ensure that the electrical work permit is taken from authorized person for the work.

(1.1). Authorized personnel working competences and all related documents will be submitted.
(1.2). Personnel use PPE properly and working with awareness.
(1.3). ELCB of 30 mA must be installed on electrical boards.
(1.4). Earthing must be provided.
(1.5). Rubber mat must available working near to DB panel.
(2.1). Authorized personnel working competences.
1. Electrical Shock (2.2). Always mark your position particularly in blind spots and only move through pedestrian areas, if
2. Struck by Shuttle and pallets moving around any; in the event of insufficient lighting, use high visibility clothing.
4 Testing automatic mission 3. Risk of entanglement in moving mechanical (2.3). Signal any operation faults of sensors to the person in charge of the System Logistics worksite and Site Enginner
parts to the Customer’s personnel .
(3.1). Use of pedestrian paths
(3.2). Correct segregation procedure and access prohibited to non-authorised persons near machines
being tested or checked
(3.3) PTW system should be followed.
(3.4) Working area should be barricaded.
(3.5) Provide appropriate signboards.
(3.6) Work should be carried out under the supervision.

At Finishing

1. Ensure work area clean from obstacle / waste/wet/equipment.


1. Scrach on sharp object 2.1 Ensure all tools & equip. safely placed in the right container.
1 Housekeeping 2. Industrial waste 2.2 Ensure personel avoid pinch point, area hazard potensial slip, trip and fall Site Enginner
2.3 Follow customer waste disposal and management plans
2.4 Personnel must wear correct PPE properly (Safety Shoes, Body Vest, Gloves, Mask, Helmet).

1. Keep the emergency exit area free from any obstacles.


Emergency evacuation or exit Slip, Trip or Fall hazards in to the exit way. 2. Emergency lighting should be provided for that area.
1 3. Workers & employees should be trained with emergency evacuation procedure & exits. Site Enginner
4. In case detect any emergency situation gather in Safe assembly point.
5. emergenct rescue team, kit & equipment to be available at site

1. Night work permit to be taken from concern engg.and safety dept.


1 Work during dark hours Darkness, fall of person, fall of machinery 2. Ensure proper illumination during dark hours. Site Enginner
3. Electrical cable should lead min 2 m height. No exposed electrical wire.
4. Route shall be illuminated.

Prepared By Reviewed By Reviewed By Reviewed By Reviewed By Reviewed By Reviewed and Approved By

Contarctor Safety Officer Contractor Site Engineer FABS Engineer FABS EHS incharge CMC EHS Manager HCCB Project Manger HCCB EHS Manager