LPS-01 PROJECT
Area
LPS-01 Date 06.03.2024 Time 08.00 PM
Location
Completed by Mark Signature
Items to be checked
1 Safety Plans 7 Waste Controls 13 Holes and Voids x 19 Lifting Plant and Lifting Gear
2 Registers and Records 8 Fire and Gases/Hot work x 14 Working at height x 20 Site Storage
Immediat
observed that operatives were training on safe work at height
2 Days
4 Days
performing work at height activity must be conducted to the
e
unsafely, they were following operatives.
unsafe methods.
√
Found that scaffolding without Ensure that scaffoldigs are
x Immediate Immediate
2 Days
4 Days
inspection tag at Level-6,zone-B. inspected by a competent
2 scaffolding inspector prior to use.
Observed that floor opening was not Ensure floor openings are
2 Days
4 Days
protected at Level-6. properly coverd by rigid
3 plywoods with signages.
Observations Closeouts
At Level-4,zone-D, it has been observed that Activity put on hold, refresh training on safe work
operatives were performing work at height at height must be conducted to the operatives.
activity unsafely, they were following unsafe
methods.
Found that scaffolding without inspection tag at Ensure that scaffoldigs are inspected by a
Level-6,zone-B. competent scaffolding inspector prior to use.
Observed that floor opening was not protected at Ensure floor openings are properly coverd by rigid
Level-6. plywoods with signages.