Professional Documents
Culture Documents
c
Materials and Labour e
LOT 31 Proposed Lagos Homes
m Projects
Schedule
e
n
ITEM DISCRIPTION MATERIALS QTY ###TOTAL QTY UNIT RATE Materials AMT Labour AMT R C St
A Setting out Peges }
Profile } 30,000.00
Sum 50,000.00
Nails }
Twine }
Excavation 155,000.00
FILLG 1598
LGH31 Page 1 of 34
o
r
Materials and Labour c
LOT 31 Proposed Lagos Homes
e Projects
Schedule
m
TOTAL GROUNDBEAM CONCRETE 2,770,436.15 231,000.00 e
n
ITEM DISCRIPTION MATERIALS QTY ###TOTAL QTY UNIT RATE Materials AMT Labour AMT R C St
CONRETE SLAB
150-300th. G.flr
slab (1:2:4)
6.08/0.139/0.219 85
Cement 516.80### 542.6 bags 3,900.00 2,116,296.00 ###
###
Concrete 212,500.00
85mc Sand 59.08### 62.0 Ton 3,250.00 201,593.44
LGH31 Page 2 of 34
n
f
Materials and Labour o
LOT 31 Proposed Lagos Homes
r Projects
Schedule
c
e
m
CONCRETE ROOF COLOMNS & BEAM 978,718.70 91,000.00 e
n
ITEM DISCRIPTION MATERIALS QTY ###TOTAL QTY UNIT RATE Materials AMT Labour AMT R C St
CONCRETE STAIRCASE
Stair case (1:2:4)
6.08/0.139/0.219 13
Cement 79.04### 83.0 bags 3,900.00 323,668.80 ###
###
Concrete 32,500.00
13mc Sand 9.04### 9.5 Ton 3,250.00 30,831.94
760,118.95 192,500.00
LGH31 Page 3 of 34
ei
n
Materials and Labour f
LOT 31 Proposed Lagos Homes
o Projects
Schedule
r
c
e
m
TOTAL SUB-STRUCTURE REINFORCEMENT 5,996,437.50 240,975.00 e
n
ITEM DISCRIPTION MATERIALS QTY ###TOTAL QTY UNIT RATE Materials AMT Labour AMT R C St
FRAME STRUCTURE(REIFORCEMENT)
Beam,Clm, Slab
Reinforcement
8.5 y20 8.5 ### 8.9 t 445,000.0 3,971,625.00 ###
LGH31 Page 4 of 34
R
Materials and Labour ei
LOT 31 Proposed Lagos Homes
n Projects
Schedule
f
o
r
c
e
m
TOTAL LITEL REINFORCEMENT 941,000.00 42,000.00 e
n
ITEM DISCRIPTION MATERIALS QTY ###TOTAL QTY UNIT RATE Materials AMT Labour AMT R C St
FORMWORK(BELOW GROUND LEVEL)
G.Beam,Clm,Slab
Form work
715 25x300x3600 715.00### 750.8 Nr 1,850.00 1,388,887.50 ###
357,500.00
376.31578947368 50x75x3600 376.32### 395.1 Nr 650.00 256,835.53
wire
TOTAL G.BEAM,COLUMN,SLAB FORM WORK 1,708,723.03 357,500.00
FORMWORK(FRAME STRUCTURE)
Form work
1765 25x300x3600 1,765.0### 1853.3 1,850.00 3,428,512.50 ###
1,235,500.00
928.95 50x75x3600 928.9### 975.4 650.00 634,006.58
LGH31 Page 5 of 34
Materials and Labour LOT 31 Proposed Lagos Homes
R Projects
Schedule
ei
n
Nail 1.0 sum 9,000.00 9,000.00
f
o
wire 0.5 sum 13,000.00 6,500.00 r
c
e
m
TOTAL (STAIRCASE) FORMWORK 360,756.58 105,000.00 e
n
