You are on page 1of 18

Cusson Emilie

Karim Ali
La Caserne Chanzy CE1

Loko Thérésia Reims


Saint-Maxent Victor
Tate Youness

Stakeholders and challenges of the construction project

1. Introduction - History of the building and the project...........................................................2


2. Previous building condition......................................................................................................3
3. Program of the rehabilitation................................................................................................... 4
4. Stakeholders............................................................................................................................... 5
5. Document of the contract - List................................................................................................6
6. Main drawings - Definition of the project............................................................................... 7
7. BOQ............................................................................................................................................8
8. Schedule......................................................................................................................................9
9. Risk Assessment.......................................................................................................................10
10. Health and Safety...................................................................................................................11
11. Annexe....................................................................................................................................12

1
1. Introduction - History of the building and the
project

La caserne de Chanzy was built in 1926 in an Art deco style. It has been a hostel since 2019.

Site construction in 1926 Specific design of the fire station

Old facade Street view of the ancient fire station

2
2. Previous building condition

This explains how the building was before


the rehabilitation project.

Plan of the interior Drawing of the different levels

View of the exterior Drawing of the facade

3
3. Program of the rehabilitation
The program is what the owner expects. The owner of this project expects to give a new life to
an old fire station. The building will gather all of the departments of the City and the
Agglomeration’s services and a hotel.

4
5
4. Stakeholders
The stakeholders are the individuals, groups or organisations that affect or can be affected by
the project. The stakeholders for the Caserne de Chanzy are :

6
5. Document of the contract - List

(a) The contract agreement

(b) The letter of acceptance

(c) The letter of tender

(d) The particular conditions

(e) The general conditions

(f) The specification

(g) The drawings

(h) The schedule and other documents forming parts of the contract

7
6. Main drawings - Definition of the project
The following pictures are architectural drawings showing the building above.

Details about heating, ventilating and Details about low voltage and high voltage
air-conditioning installations

Structures made of reinforced concrete;


generally column, beams, slabs and walls

8
7. BOQ

The project manager’s budget is close to 10% of the total cost.

9
10
11
8. Schedule

We managed to present a short schedule of the project with the GANTT application. The main
activities are:
- Site installation
- Demolition
- Foundations
- Structure
- Etancheite
- Roof
- Facade renovation
- External cladding (bardage)
- Exterior carpentry
- Walls
- False ceiling
- Interior carpentry
- Floor coverings
- Painting
- Sanitary
- Heating - ventilation (HVAC)
- Electricity

12
9. Risk Assessment

Risk N° Risks Potential Impact Probability %

1 Pandemic 5 5%

2 War in France 5 5%

3 Construction cost exceeding the 2 40%


budget

4 Fire 5 10%

5 Injury of workers 3 20%

6 Flood 5 15%

7 Bad weather 3 50%

8 Ressources delivery delay 2 40%

9 Social Movements 4 35%

10 Error in the delivery 4 15%

13
10. Health and Safety
The following pictures show the measures taken in order to ensure workers’ health and security.

PPE (EPI)

Protection measures on trenches

14
Protection measures on buildings

Protection measures on buildings

Safety railings

15
11. Annexe

16
17
18