SPRAYING PRIME COAT

1.0 PURPOSE

This purpose is to define and establish the method statement to be used for
construction of flexible pavement such as Spraying Prime Coat.

2.0 SCOPE

To provide clear instruction for construction, of flexible pavement.

2.1 The work shall be performed in accordance with the horizontal alignments,
surface levels.
2.2 The longitudinal regularity of the surfaces shall be carried out as shown on
drawing and specification.

3.0 REFERENCES

JKR Spec. ( C L : 4.2.1 )


Standard Drawing

4.0 DEFINITION

-Nil-

5.0 RESPONSIBILITIES

5.1 Project Manager.

 Ensure that method statement comply with client requirement.


 Submit method statement to client/SO for approval;

5.2 Deputy Project Manager / Section or Site Engineer

 Monitor implementation of this method statement and ensure quality of


works comply with the specified requirements;
 Co-ordinate with laboratory testing/consultant if required;

5.3 Machine Operators.

 Carry out crushed aggregate compaction using the motor grader / vibratory
roller;
 Follow site engineer/ supervisor instruction;

Version 1.A 01-April-02 Page 1 of 3


S_04 ECET-03
SPRAYING PRIME COAT

6.0 MATERIALS

6.1 The approved Prime Coat ( SS1-K ).


6.2 Approval prime coat from plant shall deliverd to site .
6.3 Material shall conform with JKR specification.

7.0 EQUIPMENT’S

7.1 Power Broom;


7.2 Compressed Air Blower;
7.3 Pressure Distributor for Bituminous Material;
7.4 Vibrating Compactor;

8.0 SAFETY CONDITION

Refer to Safety Booklet

9.0 ACTIVITY PROCESS

9.1 Method of working for subbase preparation.

9.1.1 Work shall commence on site upon approval and acceptance of the
roadbase.

9.1.2 The subbase shall be leveled and compacted by using vibratory roller
after compaction of any specified roadbase in pavement area.

9.1.3 Verification of the roadbase compaction shall be carried out using sand
replacement method or other method deemed suitable by the engineer.

9.2 Constructional Operation

9.2.1 Works shall commence on site upon approval and acceptance of the
roadbase layer.

9.2.2 The surface to receive the Prime Coat (SS1-K) shall be free from all
loose material and standing water.

9.2.3 The approval Prime Coat (SS1-K) will be sprayed by Bitumen Emulsion
self-propelled.

9.2.4 The rate for spreading the Prime Coat shall be 0.8 to1.2 liters/m²

Version 1.A 01-April-02 Page 2 of 3


S_04 ECET-03
SPRAYING PRIME COAT

9.3 Field Control

9.3.1 These shall be carried out assess and determine the rate of spread.

9.3.2 A tray will be put at middle of the area to be sprayed.

9.3.3 A tray will be weighed and measured before spraying.

9.3.4 After spraying the weight of the tray and the prime coat will be
determined.

9.3.5 Hence the rate of the spread will be determine as follows :-

( Prime coat + tray ) – ( tray )


Rate of spread = --------------------------------------------------
Density of prime coat x area of tray

9.4 Constructional Plan

One (1) unit of Bitumen Emulsion Self -Propelled Hand Operated Distrubutor.

10.0 QUALITY RECORD

 Request for Inspection ( RFI )


 Laboratory Test Report – If any required
 Survey Record
 Quality Verification Checklist (QVC)
 Daily reports

11.0 MANPOWER

 Site Engineer/Supervisor 01
 Plant Operator 01
 Laborers 02

Version 1.A 01-April-02 Page 3 of 3