ITEM DISCRIPTION MATERIALS QTY ###TOTAL QTY UNIT RATE Materials AMT Labour AMT R C St
FORMWORK(LINTEL)
Form work
243 25x300x3600 243.00### 255.2 1,850.00 472,027.50
170,100.00
127.89473684211 50x75x3600 127.89### 134.3 650.00 87,288.16
LGH31 Page 6 of 34
Materials and Labour LOT 31 Proposed Lagos Homes Projects
Schedule
R
57 25x300ridg 17.27### 18.1 2,000.00 36,272.73 ei
n
26 25x300hip 7.88### 8.3 2,000.00 16,545.45
f
57 25x300valley 17.27### 18.1 2,000.00 36,272.73 o
Treatment sum 50,000.00 r
c
Nails 4.0 sum 9,000.00 36,000.00 e
m
WOOD WORK 1,148,997.73 300,000.00 e
n
ITEM DISCRIPTION MATERIALS QTY ###TOTAL QTY UNIT RATE Materials AMT Labour AMT R C St
DOOR
Akala doors 1200x2100mm 8.0 75,000.00 600,000.00 24,000.00
with frame
900x2100mm 36 55,000.00 1,980,000.00 72,000.00
750x2100mm 32 45,000.00 1,440,000.00 64,000.00
WOODEN DOORS 4,020,000.00 160,000.00
Steel doors
1800x2100mm 1.0 150,000.0 150,000.00 3,000.00
1200x2100mm 1.0 110,000.0 110,000.00 3,000.00
900x2100mm 21.0 65,000.00 1,365,000.00 42,000.00
LGH31 Page 7 of 34
Materials and Labour LOT 31 Proposed Lagos Homes Projects
Schedule
902ms
Cement 150.00### 157.5 bg 3,900.00 614,250.00 ###
### R
ei
Sand 15.01### 15.8 ton 4,750.00 74,875.34 568,260.00 n
f
o
Tiles 902.00### 947.1 ms 2,000.00 1,894,200.00 r
c
e
m
WALL FINISHINGS 5,328,695.64 1,623,510.00 e
n
ITEM DISCRIPTION MATERIALS QTY ###TOTAL QTY UNIT RATE Materials AMT Labour AMT R C St
CEILING FINISHINGS
(15mmth)
rendering(1:4) 13
846ms ###
###
Cement 130.00### 136.5 bg 3,900.00 532,350.00
STAIRCASE19mmth 2
plan (1:3)back Cement 25.00### 26.3 bg 3,900.00 102,375.00 ###
###
2 mc
Sand 7.52### 7.9 ton 4,750.00 37,503.01 41,580.00
LGH31 Page 8 of 34
Materials and Labour LOT 31 Proposed Lagos Homes Projects
Schedule
LGH31 Page 9 of 34
Materials and Labour LOT 31 Proposed Lagos Homes Projects
Schedule
LGH31 Page 10 of 34
Materials and Labour Proposed
Schedule
ITEM DISCRIPTION MATERIALS QTY ###TOTAL QTY UNIT RATE Materials AMT Labour AMT
A Setting out Peges }
Profile } 30,000.00
Sum 50000.0
Nails }
Twine }
Excavation 40,920.00
FILLG 131
225th. G.beam
(1:2:4)
6.08/0.139/0.219 58
Cement 352.64### 370.3 bags 3,800.00 1407033.6
Concrete 174,000.00
Sand 40.31### 42.3 Ton 4,600.00 194697.3
58mc
Granite 63.51### 66.7 T 7,000.00 466798.5
150-300th. G.flr
slab (1:2:4)
6.08/0.139/0.2
19 10
Cement 60.80### 63.8 bags 3,800.00 242592.0
Concrete 25,000.00
10CM Sand 6.95### 7.3 Ton 4,600.00 33568.5
300th. Columns
(1:2:4)
6.08/0.139/0.2
19 4
Cement 24.32### 25.5 bags 3,800.00 97036.8
Concrete 12,000.00
4CM Sand 2.78### 2.9 Ton 4,600.00 13427.4
roof clm,Bm,
slab (1:2:4)
6.08/0.139/0.2
19 59
Cement 358.72### 376.7 bags 3,800.00 1431292.8
Concrete 206,500.00
59 Sand 41.01### 43.1 Ton 4,600.00 198054.2
59CM
Granite 64.60### 67.8 Ton 7,000.00 474846.8
Lintel (1:2:4)
6.08/0.139/0.2
19 7
Cement 42.56### 44.7 bags 3,800.00 169814.4
Concrete 192,500.00
7CM Sand 4.87### 5.1 Ton 4,600.00 23498.0
259,650.1
G beam,Clm, Slab
Reinforcement
Y25 0 ### 0.0 420,000.00 0.0
FRAME STRUCTURE(REIFORCEMENT)
Beam,Clm, Slab
Reinforcement
Y25 ### 0.0 420,000.0 0.0
Lintel
Reinforcement
Y25 0 ### 0.0 420,000.0 0.0
Nail
wire
FORMWORK(FRAME STRUCTURE)
Form work
374 25x300x3600 374.0### 392.7 1,100.00 431970.0
261,800.0
710.00 50x75x3600 710.0### 745.5 450.00 335475.0
FORMWORK(STAIRCASE)
Form work
32 25x300x3600 32.00### 33.6 1,100.00 36960.0
22,400.00
16.8421052632 50x75x3600 16.84### 17.7 450.00 7957.9
FORMWORK(LINTEL)
Form work
88 25x300x3600 88.00### 92.4 1,100.00 101640.0
61,600.00
46.3157894737 50x75x3600 46.32### 48.6 450.00 21884.2
Aluminium 0.55
396 Covering 440.00### 462.0 sm 2,000.00 880,000.0
Carccasing
100x75wall
117 plate 35.45### 37.2 Nr 950.00 35,365.9
150x50
296 Tiebeam 89.70### 94.2 Nr 1,300.00 122,436.4
DOOR
Tunkish doors 1200x2400mm 2.0 210,000.00 420,000.0 60,000.00
with frame
Chinize door 900x2400mm 18 45,000.00 810,000.0 72,000.00
with frame
750x2400mm 10 45,000.00 450,000.0 40,000.00
Sliding doors
2100x2150mm 2.0 70,000.0 140,000.0 8,000.00
WINDOWS
FINISHINGS (INTERNAL)
FLOOR42mmth 30
plan (1:3) Cement 375.00### 393.8 bg 2,700.00 1063125.0
30cm
Sand 112.79### 118.4 ton 3,500.00 414506.9 109,515.00
CEILING FINISHINGS
(15mmth)
rendering(1:4) 3
193
Cement 30.00### 31.5 bg 2,700.00 85050.0
POP
221 ceiling 221.00### 232.1 boundle 5,000.00 1160250.0 510,510.00
CEILING FINISHINGS 1,289,639.2 806,610.0
STAIRCASE19mm 6
plan (1:3)back Cement 75.00### 78.8 bg 2,700.00 212625.0
3
6 Sand 22.56### 23.7 ton 3,500.00 82901.4 41,580.00
EXTERNAL FINISHINGS
WALL 15mmth
plan (1:4) Cement - ### 0.0 bg 2,700.00 0.0
WALL &CEILING
PAINTING WORK
1599 Emulsion 436.09### 22.9 bg 7,500.00 171710.8
319,800.00
Texcote - ### 0.0 bg 7,500.00 0.0
N 21,991,449.7
179.5
0.0
0.0
3.3
1.2
4.1
0.0
2.5
1.1
6.8
0.0
0.0
1.3
0.0
0.6
0.0
0.0
0.0
0.0
0.9
0.0
0.0
0.0
0.0
0.0
0.0
288.8 116.6
392.7 35.50
217.4 114.4
33.6 17.7
108.6 99.9
393.8 118.4
220.5 88.7
52.5 5.3
31.5 12.7
78.8 23.7
0.0 0.0
38,368,703.5